Financial setbacks beset Slovakia’s highway development

Slovakian highway company NDS says that construction of the 13km Turany-Hubova highway may not be started in 2012. The previous Transport Ministry plan was to call the tender for this stretch in summer 2012. However, the EC has not yet approved the construction of this highway, with questions surrounding the protected area in the Velka and Mala Fatra mountains. If Slovakia does not get this approval, the country might have to chose the second option, which includes the tunnel Korbelka. The EC's decision is
June 12, 2012 Read time: 2 mins
Slovakian highway company NDS says that construction of the 13km Turany-Hubova highway may not be started in 2012.

The previous Transport Ministry plan was to call the tender for this stretch in summer 2012. However, the EC has not yet approved the construction of this highway, with questions surrounding the protected area in the Velka and Mala Fatra mountains. If Slovakia does not get this approval, the country might have to chose the second option, which includes the tunnel Korbelka. The EC's decision is expected to be made by late 2012 or early 2013. Meanwhile work on the Visnove tunnel project depends on a loan from the 1054 European Investment Bank (EIB), as Slovakia does not have the money required. Should the EIB approve a loan, construction of the section of the D1 highway with the Visnove tunnel could start in 2012. The Transport Ministry has said that funding from the EIB could be used as a bridging loan because the ministry's current plans are for using EU funds only in the 2014-2020 budgetary period.

The value of the project is €900 million. The sum provided by the EIB will depend on the Transport Ministry's updated highway construction strategy. And should the Turany-Hubova section of the D1 motorway is built as a public-private partnership, the EIB and the 1166 European Bank for Reconstruction and Development (EBRD) may participate. This would require all problems with environment protection to be solved for funding to be approved. At this stage it not possible to say when the whole D1 highway will be completed but it could be in 2018-2019 or even later.

For more information on companies in this article

Related Content

  • Germany builds its first major PPI autobahn project
    July 7, 2015
    Rebuilding of one of the oldest motorways in Germany is testing out the possibilities for public-private project road construction reports Adrian Greeman A freshly renovated section of the A8 Autobahn in southern Germany will be watched with some interest this summer as traffic begins driving along its rebuilt carriageway and additional third lanes. That is not because of any special road features, other than a distinctive reddish colour to its concrete surface, but because it is a first fullscale public
  • PPRS event highlights transport investment shortfall
    April 30, 2015
    The PPRS event in Paris highlighted the need for additional investment in road transportation – David Arminas writes. Consider the global road network. An improved road from one rural African town to another can reduce the journey time from a one-day walk to a one-hour drive. This could save lives through access to a hospital; allow small businesses to work faster by getting in supplies more quickly; allow children to attend a better equipped school. Roads affect society by allowing healthier and bett
  • Corridor for prosperity: The 5G Road
    June 14, 2019
    The next generation of highways will be a matrix of smart, intelligent and dynamic technologies that lower maintenance costs and ensure user safety. But challenges lie ahead, as Geoff Hadwick discovered in Dubrovnik The fifth-generation road is about to provide the world’s highway authorities with a big leap forward. This “forever-open”, self-healing road will integrate innovation into infrastructure, vehicles and entire intelligent transport systems, says Adewole Adesiyun, deputy secretary general of
  • Albanian PM promises new road infrastructure project cash
    September 11, 2012
    Albanian primeminister, Sali Berisha, has promised that his government will keep up its investment in road infrastructure projects, due to their importance to the economy. The PM was speaking at the launch of two new road sections, between Uzina e Autotraktoreve and Lanabregas, and the Bridge of Surrelit to Farka. Both of the sections were built using funding from the EBRD and the EIB, with some funding also being provided by the Albanian government.