Financial close for Louisiana’s Calcasieu Bridge

Sacyr said that the project is the company’s first transportation infrastructure private-public partnership contract in the US and calls for a total of $2.27 billion in construction investment.
By David Arminas August 19, 2024 Read time: 2 mins
The project length is around 9.6km and includes interstate roadways, bridge approaches, I-10 frontage roads and several interchanges (image courtesy Louisiana Department of Transportation and Development)

Sacyr and its partners have reached financial close on the I-10 Calcasieu River Bridge project in the US state of Louisiana for US$1.33 billion.

Sacyr said that the project is the company’s first transportation infrastructure P3 - private-public partnership - deal in the US and calls for a total of $2.27 billion in construction investment.

Calcasieu Bridge Partners, comprising Madrid-based Sacyr, Acciona and Plenary Americas, will design, build, operate and maintain the I-10 Calcasieu River Bridge for 50 years. The 9km-long section of the I-10 in which the bridge stand connects the towns of Lake Charles and Westlake. Work will include replacement of the existing bridge which is more than 70 years old.

The project has both public and private funding with the state of Louisiana contributing almost $1.2 billion during construction to be paid in line with construction milestones being completed during the work.

Construction is expected to start later this year for completion in 2031. The road section is expected to accommodate an average daily traffic volume of 90,000 vehicles by 2040.

The I-10 Calcasieu River Bridge project is the largest in the history of the state’s department of transportation and development and was one of the largest infrastructure contracts commissioned in North America in 2023.

The project corridor includes the Calcasieu River Bridge that connects the cities of Lake Charles and Westlake. The project length is around 9.6km and includes interstate roadways, bridge approaches, I-10 frontage roads and several interchanges that connect the interstate to state and local roads. Meanwhile, I-10 widening includes construction of a corridor with six lanes and implementation of free-flow tolling, together with various structures, ramps and approaches to the new elevated structure.

The existing 2km-long 16m-wide Calcasieu River Bridge was officially called the Louisiana Memorial World War II Bridge when it was opened in 1951. It has decorative iron work with crossed guns integrated into the railings. The I-10 Bridge was originally built as the U.S. Highway 90 bridge and later was grandfathered into Interstate 10. The structure is an arched cantilever, rivet-connected Warren through truss for the main span. The longest span is 128.3m and the bridge at its highest point in the arch has a 41m vertical clearance of the river.

For an short aerial video of the existing bridge, click here, for the official I-10 Calcasieu Mobility Partners website.

For more information on companies in this article

Related Content

  • Ayesa secures contract on Panama Canal bridge project
    November 25, 2019
    Spanish engineering firm Ayesa has been awarded a US$4.7 million contract to be the independent engineer for reviewing construction of the fourth Panama canal bridge.
  • Chiloé island highway proposal
    March 17, 2025
    A new highway is proposed for Chile’s Chiloé island.
  • Rapid replacement of multiple bridges – the plan
    December 14, 2017
    The US State of Pennsylvania is saving itself $220 million over 10 years on a programme to replace 558 bridges with an unusual public private partnership approach - Kristina Smith writes It is called the Rapid Bridge Replacement Programme with good reason. Pennsylvania’s Department of Transport, PennDOT, wants to see no less than 558 structurally deficient bridges replaced with newly designed and constructed ones, all within four years. Using traditional forms of procurement this programme would be like
  • Pocitelj Bridge reaches banks of Neretva River
    August 21, 2023
    Contractors are working to correct a concrete issue on a section of the 100m-long continuous prestressed girder bridge across the Neretva River in Bosnia and Herzegovina.