Fehmarn Belt tunnel work to start in January

Construction of the large-scale tunnel element factory at Rødbyhavn can now start soon.
By David Arminas April 29, 2020 Read time: 3 mins
Rødbyhavn work harbour will be one of Denmark’s largest factories (image copyright Fermen A/S)

Construction of the immersed Fehmarn Belt road and rail tunnel between Denmark and Germany will start in January 2021, according to the project owner Femern.

The planned 18km tunnel under the Baltic Sea, between the Danish island of Lolland and the German island of Fehmarn, received approval from the European Commission last month. However, Germany still needs to give its final approval which is expected this autumn.

Dutch construction company BAM will receive a quarter of the €3.4 billion (US$3.92 billion) spent on a contract for the tunnel construction. Meanwhile, Dutch dredging companies Boskalis and Van Oord will receive €300 million each for the dredging of the tunnel. The tunnel is expected to be opened to traffic in 2029, according to a report in the Dutch newspaper Der Telegraaf.

Femern is in charge of planning and providing the basis for regulatory approval of the project on behalf of the Danish government. The framework for this work falls under a treaty between Denmark and Germany which was signed in 2008.

Femern said it is “activating the main construction contracts” with Dutch contractors’ consortium Femern Link Contractors from January 1, 2021.

“This means that construction of the large-scale tunnel element factory at Rødbyhavn can get underway,” according to a posting on Femern’s website. The work harbour is the gateway to the construction of the tunnel element factory, which will be will be one of the biggest factories in Denmark. From here the 73,000-tonne tunnel elements will be shipped out to the Fehmarnbelt – the strait between Fehmarn and Lolland.

Femern also said that it is already engaged in a number of construction site preparations for the tunnel on the German side at Puttgarden so that further progress can be made when Germany gives formal approval of the project.

A Rambøll-Arup-TEC consultancy joint venture is engaged in a client consultancy services contract with Femern.

The Fehmarnbelt link will be user-financed. Revenues from the link will go to repay the loans that finance construction; the same model that financed the Storebælt and Øresund links. Denmark’s Parliament will decide the tolls and the operator Femern has said that there likely will be discounts such as weekend tickets, as is the case on the Øresund and Storebælt links.

Meanwhile, due to the spread of the COVID-19 virus, organisers of the Fehmarnbelt Days 2020 festival conference postponed the event that was to have taken place May 17. The Fehmarnbelt Days Secretariat said that an alternative date will be announced shortly. Since 2012 the Fehmarnbelt Days have dealt with key areas such as infrastructure, tourism, business, the labour market, transport and logistics as well as education and research.

For more information on companies in this article

Related Content

  • Denmark's Jutland bridge options
    February 29, 2012
    Cost concerns have entered the discussion arena for Denmark's proposed bridge linking the islands of Jutland and Funen.
  • VIDEO: Virginia approves Hampton Roads Bridge Tunnel expansion
    December 12, 2016
    The US state of Virginia has approved a US$4 billion project to expand the Hampton Roads Bridge Tunnel close to the city of Norfolk.

    The state has been looking at designs for the past 20 years to improve traffic flow in the area, according to a report in the Virginian-Pilot newspaper. Hampton Roads is a body of water making up one of the world's largest natural harbours. The existing structure is close to the US Navy's Atlantic Fleet home base at Norfolk.
  • Penang’s PAN 1 project to go ahead amid environmental concerns
    April 17, 2019
    Malaysia’s Penang state has approved the PAN 1 Highway project but with conditions attached following an environmental impact study. Work could start next year on the 19.5km project – officially called the Pan Island Link 1 - that will likely cost around US$1.7 billion, according to a report in the newspaper Sundaily. The project will consist of 7.6km of viaducts, four tunnel sections totalling 10.1km in length and embankment sections totalling 1.8km. Penang Island, around 300km², is the main islan
  • Tyne tunnel's water quality checks
    February 6, 2012
    Five buoy-mounted automatic water quality monitors (AWQMs) have been installed by YSI Hydrodata engineers at the new Tyne Tunnel project in north-east England. The equipment on the second vehicle tunnel under the River Tyne, currently one of the UK's largest construction projects, aims to ensure that construction operations do not significantly affect river water quality. Unusually, the contractors have not taken ownership of the instrumentation, preferring instead to simply purchase the data and alarms. Th