Environmentally friendly demolition of famous US Bay Bridge to take years

While the new eastern span of northern California’s Bay Bridge between San Francisco and Oakland will open to traffic this September, the task of taking down the old eastern bridge span roadway is likely to take years. Speaking to a local TV station Brad McCrea, regulatory director of the Bay Conservation and Development Commission, the state agency that oversees protection of the Bay Area, said: “Taking the old Bay Bridge [eastern span roadway] down is as practically as big a project as putting the new one
March 18, 2013 Read time: 2 mins
While the new eastern span of northern California’s Bay Bridge between San Francisco and Oakland will open to traffic this September, the task of taking down the old eastern bridge span roadway is likely to take years.

Speaking to local TV station KPIX 5 Brad McCrea, regulatory director of the Bay Conservation and Development Commission, the state agency that oversees protection of the Bay Area, said: “Taking the old Bay Bridge [eastern span roadway] down is as practically as big a project as putting the new one up.”

Environmental restrictions mean the existing structure will have to be carefully taken apart in sections, in the reverse order that it was originally built.

“They have great documentation about how this old structure was built in the 1930s. So they will use the architectural drawings from the 30s, they’ll use all of the photographs they have from the 30s, and they’ll use that as a road map to un-doing what was done 75 years ago,” explained McCrea in his TV interview.

The new eastern span of the Bay Bridge, a near 3km long continuation of the Bay Bridge crossing, will run on from a small island in the middle of the bay where the two suspension bridges of the western half make landfall. The route passes through this Yerba Buena Island, in a short tunnel.  A new single-span single-tower suspension bridge, with a 385m main span, is the centrepiece of the new eastern Bay Bridge span. It will cross the main east side shipping channel close to Yerba and its adjoining Treasure Island naval base, carrying five lanes of traffic each way. The road continues on the long curving Skyway concrete viaduct for the following 2.1km. A final touch down section takes motorists on to Oakland.

The US$6.3 billion renewal of the eastern Bay Bridge is seen as a long-term solution to renowned seismic activity in the area.

Related Content

  • Rader Hochbrücke construction set for summer
    April 7, 2025
    Work on the Rader Hochbrücke (bridge) near Rendsburg, Germany, will start this summer and take five years, according to DEGES.
  • Contracts are about to be signed for the Fehmarnbelt Fixed Link
    March 13, 2015
    Nearly eight years after Denmark and Germany agreed to construct a major undersea road and rail tunnel, the first contracts are about to be signed. David Arminas reports. Construction is due to start later this year on one of Europe’s most ambitious, as well as the world’s longest, road and rail tunnels, the 17.6km Fehmarnbelt Fixed Link between Germany and Denmark. Fehmarnbelt is expected to cost around US$7.5 billion and be five times the length of the Øresund tunnel between the Danish capital Copenhagen
  • Contracts are about to be signed for the Fehmarnbelt Fixed Link
    March 13, 2015
    Nearly eight years after Denmark and Germany agreed to construct a major undersea road and rail tunnel, the first contracts are about to be signed. David Arminas reports. Construction is due to start later this year on one of Europe’s most ambitious, as well as the world’s longest, road and rail tunnels, the 17.6km Fehmarnbelt Fixed Link between Germany and Denmark. Fehmarnbelt is expected to cost around US$7.5 billion and be five times the length of the Øresund tunnel between the Danish capital Copenhagen
  • Bolivia’s new highway
    October 10, 2017
    Bolivia’s new highway will provide better access into mountain areas – Mauro Nogarin writes At the beginning of 2015, work began on the construction and paving for the Tupiza - Atocha - Uyuni highway project. The route is located in Bolivia’s Potosí department: it is 189m in length and forms part of the Southwest Basic Road Network (RVF) of Bolivia.