Delays for Czech highways

THE NEW highway network currently being built in the Czech Republic will be completed in 2025, five years later than the original planned completion date of 2020. The country’s Transport Ministry has said that €19.55 billion will be needed to extend the total length of the network from the current 1,113km to 2,153km. However,it has pointed out that a new system of funding will be required or there will be a shortfall to pay for the plans by 2020.Various options are being considered at present with bond issu
May 30, 2012 Read time: 2 mins
THE NEW highway network currently being built in the Czech Republic will be completed in 2025, five years later than the original planned completion date of 2020. The country’s Transport Ministry has said that €19.55 billion will be needed to extend the total length of the network from the current 1,113km to 2,153km. However,it has pointed out that a new system of funding will be required or there will be a shortfall to pay for the plans by 2020.

Various options are being considered at present with bond issues and PPPs in the frame. The Transport Ministry has said that high priority link roads suitable for the PPP projects include the R35 linking Hradec Kralove with Olomouc;the Prague ring road; the D3 linking Prague with Ceske Budejovice, the I/11 from Nosovice to the border with Slovakia, and the reconstruction of the D1 highway. Meanwhile, an environmental report on the Prerov-Breclav dual carriageway suggests that building two tunnels (6.8km long and 1.6km long) underneath a bird habitat will be less environmentally damaging than other options.

The Transport and Environmental Ministries are in favour of the tunnels although there are questions over estimated €510 million cost of this option. Another option that avoids the bird habitat entirely would be 7km longer and be slightly more expensive.

Related Content

  • Kenya rehabilitates, widens, tolls Northern Corridor
    November 8, 2017
    A massive highway project in Kenya will boost transport for the country as well as its neighbours - Shem Oirere reports. Kenya has commenced the process of rehabilitating, expanding and tolling of 657km of East Africa’s Northern Corridor that is anchored on the Indian Ocean port of Mombasa and which links the gateway with landlocked countries of Uganda, Rwanda, Burundi and parts of eastern Democratic Republic of Congo (DRC).
  • Slovakia to use €4bn EU funding on roads
    March 14, 2014
    Slovakia plans to use €4 billion of its €15.3 billion EU funding package for 2014-2020 on road projects. The projects include the construction of several new stretches of the D1 and D3 motorways, as well as repairs and modernisations of Class II and Class III roads. The government in cooperation with the regions are currently drafting a strategic plan for the development and maintenance of roads at a regional level.
  • Peruvian road project paperwork delay
    May 12, 2021
    Paperwork problems have caused delays to a Peruvian road project.
  • Delays to highway, tunnel and bridge building
    May 14, 2012
    The Slovakian government is being asked for financial compensation by Granvia, the group building the country’s new Nitra-Banska Bystrica highway. Granvia is building the highway under the PPP model through a 30-year concession deal. The compensation has been requested due to delays that have been caused by the need for archaeological investigations along the route.