Delays for Czech highways

THE NEW highway network currently being built in the Czech Republic will be completed in 2025, five years later than the original planned completion date of 2020. The country’s Transport Ministry has said that €19.55 billion will be needed to extend the total length of the network from the current 1,113km to 2,153km. However,it has pointed out that a new system of funding will be required or there will be a shortfall to pay for the plans by 2020.Various options are being considered at present with bond issu
May 30, 2012 Read time: 2 mins
THE NEW highway network currently being built in the Czech Republic will be completed in 2025, five years later than the original planned completion date of 2020. The country’s Transport Ministry has said that €19.55 billion will be needed to extend the total length of the network from the current 1,113km to 2,153km. However,it has pointed out that a new system of funding will be required or there will be a shortfall to pay for the plans by 2020.

Various options are being considered at present with bond issues and PPPs in the frame. The Transport Ministry has said that high priority link roads suitable for the PPP projects include the R35 linking Hradec Kralove with Olomouc;the Prague ring road; the D3 linking Prague with Ceske Budejovice, the I/11 from Nosovice to the border with Slovakia, and the reconstruction of the D1 highway. Meanwhile, an environmental report on the Prerov-Breclav dual carriageway suggests that building two tunnels (6.8km long and 1.6km long) underneath a bird habitat will be less environmentally damaging than other options.

The Transport and Environmental Ministries are in favour of the tunnels although there are questions over estimated €510 million cost of this option. Another option that avoids the bird habitat entirely would be 7km longer and be slightly more expensive.

Related Content

  • Boring complete for Slovakian tunnel project
    November 30, 2022
    Tunnel boring is now complete for a major Slovakian tunnel project.
  • Lincoln bypass project in the UK approved
    April 15, 2022
    The Lincoln bypass project in the UK has been approved.
  • Terex TA300 blazes trail for new stretch of D11 Czech motorway
    March 12, 2018
    Workers on a stretch of the Czech Republic’s D11 motorway have found a friend in the Terex TA300 28tonne articulated dump truck. Czech-based company ATM CZ has a two-year contract to extend the 90km D11 by 15.5km; no easy task, from earthwork to compaction and paving. The road connects the Czech capital Prague and the city of Hradec Králové. Once the project is complete, the motorway will continue to Smiřicemi. The motorway is part of European route E67 – the so-called Via Baltica – from Prague to the Fin
  • Czech road project now underway
    October 12, 2018
    Construction work is underway on stretch of the D11 highway connecting Hradec Kralove and Smirice in the northern Czech Republic. The work is being carried out by a construction consortium comprising contractors Eurovia, Metrostav and Swietelsky. However, the start of the work for the 15.5km highway section was delayed and its completion is timed for 2022. The project is costing €100.5 million and includes a number of engineering challenges due to the complexity of the terrain. In all the work will include