Delayed ring road due for completion

In Romania, modernisation of capital Bucharest’s ring road is now due for completion in 2012. The delay has been caused by a lack of funds. Upgrading of the sections between DN7 and DN1A and DN1A (Mogosoaia)and DN1 (Otopeni) started in 2007 and some 51km have been improved so far. The total length of the ring road will be 71km when it is complete. Tenders still have to be launched for two more sections of the ring road, the 11km DN2/A2 stretch and the 8.6km A1/DN7 section. Financing for these last section
May 15, 2012 Read time: 2 mins
In Romania, modernisation of capital Bucharest’s ring road is now due for completion in 2012. The delay has been caused by a lack of funds.

Upgrading of the sections between DN7 and DN1A and DN1A (Mogosoaia)and DN1 (Otopeni) started in 2007 and some 51km have been improved so far. The total length of the ring road will be 71km when it is complete.

Tenders still have to be launched for two more sections of the ring road, the 11km DN2/A2 stretch and the 8.6km A1/DN7 section. Financing for these last sections will be provided in part by a €50 million loan from the 1054 European Investment Bank, which is expected to cover around 50% of the costs.

Meanwhile the 1207 SEARCH Corporation is now working on a feasibility study for the construction of Targu Mures-Ditrau highway. Search was contracted by the National Highways and Roads Company.

For more information on companies in this article

Related Content

  • Contractor bankruptcy delays Romanian road project
    July 26, 2013
    The recent bankruptcy of the Austrian contractor Alpine Bau has affected a number of key projects across Europe in countries including Norway, Poland and now Romania. Following Alpine Bau’s bankruptcy, Romania’s national roads authority, CNADNR, cancelled the Austrian contractor’s contract to build a section of highway from Nadlac-Arad. So far, Alpine Bau has been paid €69.5 million to build a 16.6km section of the highway and around 85% of the work has been completed. It is not clear at this stage how the
  • Tenders coming for Nowe Miasto Lubawskie ring road second phase
    September 9, 2016
    The Polish government has approved construction of the second phase of the ring road around Nowe Miasto Lubawskie. A deal is expected to be signed at the beginning of next year to complete the 18km road.
  • EIB backing Irish motorway link
    April 30, 2014
    The European Investment Bank (EIB) is providing financial backing worth €144 million for the new M17/M18 Gort-Tuam motorway project. The M17/M18 Gort to Tuam PPP Scheme is situated in the west of Ireland and will be constructed as a four lane motorway that will replace the existing N17/N18 roads. This new motorway will reduce journey times by around 20 minutes and has an overall cost estimated at €550 million. Construction work will start during this year and this is the second transport PPP to be signed un
  • India rushing to improve its highway system
    February 9, 2012
    Despite the world economic slowdown, India still seems in a rush to improve its highway system as Patrick Smith reports. Later this year India will be seen by hundreds of millions worldwide when the country's capital New Delhi hosts its biggest event ever.