Delayed ring road due for completion

In Romania, modernisation of capital Bucharest’s ring road is now due for completion in 2012. The delay has been caused by a lack of funds. Upgrading of the sections between DN7 and DN1A and DN1A (Mogosoaia)and DN1 (Otopeni) started in 2007 and some 51km have been improved so far. The total length of the ring road will be 71km when it is complete. Tenders still have to be launched for two more sections of the ring road, the 11km DN2/A2 stretch and the 8.6km A1/DN7 section. Financing for these last section
May 15, 2012 Read time: 2 mins
In Romania, modernisation of capital Bucharest’s ring road is now due for completion in 2012. The delay has been caused by a lack of funds.

Upgrading of the sections between DN7 and DN1A and DN1A (Mogosoaia)and DN1 (Otopeni) started in 2007 and some 51km have been improved so far. The total length of the ring road will be 71km when it is complete.

Tenders still have to be launched for two more sections of the ring road, the 11km DN2/A2 stretch and the 8.6km A1/DN7 section. Financing for these last sections will be provided in part by a €50 million loan from the 1054 European Investment Bank, which is expected to cover around 50% of the costs.

Meanwhile the 1207 SEARCH Corporation is now working on a feasibility study for the construction of Targu Mures-Ditrau highway. Search was contracted by the National Highways and Roads Company.

For more information on companies in this article

Related Content

  • Construction underway on Italian highways with more planned
    August 8, 2012
    Two key highway projects in Italy are exhibiting good progress at present. Construction work on the new Brescia-Milan highway link is now more than 50% complete. The bridges crossing the Serio, Adda and Oglio rivers are 84% complete, while the underpasses and drainage is 49% ready. Service stations, surveying and foundation work is 40% complete while the remaining operations are 227% ready. Italian road construction firm Brebemi believes that the highway be will be complete and open to traffic by 31 Decembe
  • Tunisia's road strategy
    March 1, 2012
    A technical study worth US$5.9 million (€4 million) is starting for Tunisia's Kairouan-Enfidha highway.
  • Italian highway projects advancing
    December 17, 2012
    Two key highway projects in Italy are exhibiting good progress at present. Construction work on the new Brescia-Milan highway link is now more than 50% complete. The bridges crossing the Serio, Adda and Oglio rivers are 84% complete, while the underpasses and drainage is 49% ready. Service stations, surveying and foundation work is 40% complete while the remaining operations are progressing. Italian road construction firm Brebemi believes that the highway be will be complete and open to traffic by 31 Decemb
  • EBRD funding for St Petersburg project?
    April 27, 2012
    The European Bank for Reconstruction and Development (EBRD) intends to provide a US$277 million (€200 million) loan to the Northern Capital Highway consortium, which will build the central 11.5km section of St Petersburg’s Western High Speed Diameter (WHSD) route. The EBRD’s board of directors has said will consider the loan on 14th February 2012. The finance package is of note as Russian road projects have largely found funds from other sources so far. The Northern Capital Highway consortium estimates the