D11 motorway in Czech Republic could be completed after over 17 year land dispute

A land dispute that has stalled the completion of the D11 motorway in the Czech Republic for more than 17 years is reportedly nearing its end. The Czech road management firm RSD has applied for planning permission to build the D11 between Prague and Hradec Kralove omitting the disputed land. But it’s reported that the Transport Ministry is looking to come to an agreement with the owner of the last outstanding bit of land on the originally proposed D11 route, which will allow the preferred route to be comple
March 6, 2013 Read time: 2 mins
A land dispute that has stalled the completion of the D11 motorway in the Czech Republic for more than 17 years is reportedly nearing its end.

The Czech road management firm RSD has applied for planning permission to build the D11 between Prague and Hradec Kralove omitting the disputed land.

But it’s reported that the Transport Ministry is looking to come to an agreement with the owner of the last outstanding bit of land on the originally proposed D11 route, which will allow the preferred route to be completed.

The construction of the D11 motorway connecting Prague, Hradec Kralove and the Polish borders started in 1978, and is estimated to cost a total of around CZK 34bn (US$1.73bn). The 85km section to Hradec Kralove, worth an estimated CZK 1.5bn, is currently in use, but the 70km section to the Polish borders is awaiting completion.

Related Content

  • First part of Hradec-Smirice D11 gets planning permission
    June 12, 2017
    The Czech Transport Ministry has issued a planning permission for the first part of the planned D11 motorway construction for the 15.5km long section Hradec Kralove-Smirice which is expected to cost nearly €247 million.
  • Czech tenders for section of D11, part of the E67 Via Baltica
    July 15, 2016
    The Czech road management company RSD is seeking a contractor for construction of 15km of the D11 motorway between Hradec Kralove and Smirice. Both towns are in northern Czech Republic, near the Polish border. The work is worth around €218.3 million, according to Czech media, and is one of the last remaining sections of the D11 to be built. Construction of another section between the town of Trutnov and the border with Poland is likely to start in 2019 and the Jaromer-Trutnov section after 2020.
  • Czech Republic: permit for D11 section moving ahead
    October 25, 2019
    The Czech highway authority has applied for permits to start work on a 41km stretch of the D11 motorway, from Prague to the border with Poland at a cost of around €853 million. Last year a consortium comprising contractors Eurovia, Metrostav and Swietelsky began work on a stretch of the D11 connecting Hradec Kralove and Smirice in the north of the country with completion of the €100.5 million project in 2022. The D11 motorway connecting Prague and Hradec Králové began in 1978. It is part of European r
  • Czech Republic: RSD gives go-ahead to road contracts worth €966mn
    September 30, 2013
    The Czech road and motorway management company RSD has given permission to construction firms to begin road building projects worth over €966 million (CZK 25 billion). The projects originate from the years 2008 to 2010, when expensive contracts were signed after only two subjects having taken part in tenders. The top three most expensive projects include the R49 road between Hulin and Frystak worth €302.26 million (CZK 7.8 billion), the motorway section D11 Osicky-Hradec Kralove worth €144.15 million (CZ