Cranes coming down on Gordie Howe Bridge

The Gordie Howe International Bridge will route traffic away from more populated areas and directly connect Highway 401 in the Canadian province of Ontario with the Interstate 75 in the US state of Michigan.
By David Arminas June 30, 2025 Read time: 3 mins
Throughout construction of the CAN$6.4 billion bridge, the two tower cranes lifted heavy materials such as rebar, formwork, anchor boxes and all 216 stay cables (image courtesy of WDBA)

After five years, the second of two tower cranes on either side of the Gordie Howe International Bridge across the Detroit River is coming down.

The complete dismantling of the second crane, on the US end of the bridge, is expected in the next several weeks. A 600-tonne crawler crane that is fitted with a 165m-long boom is assisting in the work. An identical crane on the Canadian side was dismantled in May.

According to the Windsor-Detroit Bridge Authority, the cranes arrived on site in 2020 in an assembly process that took 35 hours over three days. They climbed in height throughout construction to keep up with the growing bridge towers in a process known as “tower crane self-climbing”. With the bridge towers reaching their full heights of 220m last year, the tower cranes, too, hit their final heights of 243m.

Throughout construction of the CAN$6.4 billion bridge, the tower cranes were used to lift heavy materials such as rebar, formwork, anchor boxes and all 216 stay cables.

Meanwhile, work continues on installation of electrical, drainage and fire suppression systems as well as barriers, signage, lighting pavement markings and the completion of a multi-use path.

The bridge is named after Gordie Howe, a professional Canadian ice hockey player who played most of his National Hockey League career with the Detroit Red Wings.

Last summer, the 26m gap was closed between the two deck of the bridge that will connect city of Detroit in the US state of Michigan and the city of Windsor in the Canadian province of Ontario. The bridge is expected to open to traffic by the end of this year. It will also include a one-lane 2.5km-long multi-use path that will accommodate two-way pedestrian and cyclist traffic and connect into existing local trail networks on both sides of the border.

The 853m main bridge deck between the two towers makes it the longest main span of any cable-stayed bridge in North America and the tenth longest in the world. Clearance above the river is 42m. It will also be the longest composite steel and concrete bridge deck for any cable-stayed bridge in the world.

The Windsor-Detroit Bridge Authority is a not-for-profit corporation wholly owned by the government of Canada  which is paying for the entire project through a public-private partnership. WDBA is responsible for the delivery of the Bridge and also responsible for project oversight of the construction and the operation of the new crossing. As the operator of the new bridge, WDBA will set and collect all tolls.

Related Content

  • Indeco cuts up New York City’s old Kosciuszko Bridge
    November 23, 2017
    An Indeco ISS 45/90 is proving essential for demolishing the old Kosciuszko Bridge in New York City. New York City’s old 1.9km Kosciuszko Bridge, which crosses Newtown Creek connecting Green Point, Brooklyn with Maspeth, Queens, has been out of service since April. By the end of the year, the polygonal Warren through-truss structure will be no more. To replace the old bridge, in 2009, the New York State Department of Transportation planned the construction of two cable-stayed replacement bridges.
  • Champlain Bridge set to open by end of year, says SNC-Lavalin
    March 6, 2018
    The replacement Champlain Bridge in Montreal will open on schedule at the end of the year, according to the SNC-Lavalin-led consortium heading the project. Cost of the entire corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments. Failure to open the bridge to vehicular traffic on time means the consortium faces stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $31
  • Norway considers wooden bridge across Lake Mjosa
    May 12, 2017
    Norway could be home to the world’s longest wooden bridge if the government gives the go-ahead for a span across Lake Mjosa. In a new report, researchers conclude that it is possible, both technically and economically, to build a 1.7km wooden bridge between the towns Biri and Moelv. Importantly, the report notes that construction cost differences between a wooden and concrete structure would be little. Estimates for a wooden bridge are around €420 million while for a concrete structure would come in about €
  • New York tunnels upgrade complete
    June 9, 2022
    Upgrade work is complete for New York’s key tunnel links.