Cranes coming down on Gordie Howe Bridge

The Gordie Howe International Bridge will route traffic away from more populated areas and directly connect Highway 401 in the Canadian province of Ontario with the Interstate 75 in the US state of Michigan.
By David Arminas June 30, 2025 Read time: 3 mins
Throughout construction of the CAN$6.4 billion bridge, the two tower cranes lifted heavy materials such as rebar, formwork, anchor boxes and all 216 stay cables (image courtesy of WDBA)

After five years, the second of two tower cranes on either side of the Gordie Howe International Bridge across the Detroit River is coming down.

The complete dismantling of the second crane, on the US end of the bridge, is expected in the next several weeks. A 600-tonne crawler crane that is fitted with a 165m-long boom is assisting in the work. An identical crane on the Canadian side was dismantled in May.

According to the Windsor-Detroit Bridge Authority, the cranes arrived on site in 2020 in an assembly process that took 35 hours over three days. They climbed in height throughout construction to keep up with the growing bridge towers in a process known as “tower crane self-climbing”. With the bridge towers reaching their full heights of 220m last year, the tower cranes, too, hit their final heights of 243m.

Throughout construction of the CAN$6.4 billion bridge, the tower cranes were used to lift heavy materials such as rebar, formwork, anchor boxes and all 216 stay cables.

Meanwhile, work continues on installation of electrical, drainage and fire suppression systems as well as barriers, signage, lighting pavement markings and the completion of a multi-use path.

The bridge is named after Gordie Howe, a professional Canadian ice hockey player who played most of his National Hockey League career with the Detroit Red Wings.

Last summer, the 26m gap was closed between the two deck of the bridge that will connect city of Detroit in the US state of Michigan and the city of Windsor in the Canadian province of Ontario. The bridge is expected to open to traffic by the end of this year. It will also include a one-lane 2.5km-long multi-use path that will accommodate two-way pedestrian and cyclist traffic and connect into existing local trail networks on both sides of the border.

The 853m main bridge deck between the two towers makes it the longest main span of any cable-stayed bridge in North America and the tenth longest in the world. Clearance above the river is 42m. It will also be the longest composite steel and concrete bridge deck for any cable-stayed bridge in the world.

The Windsor-Detroit Bridge Authority is a not-for-profit corporation wholly owned by the government of Canada  which is paying for the entire project through a public-private partnership. WDBA is responsible for the delivery of the Bridge and also responsible for project oversight of the construction and the operation of the new crossing. As the operator of the new bridge, WDBA will set and collect all tolls.

Related Content

  • Contracts for $1.9 billion Francis Scott Key bridge
    February 27, 2025
    Key contracts have been awarded for the $1.9 billion Francis Scott Key bridge.
  • Winning formula for formwork
    July 19, 2012
    An unusual application of formwork took place recently in France, while formwork using one particular engineering construction kit was used for the first time in Poland. Guy Woodford reports An 80m long wild game underpass is an innovative feature of the Route Nationale 88 (RN 88) expansion in south-west France. For construction of the arched underpass tunnel, a PERI tunnel formwork carriage using VARIOKIT engineering construction kit was used. Thanks to the equipment’s easy handling, along with pre-assembl
  • Iowa-Wisconsin bridge link demolition
    July 23, 2025
    A historic Iowa-Wisconsin bridge link will be demolished.
  • Project underway for Chinese bridge
    May 15, 2014
    Potain tower cranes are being used to construct a major cable-stayed bridge in China. The conditions are tough and feature high winds and monsoon conditions, with the cranes working at an altitude of 1,500m above sea level in a mountain range in southern China to build the Duge Beipanjiang Bridge, which will span 720m when it is complete The job is requiring six Potain tower cranes in total during the course of the US$92.75 million (570 million RMB) project. Two cranes have been erected at the job site a