Cofferdams completed for Sunderland city’s New Wear River Crossing

In the UK, foundation work for Sunderland city’s new bridge is about to start as the huge cofferdam in the middle of the River Wear nears completion. Water has been drained out of the cofferdam, a large steel watertight structure within the river, to allow the building of pylons for the bridge deck. It is the first bridge to be built over the Wear in Sunderland for more than 40 years and is part of the wider strategic transport plan to link the Port of Sunderland and city centre with the A19 road.
May 25, 2016 Read time: 2 mins
Cofferdam construction to allow work on main pylon foundations
In the UK, foundation work for Sunderland city’s new bridge is about to start as the huge cofferdam in the middle of the River Wear nears completion.

Water has been drained out of the cofferdam, a large steel watertight structure within the river, to allow the building of pylons for the bridge deck.

It is the first bridge to be built over the Wear in Sunderland for more than 40 years and is part of the wider strategic transport plan to link the Port of Sunderland and city centre with the A19 road.

Before the end of the year, a 105m A-frame pylon will be floated from Belgium on a giant barge before being slowly hoisted into position on the river. It will take several hours to raise the pylon and secure it.

Stephen McCaffrey, project director for FVB joint venture, created by 1622 Farrans Construction and Victor Buyck Steel Construction, said the positioning of the pylon will be “a very complex project” and “not straightforward”.

Farrans Construction is a building and civil engineering contractor across the UK and Ireland. Victor Buyck is based in Belgium and specialises in major structural steelwork, especially steel bridges. The FVB joint venture is supported by their design team led by Buro Happold Engineering and Roughan & O'Donovan.

Sunderland City Council is holding a two-phase consultation to find a name for the new bridge.

For more information on companies in this article

Related Content

  • Controversial Russian bridge opens
    August 10, 2018
    The first stage of a controversial Russian bridge project is now complete, with the link having been opened to use by cars and buses. The Kerch Strait bridge spans the Black Sea, connecting Russia’s Taman Peninsula in Krasnodar with Crimea, the latter having been controversially annexed by Russia from Ukraine in 2014. The official opening of the 19km-long bridge was carried out by Russia’s president, Vladimir Putin, who drove across the link in a Russian-manufactured Kamaz truck to reach the city of Kerch.
  • We can be Heroes
    January 11, 2023
    Paraguay’s Puente Héroes del Chaco will provide a vital transport link for the country once it is complete, Mauro Nogarin and Mike Woof report
  • Giving four hours back to the day… and much more
    October 7, 2019
    A 20km long elevated expressway in Dhaka will be one of Bangladesh’s first Public Private Partnership transport projects – words and pictures by Ruby Kitching, on behalf of Mott MacDonald.
  • Clever approach to reducing bridge vibrations
    November 14, 2013
    Reducing vibrations on a bridge, supplying high-quality binders to emerging countries and helping small and medium players with warm mix, this month’s stories showcase some innovative bitumen technology solutions - Kristina Smith reports The Kessock Bridge in the Highlands of Scotland has become the third bridge in the UK to be resurfaced with Gussasphalt. A dense mastic asphalt containing Nynas Endura N5, a polymer modified binder, Gussasphalt has been designed to have a longer life than standard mastic as