Cofferdams completed for Sunderland city’s New Wear River Crossing

In the UK, foundation work for Sunderland city’s new bridge is about to start as the huge cofferdam in the middle of the River Wear nears completion. Water has been drained out of the cofferdam, a large steel watertight structure within the river, to allow the building of pylons for the bridge deck. It is the first bridge to be built over the Wear in Sunderland for more than 40 years and is part of the wider strategic transport plan to link the Port of Sunderland and city centre with the A19 road.
May 25, 2016 Read time: 2 mins
Cofferdam construction to allow work on main pylon foundations
In the UK, foundation work for Sunderland city’s new bridge is about to start as the huge cofferdam in the middle of the River Wear nears completion.

Water has been drained out of the cofferdam, a large steel watertight structure within the river, to allow the building of pylons for the bridge deck.

It is the first bridge to be built over the Wear in Sunderland for more than 40 years and is part of the wider strategic transport plan to link the Port of Sunderland and city centre with the A19 road.

Before the end of the year, a 105m A-frame pylon will be floated from Belgium on a giant barge before being slowly hoisted into position on the river. It will take several hours to raise the pylon and secure it.

Stephen McCaffrey, project director for FVB joint venture, created by 1622 Farrans Construction and Victor Buyck Steel Construction, said the positioning of the pylon will be “a very complex project” and “not straightforward”.

Farrans Construction is a building and civil engineering contractor across the UK and Ireland. Victor Buyck is based in Belgium and specialises in major structural steelwork, especially steel bridges. The FVB joint venture is supported by their design team led by Buro Happold Engineering and Roughan & O'Donovan.

Sunderland City Council is holding a two-phase consultation to find a name for the new bridge.

For more information on companies in this article

Related Content

  • Sunderland’s Northern Spire bridge opens
    August 28, 2018
    Sunderland’s Northern Spire bridge with its 105m-high central A-frame pylon opens to traffic today after a four-month delay because of poor weather. The bridge opened for pedestrians and cyclists yesterday after three Sunderland-built Nissan vehicles first crossed the bridge during a ceremony to mark completion of the project. Work began in May 2015 and the bridge has been built within its allocated €129 million budget. However, poor weather conditions pushed back the opening of the bridge from this past
  • Sunderland’s Northern Spire bridge opens
    August 28, 2018
    Sunderland’s Northern Spire bridge with its 105m-high central A-frame pylon opens to traffic today after a four-month delay because of poor weather. The bridge opened for pedestrians and cyclists yesterday after three Sunderland-built Nissan vehicles first crossed the bridge during a ceremony to mark completion of the project. Work began in May 2015 and the bridge has been built within its allocated €129 million budget. However, poor weather conditions pushed back the opening of the bridge from this past
  • Sunderland’s Northern Spire bridge opens
    August 28, 2018
    Sunderland’s Northern Spire bridge with its 105m-high central A-frame pylon opens to traffic today after a four-month delay because of poor weather. The bridge opened for pedestrians and cyclists yesterday after three Sunderland-built Nissan vehicles first crossed the bridge during a ceremony to mark completion of the project. Work began in May 2015 and the bridge has been built within its allocated €129 million budget. However, poor weather conditions pushed back the opening of the bridge from this past
  • Launch soon for the Sunderland Bridge’s deck across the Wear
    March 24, 2017
    The team constructing the New Wear Crossing near the English city of Sunderland is preparing for the final launch of the 300m bridge deck. In recent weeks, the legs of the 100m-tall centrepiece have been secured to the foundations within the riverbed and most of the rigging used to raise it into place has been removed. While the bridge deck was being painted, the bottoms of both pylon legs were filled with 175tonnes of concrete, The next major process will be to slowly pull the bridge deck out acr