Chilean bridge project to Chiloe Island delayed

Delays to the project to construct Chile’s Chacao Bridge mean that an additional two years may be required for the work. The work is now being carried out solely by a consortium, Consorcio Puente Chacao, headed by the South Korean contractor Hyundai.
October 31, 2018 Read time: 2 mins

Delays to the project to construct Chile’s Chacao Bridge mean that an additional two years may be required for the work. The work is now being carried out solely by a consortium, Consorcio Puente Chacao, headed by the South Korean contractor 236 Hyundai. The consortium asked for an extra US$200 million to carry out the project, in addition to extending the work by two years. The bridge was originally planned to be complete by 2020 but the various delays so far mean that it will not now be ready for traffic until 2023. The extra costs mean that the final bill for the project could be $900 million. 

A suspension bridge design was selected  for the link as it was thought to be best able to cope with the extremes of weather, as well as the massive earthquakes that can occur in the area. At 2.75km long, this will be South America’s longest suspension bridge once complete, with main spans of 1,055 and 1,155m. According to Hyundai, progress is being achieved on the project and the design for the south pillar is now complete.

Once the bridge is complete it will help to redevelop the economy of Chiloe Island. At present the inhabitants rely on a ferry service however the new bridge will speed transport and reduce journey times, boosting the economy and also helping to develop tourism. 

The bridge has been discussed for some years. An earlier plan for the project was cancelled over concerns about its costs. However the current project was commissioned as the suspension bridge configuration offered considerable cost benefits over the previous design, while delivering the expected connectivity to the island.
 

For more information on companies in this article

Related Content

  • Poland's A1 motorway progressing well
    February 9, 2012
    The second major phase of a north-south motorway in Poland is well underway. It will reduce congestion and improve safety as Patrick Smith reports Before the whistle blows to herald the start of Euro 2012, Poland's main seaport Gdansk will boast new roads, a new airport and a new stadium. The historic city in the north of the country on the Baltic coast will be one of the venues for football's 14th European Championship, being co-hosted by Poland and Ukraine.
  • Mobile River Bridge project proposed
    April 13, 2021
    A new proposal for the Mobile River Bridge project has been put forward.
  • Chile awards CRCC major Talca-Chillán upgrade
    April 14, 2021
    China Railway Construction Corporation will upgrade and operate a section of Route 5.
  • Delay to SF-Oakland Bay Bridge East Span opening and probe report
    July 9, 2013
    The Toll Bridge Program Oversight Committee (TBPOC) today said that the previously scheduled Labor Day (2 Sep) opening of the new East Span of the San Francisco-Oakland Bay Bridge has been postponed. News of the delayed opening was announced at the same time as TBPOC released its investigative report into the 32 bolts that broke on the Bay Bridge in March 2013, and its review of other bolts on the bridge. The contractor now forecasts that the steel saddle retrofit of the failed bolts on the east pier will b