Auckland’s causeway project

When it is finished in early 2017, the causeway on Auckland’s North-western Motorway, State Highway 16, will have been raised 1.5m to stop flooding at extreme high tides. There will be four lanes city-bound and four/five lanes westbound with dedicated bus lanes in each direction, and the existing North-western cycleway that runs alongside it will be upgraded.
April 4, 2014 Read time: 3 mins
Part of the 4.8km Causeway Upgrade Project on Auckland's North-western motorway which runs through a marine reserve, looking east towards the city - Photography by Greg Kempthorne
When it is finished in early 2017, the causeway on Auckland’s North-western Motorway, State Highway 16, will have been raised 1.5m to stop flooding at extreme high tides. There will be four lanes city-bound and four/five lanes westbound with dedicated bus lanes in each direction, and the existing North-western cycleway that runs alongside it will be upgraded.

More than 10,000 wick drains have already been installed to accelerate consolidation of up to 15m of alluvial marine mud as part of the NZ Transport Agency’s 4.8km, US$183.3 million (NZ$220 million) Causeway Upgrade Project. “Intensive ground reclamation like this is an important part of the project’s work to upgrade and improve this section of the motorway. We are mindful to protect the marine reserve environment where we are working, installing new bird roosts for species which inhabit the area, and silt fences,” said the Transport Agency’s highways manager, Tommy Parker. 

A 2-3M-deep drainage blanket using more than 26,000 truckloads of 19-25mm recycled aggregate has been spread on top of the wick drains. When the settlement has stabilised, construction of new motorway lanes will start on top of it.

The Causeway Alliance – the NZ Transport Agency, AECOM, Coffey, Fulton Hogan, Leighton Contractors and Sinclair Knight Merz – is completing the upgrade.
 
The project is one of five underway or planned to finish the 47km-long Western Ring Route along the South-western, North-western and Upper Harbour motorways, which is identified by the Government as one of its Roads of National Significance to support New Zealand’s economic growth.

The project is the first in New Zealand to adopt temporary orange marking tape to improve lane definition and enhance driver safety. Maintaining traffic flow of almost 100,000 vehicles/day while upgrading this section of the state highway network is a key challenge and driver cooperation is essential.

Mr Parker said that for the first time, Auckland will have direct motorway access between the central business district and the airport, and the Western Ring Route will also better connect people and freight with the city’s rapidly growing areas in the north-west and south-west. 

 “It’s a key part of a massive investment in infrastructure needed to meet the demands of rapid economic and population growth underway in the top half of the North Island,” he said. 

More detailed information on this project will be included in a feature in the April issue of World Highways.

Related Content

  • Israel interchange
    March 20, 2012
    A new US$350 million road project by the Israel National Roads Company will boost connectivity from the north to the centre of the country. The project is seeing the opening of new interchanges and roads in western Galilee.
  • A tricky road update is planned for an important rural road in Brazil
    September 27, 2013
    Brazilian consultant SOTEPA has been closely involved with infrastructure improvements in a series of projects in the southern state of Santa Catarina. One of the most important of these has been design work for the SC-477 state highway, which connects the east of the state to Brazil’s Littoral zone and the BR-101 federal highway. The SC-477 has had to be upgraded as part of it has been unsurfaced, without an asphalt surface between Itaiópolis and Doutor Pedrinho. The road provides an important link for the
  • Turner & Townsend picks up services deal for Stonehenge in the UK
    April 6, 2018
    Professional services company Turner & Townsend has been appointed to provide commercial services for two major Highways England programmes, including its flagship A303 Stonehenge scheme. The A303 upgrade includes plans to build a road tunnel near Stonehenge, a prehistoric monument in western England believed to have been built around 3,100 BC. The road project is part of a series of planned upgrades to A303/A358 corridor to improve connectivity between the south east and south west of England. The
  • McCann lights up the M1 in major upgrade
    January 7, 2019
    UK engineering firm J. McCann is installing 500 lighting columns and accessories as part of a major 12km upgrade to one of England’s busiest motorways.