Auckland’s causeway project

When it is finished in early 2017, the causeway on Auckland’s North-western Motorway, State Highway 16, will have been raised 1.5m to stop flooding at extreme high tides. There will be four lanes city-bound and four/five lanes westbound with dedicated bus lanes in each direction, and the existing North-western cycleway that runs alongside it will be upgraded.
April 4, 2014 Read time: 3 mins
Part of the 4.8km Causeway Upgrade Project on Auckland's North-western motorway which runs through a marine reserve, looking east towards the city - Photography by Greg Kempthorne
When it is finished in early 2017, the causeway on Auckland’s North-western Motorway, State Highway 16, will have been raised 1.5m to stop flooding at extreme high tides. There will be four lanes city-bound and four/five lanes westbound with dedicated bus lanes in each direction, and the existing North-western cycleway that runs alongside it will be upgraded.

More than 10,000 wick drains have already been installed to accelerate consolidation of up to 15m of alluvial marine mud as part of the NZ Transport Agency’s 4.8km, US$183.3 million (NZ$220 million) Causeway Upgrade Project. “Intensive ground reclamation like this is an important part of the project’s work to upgrade and improve this section of the motorway. We are mindful to protect the marine reserve environment where we are working, installing new bird roosts for species which inhabit the area, and silt fences,” said the Transport Agency’s highways manager, Tommy Parker. 

A 2-3M-deep drainage blanket using more than 26,000 truckloads of 19-25mm recycled aggregate has been spread on top of the wick drains. When the settlement has stabilised, construction of new motorway lanes will start on top of it.

The Causeway Alliance – the NZ Transport Agency, AECOM, Coffey, Fulton Hogan, Leighton Contractors and Sinclair Knight Merz – is completing the upgrade.
 
The project is one of five underway or planned to finish the 47km-long Western Ring Route along the South-western, North-western and Upper Harbour motorways, which is identified by the Government as one of its Roads of National Significance to support New Zealand’s economic growth.

The project is the first in New Zealand to adopt temporary orange marking tape to improve lane definition and enhance driver safety. Maintaining traffic flow of almost 100,000 vehicles/day while upgrading this section of the state highway network is a key challenge and driver cooperation is essential.

Mr Parker said that for the first time, Auckland will have direct motorway access between the central business district and the airport, and the Western Ring Route will also better connect people and freight with the city’s rapidly growing areas in the north-west and south-west. 

 “It’s a key part of a massive investment in infrastructure needed to meet the demands of rapid economic and population growth underway in the top half of the North Island,” he said. 

More detailed information on this project will be included in a feature in the April issue of World Highways.

Related Content

  • Tackling the UK's traffic congestion
    February 28, 2012
    The biggest problem on UK roads is congestion, and there is no shortage of ideas as to how it should be tackled. Patrick Smith reports. Congestion (and how to relieve it), along with safety, are among the top priorities facing those responsible for looking after the UK's roads. Road pricing, car-share lanes, greener vehicle initiatives and alternative methods of transport such as buses, trams and rail are all part of the approach, but prior to the current economic climate the nation's love affair with the c
  • Upgrading Bolivia’s important Uyuni – Condo K Highway
    May 16, 2016
    Upgrading Bolivia’s Uyuni – Condo K route will help boost the country’s economy - Mauro Nogarin writes. The area of influence along the new Uyuni - Huarancani - Condo K road in Bolivia is of major importance to the country’s economy as it has great agricultural potential for quinoa. The highway is located in south-western Potosi and it has a cultivated area of 55,000ha, with an annual output of 13,154tonnes of quinoa. South-western Potosi is also one of the areas with the highest population of camelid lives
  • What kind of future is there for road tolls?
    November 12, 2013
    Hugh Basham, transport strategy and policy director, UK and Ireland, at DHL Supply Chain, enters the ongoing global debate around the use of road tolls Road pricing has always polarised opinion. Whilst road users - who are already struggling to cope with high fuel prices and insurance premiums – may resent the additional expense, environmentalists and frequent drivers often welcome the introduction of tolls as offering an escape from gridlocked roads. Charging to use the road network isn’t a new phenomenon
  • New Zealand expressway opening shortly
    October 7, 2019
    A 15km stretch of the Waikato Expressway project in New Zealand will open to traffic at the beginning of 2020. Building the expressway has taken five years and comes with a total pricetag of US$262.7 million (NZ$408 million). The final section of the route will be open in late 2021 and will bypass the city of Hamilton.