Skip to main content

Auckland’s causeway project

When it is finished in early 2017, the causeway on Auckland’s North-western Motorway, State Highway 16, will have been raised 1.5m to stop flooding at extreme high tides. There will be four lanes city-bound and four/five lanes westbound with dedicated bus lanes in each direction, and the existing North-western cycleway that runs alongside it will be upgraded.
April 4, 2014 Read time: 3 mins
Part of the 4.8km Causeway Upgrade Project on Auckland's North-western motorway which runs through a marine reserve, looking east towards the city - Photography by Greg Kempthorne
When it is finished in early 2017, the causeway on Auckland’s North-western Motorway, State Highway 16, will have been raised 1.5m to stop flooding at extreme high tides. There will be four lanes city-bound and four/five lanes westbound with dedicated bus lanes in each direction, and the existing North-western cycleway that runs alongside it will be upgraded.

More than 10,000 wick drains have already been installed to accelerate consolidation of up to 15m of alluvial marine mud as part of the NZ Transport Agency’s 4.8km, US$183.3 million (NZ$220 million) Causeway Upgrade Project. “Intensive ground reclamation like this is an important part of the project’s work to upgrade and improve this section of the motorway. We are mindful to protect the marine reserve environment where we are working, installing new bird roosts for species which inhabit the area, and silt fences,” said the Transport Agency’s highways manager, Tommy Parker. 

A 2-3M-deep drainage blanket using more than 26,000 truckloads of 19-25mm recycled aggregate has been spread on top of the wick drains. When the settlement has stabilised, construction of new motorway lanes will start on top of it.

The Causeway Alliance – the NZ Transport Agency, AECOM, Coffey, Fulton Hogan, Leighton Contractors and Sinclair Knight Merz – is completing the upgrade.
 
The project is one of five underway or planned to finish the 47km-long Western Ring Route along the South-western, North-western and Upper Harbour motorways, which is identified by the Government as one of its Roads of National Significance to support New Zealand’s economic growth.

The project is the first in New Zealand to adopt temporary orange marking tape to improve lane definition and enhance driver safety. Maintaining traffic flow of almost 100,000 vehicles/day while upgrading this section of the state highway network is a key challenge and driver cooperation is essential.

Mr Parker said that for the first time, Auckland will have direct motorway access between the central business district and the airport, and the Western Ring Route will also better connect people and freight with the city’s rapidly growing areas in the north-west and south-west. 

 “It’s a key part of a massive investment in infrastructure needed to meet the demands of rapid economic and population growth underway in the top half of the North Island,” he said. 

More detailed information on this project will be included in a feature in the April issue of World Highways.

Related Content

  • Key Polish road contract awarded
    April 16, 2021
    A key Polish road contract has been awarded to Poland.
  • Philippines projects proceeding as planned
    October 25, 2016
    Major expressway projects are now moving forward in the Philippines, with building due to start in the first quarter of 2017. Metro Pacific is gearing up to commence construction of the C5 Link Expressway. Meanwhile Metro Pacific Investments Corp (MPIC) has plans to commence construction of the Cavite-Laguna Expressway. The 7.6km C5 Link Expressway forms part of the Cavitex network. The US$291 million project will join the C-5 Road in Taugig to the R-1 Coastal Expressway. The $728 million Cavite-Laguna e
  • Texan tolling
    February 7, 2012
    Work is now underway on the new DFW Connector near Dallas, in the US state of Texas. This is of note as it is the largest investment of Recovery Act (ARRA) investment in a highway project so far.
  • India plans major infrastucture investment
    February 10, 2012
    India says it turned its Commonwealth Games into a world-class success, and now it aims to do the same with its infrastructure. Patrick Smith reports. On October, 2010 India put itself on the world stage, and disaster appeared to loom as a catalogue of problems dogged its biggest ever sporting event. Costing nearly US$2 billion to stage, the most expensive Commonwealth Games ever were, according to some, in doubt.