Another US$94.08mn for repairs to Hammersmith flyover in London

A further US$94.08 million (£60mn) is to be spent on fixing the Hammersmith flyover “monstrosity” in west London, England. Transport for London (TfL) is to fund a second phase of repairs to the structure’s badly corroded arches due to start in October 2013. The flyover was shut to all traffic just before Christmas 2011 to allow initial emergency arch repairs – leading to huge traffic chaos in west London – before being partially reopened a few weeks later. It was not fully opened until late May 2012.
June 14, 2013 Read time: 2 mins
A further US$94.08 million (£60mn) is to be spent on fixing the Hammersmith flyover “monstrosity” in west London, England.

2387 Transport for London (TfL) is to fund a second phase of repairs to the structure’s badly corroded arches due to start in October 2013. The flyover was shut to all traffic just before Christmas 2011 to allow initial emergency arch repairs – leading to huge traffic chaos in west London – before being partially reopened a few weeks later. It was not fully opened until late May 2012.

The latest work will take the total spent on maintaining it to at least $109.75 million (£70mn). The latest work will be carried out by the construction and civil engineering firm 2319 Costain.

Hammersmith flyover, which carries the A4 over Hammersmith and is used by 90,000 vehicles daily, will be subject to overnight lane closures, but engineers are confident there will be no need for weight restrictions.

Only last month, Hammersmith & Fulham Council (HFC) backed an expensive ‘flyunder’ tunnel as an alternative route into London from the west, but works could cost at least $392 million (£250mn) to complete.

Speaking recently on the long-running Hammersmith flyover safety saga, HFC council leader Nick Botterill reportedly said, “We know that vital repairs are necessary to the flyover but this needs to be the last time TfL spends a huge amount of taxpayers’ money on maintaining this monstrosity. Any other cash set aside for future work to the flyover needs instead to be pumped into making the flyunder a reality.

“A new tunnel solution would dramatically improve the quality of life for thousands of west Londoners and link the riverfront with Hammersmith town centre for the first time since the 60s.”

For more information on companies in this article

Related Content

  • Bid to solve pothole problem
    July 3, 2012
    The UK now has new guidance designed to ensure that when utilities companies dig up the road surface, they leave proper repairs once the work is complete. It is estimated that poorly replaced road surfaces mean there are around 90,000 remedial works each year, adding inconvenience to motorists and cyclists. Many of the road repairs are not properly carried out, increasing the risk of potholes forming and further defects. This significantly increases the risk of accidents and of damage to vehicles. The new l
  • World growth in geosynthtics set to rise
    February 17, 2012
    With geosynthetics sales set to grow rapidly in the next three years, manufacturers are preparing for the demand. Patrick Smith reports. Global demand for geosynthetics is projected to increase 5.3% annually to 4.7 billion m² in 2013 with countries such as China, India and Russia expected to post the strongest gains through the forecast period. All are building large-scale infrastructure developments and face evolving environmental protection regulations and strict building construction codes.
  • Scottish fixed link project planned
    April 30, 2020
    A Scottish fixed link project is being planned to replace a ferry service.
  • Major new road link for Stafford, UK
    December 25, 2024
    Stafford in the UK is to benefit from a major new road link.