$594 million Chilean highway delayed

Bidding for a $594 million Chilean highway is delayed.
By MJ Woof May 6, 2025 Read time: 2 mins
The new highway planned for Chile’s Chacao Island has been delayed once more – image courtesy of © Marcelo Vildosola Garrigo| Dreamstime.com


Bidding for the $594 million highway project linking Chacao and Chonchi in Chile is being delayed. All bids for the project now have to be received by 4th June 2025, with the opening of bids received now scheduled for 2nd July 2025.

The bids were originally supposed to be received by June 2021 but the deadlines have now been set back at least eight times by Chile’s Ministry of Public Works (MOP). The project will widen Route 5 on Chiloe Island, boosting capacity. 

When the long-planned Chacao Bridge connecting the island with the Chilean mainland is finally complete, this is expected to boost tourism, transport, trade and traffic considerably. The alignment runs through Castro, the island’s capital, a world heritage site. With the widened and upgraded highway between Chacao and Chonchi complete, it will be able to cope with the increased vehicle flow rates, as well as boosting safety.

The bridge project itself has been delayed numerous times. The structure was proposed a number of decades ago but then cancelled. It was then revived but the technical challenges involved in spanning a channel noted for its ferocious tides and fierce storms and that is also located in an area that suffering some of the most severe earthquake activity ever recorded has meant the bridge has taken rather longer to build than hoped.

 

 

Related Content

  • $215 million for Kenya road project
    April 21, 2025
    Funding worth $215 million will help pay for a key Kenya road project.
  • Chilean road tender due to open
    April 18, 2019
    The tender process is due to open for a major road project in Chile. The budget for the project has now been increased from US$520 million to $800 million as extra works have now been included in the project. The work will be carried out on the Talca-Chillan section of Ruta 5, the main north-south highway in Chile. The winner of the tender process will carry out the construction work and then have a 10 year concession package to manage the highway. Rute 5 is one of the most important highways in Chile, stre
  • Costa Rica construction contracts
    May 22, 2020
    Costa Rica construction contracts are facing challenges.
  • Hyundai looking for new partner for Chilean bridge deal
    March 21, 2016
    South Korean firm Hyundai is looking for a new partner to join the consortium that will construct Chile’s Chacao Bridge. The project has been planned for some years, having been cancelled once previously, and will connect with Chiloe Island, replacing the current ferry service. The new partner for the consortium would take the place of Brazilian firm OAS, which is currently embroiled in legal difficulties due to an ongoing investigation in Brazil. The aim is that a new partner could buy out the 49% stake in