30% increase in cost expected for Bangladesh’s Padma Bridge project

The price of building the Padma Bridge in Bangladesh could rise by 30% due to the depreciation of the taka against the US dollar and rising construction material prices. The bridge had been most recently forecast to cost US$2.9billion, with budgets previously having risen two-fold from the US$1.22billion funding package approved in 2007 by Bangladesh’s Executive Committee of the National Economic Council (ECNEC).
June 15, 2012 Read time: 1 min
The price of building the Padma Bridge in Bangladesh could rise by 30% due to the depreciation of the taka against the US dollar and rising construction material prices.

The bridge had been most recently forecast to cost US$2.9billion, with budgets previously having risen two-fold from the US$1.22billion funding package approved in 2007 by Bangladesh’s Executive Committee of the National Economic Council (ECNEC).

Last year, The World Bank decided to temporarily halt the disbursement of an aid fund for the project over an alleged corruption in the bidding process.

Related Content

  • Denmark concerned over rising cost of Fehmarn Belt Fixed Link
    February 19, 2015
    The Danish government is in talks with contractors over the latest rise in cost estimates for the proposed prestigious Fehmarn Belt Fixed Link between Denmark and Germany. Contractors have estimated an extra €295.5 million will be needed. This is in addition to a statement last November by the contracting company Femern saying that costs had risen nearly €900 million. The total rise price hike is nearly €1.2 billion. This puts the final cost of the 18km tunnel including two railway tunnels, two motorway tun
  • Bangladesh highway contract awarded
    November 15, 2022
    A major Bangladesh highway contract has been awarded.
  • Cost increases for major Chilean highway project
    November 15, 2013
    The cost of Chile’s Vespucio Oriente highway project is increasing, while its completion also looks set to be delayed. A 13% budget increase is now required due to additional costs from a number of factors such as urban landscaping, according to Business News Americas. The Américo Vespucio Oriente (AVO) expressway is being built in Chilean capital Santiago and was originally expected to cost in the region of US$940 million. However Chile’s Public Works Ministry, MOP, has said that the route will now cost so
  • Ukraine’s shattered highways
    July 26, 2024
    With no end to its war with Russia in sight, Ukraine is also fighting hard to cope with a growing backlog of major infrastructure projects, especially in terms of rebuilding the country’s roads and bridges. David Arminas reports.