Zhejiang Jiashao Bridge Investment & Development Co

Located in Zhejiang Province of China, Jiashao Bridge spans the Qiantang River and connects the cities of Jiaxing and Shaoxing. The total length of the bridge project is 10.14km and carries an eight-lane expressway The Qiantang River suffers from a high flow rate of up to 7.5m/s. As the tidal range is around 7-9m, the water depth is less than 2m in time of low level tide, so ships can only move at high tide and large scale ship-lifting equipment cannot be used downstream of Jiashao Bridge. However, to
April 6, 2017 Read time: 3 mins
The high flow rate and tidal range of the Qiantang River is a challenge to vessels, as well as to the construction of the new bridge
RSSLocated in Zhejiang Province of China, Jiashao Bridge spans the Qiantang River and connects the cities of Jiaxing and Shaoxing. The total length of the bridge project is 10.14km and carries an eight-lane expressway

The Qiantang River suffers from a high flow rate of up to 7.5m/s. As the tidal range is around 7-9m, the water depth is less than 2m in time of low level tide, so ships can only move at high tide and large scale ship-lifting equipment cannot be used downstream of Jiashao Bridge.

However, to protect against the Qiantang tidal bore and reduce the construction risks under the difficult conditions, an innovative structure design was adopted for this bridge project. For the main bridge design, a six-pylon cable-stayed bridge with five 428m-long main spans is adopted. Single-pylon structure, with the top of pile caps located under the riverbed surface is used to control the water blocking rate of the bridge structure. The superstructure of the main bridge is separated by four-plane stud welding streamlined flat steel box girders. The total steel girder width reaches 55.6m.

To increase the vertical stiffness of the main girder effectively and control the temperature deformation of the whole 2680m-long main girder, an innovative double-support and hinge (DSH) system was adopted.

With the DSH system, there are two vertical supports set at both sides of the pylon for the steel box girder at the pylon bracket area, and four two-way sliding bearings for one pylon. Using the DSH system, the scale of pylons and foundations were reduced, and US$139.8 million was saved compared to traditional designs without hinges.

In order to enhance the integral stability of the structure with tall and flexible single-pile-column foundations, I-shape transversal beams were set between the separated decks. The single-pile-column substructure had a small water-blocking area, which had a small influence on hydrology. And with no pile cap, it avoided the risk of cofferdam construction from the tidal bore.

The completed Jiashao Bridge now features an elegant and integral structural design. The application of the DSH system and hinge-related technologies, including design, manufacturing, erection, monitoring, and maintenance promotes the theoretical and technical development of multi-pylon cable-stayed bridges and contributes to the promotion of multi-pylon cable-stayed bridges worldwide.

Wang Zhangxuan, vice general manager of Jiashao Bridge Investment & Development Co said, “On behalf of Zhejiang Jiashao Bridge Investment & Development Co of China, I am very grateful that the 3918 IRF Washington has awarded the 2016 Design GRAA to the Jiashao Bridge project.

It was a great challenge for the designers, CCCC Highway Consultants Co, to account for the Qiantang River tide and incorporate appropriate technical and material innovations for design and construction. I welcome bridge specialists from around the world to come to China and visit the project; we are happy to exchange and share experiences and concepts with each other.”

For more information on companies in this article

Related Content

  • Bridge project uses high performing formwork
    February 20, 2012
    Doka designed and supplied a high-performing formwork technology solution for a challenging bridge project south of the German town of Halle. The 8,614m long single-cell box girder superstructure of the Saale-Elster Viaduct, with a typical cross section width of 13.9m, is borne on 220 piers, and has a constructional depth of 4m. It is mainly being erected on launching girders to minimise the impact on flora and fauna.
  • Innovative Ohio River Bridge crossing
    March 31, 2016
    Work is underway on an innovative new bridge link over the Ohio River in the US.
  • The world’s longest suspension bridge
    June 24, 2024
    The world’s longest suspension bridge is the 1915 Çanakkale Bridge in Turkey. This engineering marvel links Gelibolu with Lapseki, forming a key section of the 101km highway linking Malkara with Çanakkale. *Article produced in partnership with the General Directorate of Highways (KGM), Ministry of Transport and Infrastructure, Republic of Türkiye.
  • Mersey Gateway Bridge has won IABSE’s Outstanding Structure Award
    June 25, 2019
    The UK’s Mersey Gateway Bridge has picked up the Outstanding Structure Award 2019 from IABSE, the International Association for Bridge and Structural Engineering*. Judges described the bridge, designed by Cowi, as "an elegantly integrated solution for a multi-span concrete cable stay bridge in which form follows function". "Everyone involved with the design and construction the Mersey Gateway Bridge over the past six years knows that this is an incredibly special structure,” said Paul Sanders, Cowi’s