Wolffkran leads the pack

At present, the two WOLFF 7534.16 Clear cranes are drawing a lot of attention near Horb in Germany’s Neckar Valley
By David Arminas December 10, 2024 Read time: 3 mins
Porr owns a large WOLFF pack: the rental of additional components, the production of special parts and special static calculations are all part of Wolffkran’s service portfolio (image ©Jürgen Pollak)

When completed, this impressive 667m-long and up to 90m-high bridge will span the Neckar Valley near the small town of Horb in Baden-Württemberg state, Germany. Thanks to this new bypass, traffic in the centre of Horb will be reduced and the region's transport infrastructure will be upgraded.

But until then, there will be plenty to do for the contractor Porr and five WOLFF cranes that are in use at the enormous construction site. Their figures are also impressive: two freestanding WOLFF cranes are operating on towers 96m and 101m high.

At present, the two WOLFF 7534.16 Clear cranes are drawing a lot of attention in the Neckar Valley. Both are around 100m high and tower over the first 70m elements of the new viaduct. Since the fall of 2023, they have been moving heavy freestanding steel components, formwork, reinforcements and concrete buckets. With their 75m jibs, they can lift a maximum of 16.5 tonnes and 3.4 tonnes at the top (4-strand operation).

“This is normally not possible with a freestanding crane,” explains Wolfgang Kavelius, sales manager at Wolffkran. “But the special design of the bridge piers meant that no tie-ins could be used or they would have been disproportionately complex and expensive.”

The WOLFF technical team

For this reason, Porr turned to the technical support team at Wolffkran, which not only developed a suitable crane concept, but also a special structural solution for the two Porr-owned WOLFF cranes. “To ensure the necessary stability, the towers were assembled using three different tower elements,” explains Peter Hegen-bart, head of sales project engineering at Wolffkran.

The lower third of the towers is formed by the TV 33 tower element with a side length of 3.3m. Above this is a transition area composed of tower sections with a side length of 2.5m, which leads into the upper half of the tower made of 2mx2m tower sections (TV 20). “This specialised structure makes it possible to limit the maximum tower deformation to well under 2m, thus allowing the cranes to be operated safely as freestanding units,” says Hegenbart.

“Thanks to Wolffkran’s experience and technical expertise, we can use our own WOLFF 7534 Clear cranes as planned. This also allowed us to simply rent the additional 3.3m tower elements we needed for the project. We appreciate this flexibility, which goes above and beyond the normal standard, from our long-standing partner Wolffkran,” says Markus Jahn, project manager at Porr.

Two-stage assembly

In the inaccessible terrain of the Neckar Valley, which is also traversed by an intercity express railway line and a cycle path, the available space is very limited. This makes the construction site logistics particularly challenging.

Because it was not possible to use a sufficiently large mobile crane to erect the two WOLFF 7534.16 Clear cranes to their ultimate height, the assembly was carried out in two stages. After the mobile crane had assembled the tower to a height of around 60m, the cranes climbed the remaining 40m to the top using an external climbing mechanism.

For space reasons, both cranes were placed on foundation anchors. As construction progresses, the complex assembly process, which takes two days for each crane, will have to be repeated, as one of the two cranes will be moved to follow the progress of the expanding bridge.

The WOLFF 7534.16 Clear cranes are currently being supported by a WOLFF 6031.12 Clear with a 65m jib and a 47.3m hook height. As the construction process moves forward, a WOLFF 7534.16 Clear and a WOLFF 6031.12 Clear from the Porr crane fleet will support the pack.
 

Related Content

  • Gordie Howe Bridge towers rise
    January 19, 2022
    Each tower is composed of 51 segments constructed using a jump-form climbing system.
  • Doka formwork rises above the Orinoco River in Venezuela
    July 8, 2016
    Taking a road and rail link across one of the biggest rivers in South America, together with its swamps and flood-plain, called for a new crossing of truly superlative dimensions. Two 135.5m pylons for the third bridge across the Orinoco River, at Caicara del Orinoco, in Venezuela took shape with a formwork solution and automatic climbing technology from Doka. The bridge has an overall length of just over 11km and the main bridge is nearly 2.3km long with the roadway 55m above the river. The two ident
  • Austria's first PPP project takes shape
    July 31, 2012
    North of the Austrian capital Vienna, one of the region's biggest transport infrastructure projects for decades is currently under construction, the A5 Nordautobahn. This will give the Greater Vienna region its first-ever high-capacity link to the Czech motorway and arterial road network, greatly easing congestion on the old main road. In the first phase of construction, 22.7km of motorway are to be built. Work on the second section, all the way through to the Czech border, is to start in 2010. The A5 Norda
  • Formwork solutions for bridge maintenance and repair
    January 6, 2015
    An array of innovative formwork solutions have helped in the repair and construction of key bridge links - Mike Woof writes Formwork producers are continually developing novel solutions for bridge maintenance and construction applications. Several key structures have benefited from the novel use of formwork systems, with suppliers such as Doka, PERI, Pilosio and RMD all working on important structures in recent times. In Estonia, construction work is underway on the bypass around Tartu, the country’s