Wolffkran leads the pack

At present, the two WOLFF 7534.16 Clear cranes are drawing a lot of attention near Horb in Germany’s Neckar Valley
By David Arminas December 10, 2024 Read time: 3 mins
Porr owns a large WOLFF pack: the rental of additional components, the production of special parts and special static calculations are all part of Wolffkran’s service portfolio (image ©Jürgen Pollak)

When completed, this impressive 667m-long and up to 90m-high bridge will span the Neckar Valley near the small town of Horb in Baden-Württemberg state, Germany. Thanks to this new bypass, traffic in the centre of Horb will be reduced and the region's transport infrastructure will be upgraded.

But until then, there will be plenty to do for the contractor Porr and five WOLFF cranes that are in use at the enormous construction site. Their figures are also impressive: two freestanding WOLFF cranes are operating on towers 96m and 101m high.

At present, the two WOLFF 7534.16 Clear cranes are drawing a lot of attention in the Neckar Valley. Both are around 100m high and tower over the first 70m elements of the new viaduct. Since the fall of 2023, they have been moving heavy freestanding steel components, formwork, reinforcements and concrete buckets. With their 75m jibs, they can lift a maximum of 16.5 tonnes and 3.4 tonnes at the top (4-strand operation).

“This is normally not possible with a freestanding crane,” explains Wolfgang Kavelius, sales manager at Wolffkran. “But the special design of the bridge piers meant that no tie-ins could be used or they would have been disproportionately complex and expensive.”

The WOLFF technical team

For this reason, Porr turned to the technical support team at Wolffkran, which not only developed a suitable crane concept, but also a special structural solution for the two Porr-owned WOLFF cranes. “To ensure the necessary stability, the towers were assembled using three different tower elements,” explains Peter Hegen-bart, head of sales project engineering at Wolffkran.

The lower third of the towers is formed by the TV 33 tower element with a side length of 3.3m. Above this is a transition area composed of tower sections with a side length of 2.5m, which leads into the upper half of the tower made of 2mx2m tower sections (TV 20). “This specialised structure makes it possible to limit the maximum tower deformation to well under 2m, thus allowing the cranes to be operated safely as freestanding units,” says Hegenbart.

“Thanks to Wolffkran’s experience and technical expertise, we can use our own WOLFF 7534 Clear cranes as planned. This also allowed us to simply rent the additional 3.3m tower elements we needed for the project. We appreciate this flexibility, which goes above and beyond the normal standard, from our long-standing partner Wolffkran,” says Markus Jahn, project manager at Porr.

Two-stage assembly

In the inaccessible terrain of the Neckar Valley, which is also traversed by an intercity express railway line and a cycle path, the available space is very limited. This makes the construction site logistics particularly challenging.

Because it was not possible to use a sufficiently large mobile crane to erect the two WOLFF 7534.16 Clear cranes to their ultimate height, the assembly was carried out in two stages. After the mobile crane had assembled the tower to a height of around 60m, the cranes climbed the remaining 40m to the top using an external climbing mechanism.

For space reasons, both cranes were placed on foundation anchors. As construction progresses, the complex assembly process, which takes two days for each crane, will have to be repeated, as one of the two cranes will be moved to follow the progress of the expanding bridge.

The WOLFF 7534.16 Clear cranes are currently being supported by a WOLFF 6031.12 Clear with a 65m jib and a 47.3m hook height. As the construction process moves forward, a WOLFF 7534.16 Clear and a WOLFF 6031.12 Clear from the Porr crane fleet will support the pack.
 

Related Content

  • Superlative formwork’s global appeal
    April 25, 2013
    The latest formwork solutions are enabling some tough bridge-building projects to be delivered in South America and Europe, while the world’s largest construction equipment show is seeing the merits of other cutting-edge formwork. Guy Woodford reports. Taking a road and rail link across one of South America’s largest rivers, together with its swamps and floodplain, calls for a new crossing of superlative dimensions. Two 135.5m pylons for the third bridge across the Orinoco River in Venezuela are taking shap
  • Moscow crane deal for Manitowoc
    June 25, 2018
    Moscow-based crane rental company TOPKRAN-RENT has purchased four new Potain Hup cranes The deal is of note as these are the first units of this type to be sold in Russia. The four new Hup 40-30 self-erecting cranes are being put to work on a four-month project in the capital. TOPKRAN-RENT is already familiar with the Potain self-erecting cranes from Manitowoc, having previously purchased several Igo 50 cranes – the biggest model in the Igo range. Like the existing Igo cranes from the firm, the new Hup r
  • Formwork plays a leading role in global infrastructure projects
    June 13, 2012
    New and highly regarded existing formwork systems have been used in major recent transport-related construction projects across the globe. Guy Woodford looks at some of their applications The multi-million dollar Mississippi River Bridge project in the United State is creating a vital new gateway between Illinois and Missouri. Central to the project is the realignment and reconstruction of Interstate 70 and a new landmark bridge, featuring two pylons projecting vertically from the Mississippi river bed w
  • São Paulo's landmark bridge construction
    February 21, 2012
    To improve access from the east to São Paulo city centre, main contractor Construbase Engenharia is building a road complex comprising three viaducts and access ramps. The greatest challenge in Brazil's largest city is the showpiece Padre Adelino viaduct, a 122m long single-arch, single-span, cable-stayed concrete bridge moulded in situ with a parabola-shaped arch and a single-cell post-tensioned cantilever caisson