Versatile concrete pour

One of Wirtgen’s SP 15i compact concrete slipformers has been used to handle a paving job within confined conditions in Germany
August 18, 2021 Read time: 3 mins
The Wirtgen compact slipformer was able to handle the job quickly and efficiently

Despite the machine’s compact size however, it can pave profiles up to 1.3m high, while the new offset mould now allows it to pave up to 2.2m wide compared with 1.8m for the previous variant. The SP 15i is suited to duties such as the construction of kerb and gutter profiles, concrete safety barriers, drainage structures or channels as well as narrow paths.

This last function came in useful for a project in Esterwegen, near Papenburg, Germany. The machine was used by a contractor for paving a 750m-long y 2m-wide cycle path alongside a rural road. As the adjacent trees left little space to work, the machine’s manoeuvrability came in useful, as did its compact dimensions. The intelligent steering and control system with the proven Ackermann steering system allowed the machine to be handled with precision. The computer-assisted steering system varied the speed of the individual track units so that the SP 15i followed the specified references accurately.

In addition, the system can adjust the steering angle of each track unit automatically, depending on the paving radius and the machine geometry. This means that the machine can, in principle, be used to pave curved profiles with minimum radii of only 500mm. In addition, the slipform paver can be easily manoeuvred with the help of the additional crab and coordinated steering modes.

The SP 15i used in Papenburg was equipped with two steering and two height sensors each that scanned the previously tensioned stringline on the left-hand working side, ensuring the process of levelling the 12cm-thick cycle path was precise.

The machine is versatile as the auger conveyor is hydraulically adjustable longitudinally, in the angle of incline and rotatable in order to feed concrete to the mould on both the right and left side of the machine. It has conventional levelling, mechanically scanning stringlines to control the position and height during paving.

The machine was used to pave a width of 2m and with a 120mm thickness
The machine was used to pave a width of 2m and with a 120mm thickness

Cloth and manual brushing was used to deliver the required surface texture. During construction, traffic on the quiet rural road kept flowing on one lane. At the same time, the construction site was accessible for the truck mixers to discharge the concrete into the receiving hopper of the paver’s 4.6m-long auger conveyor. The 2m-wide mould was fed via the auger. As the auger conveyor is capable of holding large quantities of concrete, paving was able to continue between loads from the truck mixers.

Due to the ability to continuously pour concrete and the machine’s average advance rate of 1.3m/min, the contractor was able to complete the project in just three days.

The machine was equipped with Wirtgen’s WIDOS information system and the contractor also benefited from the supplier’s SmartService service agreement as well as the WITOS FleetView telematics solution.

For more information on companies in this article

Related Content

  • Asphalt paving design advances
    June 15, 2012
    A diverse array of advanced paver designs is now being offered in the asphalt paving sector – Mike Woof reports With the World of Asphalt and INTERMAT 2012 events having both taken place in recent months, a series of innovations have been introduced for the asphalt paving market. Developments have come to market that widen the array of both US and European asphalt paving systems and all the major manufacturers have developed new pavers and materials feeders to meet the latest emissions requirements. Demand
  • Hot-to-hot paving upgrades Bremen City Airport runway
    September 30, 2013
    A new high quality runway surface has been laid at Bremen City Airport. This has provided a much-needed replacement at the airport as the old runway was laid over 20 years ago and was suffering from cracking and potholes. Laying the new surface required the airport to be closed, with the work having to be carried out in a tight time schedule. Contractor Heitkamp Erd- und Straßenbau was brought in to carry out the work as the firm had experience in runway rehabilitation projects having carried out pavemen
  • Milling versatility on German road job
    March 22, 2017
    Milling efficiently with a versatile, mid-sized machine has offered benefits on a German road job. A German contractor has found that using a mid-sized milling machine from Wirtgen has offered a good combination of both versatility and productivity for a road rebuild job. Kassel-based milling specialist VORO has used a Wirtgen W 100 CFi to upgrade the surface of a section of the busy B3 route. The B3 is an important route and runs 755km from Buxtehude in the north of Germany through to the Swiss border in t
  • Much from Mazio, the SKID Paver
    May 25, 2022
    SKID Paver’s retractable hydraulic screed allows the operator to work around obstacles.