Special formwork solution for tricky Orinoco project

Taking a road and rail link across one of the biggest rivers in South America, together with its swamps and flood plain, calls for a new crossing of superlative dimensions. Two 135.5m pylons for the third bridge across the Orinoco River in Venezuela are taking shape with the Venezuelan government investing in the showcase project at Caicara del Orinoco. The bridge will have an overall length of 11.125km on completion, which is scheduled for 2015. The main bridge is 2.28km long, and the roadway is 55m above
April 24, 2013 Read time: 4 mins
Formwork from Doka meets the requirements regarding changes in the cross-section (Picture: Doka)

Taking a road and rail link across one of the biggest rivers in South America, together with its swamps and flood plain, calls for a new crossing of superlative dimensions

Two 135.5m pylons for the third bridge across the Orinoco River in Venezuela are taking shape with the Venezuelan government investing in the showcase project at Caicara del Orinoco.

The bridge will have an overall length of 11.125km on completion, which is scheduled for 2015. The main bridge is 2.28km long, and the roadway is 55m above the water level of the Orinoco.

The two identical diamond-shaped pylons of the 360m main span will be the centrepiece of this high-capacity link.

The formwork solution for both the north and south pylon comes from 203 Doka, which is represented in Latin America by subsidiaries in Brazil, Chile, Mexico, Panama and Peru.

When the contractors 1305 Odebrecht first approached Doka Brasil, the forming operations for the south pylon had already started.

According to Doka, by this time it had become clear that the local crane-jumped formwork originally fielded here was not suitable for the task.

Following initial discussions with Odebrecht, Doka developed a solution based on the crane-independent automatic climbing formwork SKE100. “The formwork solution presented by Doka convinced the client in terms of safety and cost-efficiency, as well as speedy construction progress,” says Markus Kamleithner and Nikolaus Eder, the Doka project managers.

The 135.5m tall pylons are basically identical, but with certain minor design differences. They incline at an 18° angle below the cross-beam, and at 13° above it.

Doka says that the most difficult aspects to deal with in the planning work were the changes in the cross-section, the catwalk between the legs of each pylon, and incorporating an extra suspended platform to provide access to the passenger hoist.

With significant changes in cross-section between the foundations and the cross-beam, and a continued upward taper until the point where the pylon legs meet, the structure geometry demands a great deal of adaptability from the formwork systems.

“Automatic climbing formwork SKE100 and the versatile Large-area formwork Top 50 system meet these requirements without needing time-consuming adaptation work,” says Doka.

The load capacity of 10tonne per bracket allows work to proceed simultaneously on several levels. An extra work deck level has been provided above the pouring platform for mounting the reinforcing cages. This allows the forming and reinforcing operations to run in parallel.

A protection screen has been deployed to ensure workplace safety. The working platform and Level +1 are enclosed with trapezoidal sheeting, and all other levels safeguarded by standard handrails.

A catwalk is the main route for site traffic between the legs of each pylon. It is attached to the automatic climbers and is raised along with them up to the next section. A third telescopic suspended platform provides access to the passenger hoist.
After an approximately five-month planning stage, work on pre-assembling the SKE100 units began in September 2011. Doka took over the forming operations on the south pylon from the 17th casting step onward, while on the north pylon the company’s automatic climbing technology was used from the outset.

Two sets of automatic climbing formwork SKE100 with 54 units in total, a catwalk and Large-area formwork Top 50 are in use.

Doka supplied all the systems for on-site pre-assembly and installation. In the crucial assembly phase, both project manager Markus Kamleithner and international formwork instructors were on the site, giving professional introductory training to the site crew and making sure that the formwork systems were properly assembled, installed and handled.

A formwork instructor has been on-site ever since, to assist the project team with his technical expertise.

After seven cycles on one pylon and eight on the other, the Doka automatic climbers had climbed to heights of 65.7m and 33.8m respectively by the start of 2013. The Odebrecht company has worked closely with Doka on projects in Brazil and other countries.

“Doka convinced us with a well thought-out formwork solution. Both the all-in package and the level of detail in the offer documents were truly impressive. The help the Doka formwork experts gave us with on-site assembly laid down an important basis for the project to progress smoothly,” says Vicente Rodrígues.

For more information on companies in this article

Related Content

  • Mexico viaduct complete with ULMA formwork
    February 9, 2018
    ULMA developed a comprehensive solution for the construction project of the Interlomas Viaduct, México. Forming part of Mexico City’s transportation infrastructure development plan, this viaduct is 227m long and connects the residential and commercial area Interlomas with the Naucalpan-Toluca highway. ULMA designed a solution fully tailored to meet the pace and needs of the client: gantry falsework for two 59m outer spans, and a CVS Form Carrier for the central span of 108m. ULMA’s engineering team combi
  • Cranes coming down on Gordie Howe Bridge
    June 30, 2025
    The Gordie Howe International Bridge will route traffic away from more populated areas and directly connect Highway 401 in the Canadian province of Ontario with the Interstate 75 in the US state of Michigan.
  • New German autobahn bridge under constriuction
    May 1, 2015
    Crane manufacturer Manitowoc has supplied six Potain cranes to German contractor Max Bögl. These machines are being used for constructing a new bridge carrying the A3 autobahn, close to Limburg. Working at over 70m high, the cranes tower over the Lahn Valley. The cranes for this project were supplied by Max Bögl’s subsidiary, Max Bögl Transport & Geräte. The three topless Potain MDT 222 cranes were selected for the work as they feature tip heights of up to 76.2m and can operate with a working radius of
  • New Angolan bridge offers improved connectivity
    September 30, 2013
    Drivers in Angola are benefiting from a bridge that spans the Catumbela River, taking the place of an old structure that had proven not fit for purpose. The US$35 million cable stayed bridge is located in the highway between Benguela and Lobito, around 7km from Angola’s Atlantic coast and is one of a series of new infrastructure developments in the country. Angola suffered a long period of war that impacted on its people and infrastructure. The war resulted in severe damage to the country’s road system alon