Unusual staircase columns for pedestrian crossings outside Moscow required custom-made forms Every day the largest city in the largest country in the world is threatened with gridlock. The infrastructure of the present-day traffic system can no longer cope with the increased number of vehicles, and the urban administration of Moscow, Russia, resolved to upgrade the traffic arteries connecting the inner city to satellite towns. Greater Moscow (Oblast) has a population of over seven million, and to date
June 15, 2012 Read time: 3 mins
Paschal produced a total of four form sets, each with two forms, 2m and 3m high, respectivelyPaschal produced a total of four form sets, each with two forms, 2m and 3m high, respectively
Unusual staircase columns for pedestrian crossings outside Moscow required custom-made forms

Every day the largest city in the largest country in the world is threatened with gridlock.

The infrastructure of the present-day traffic system can no longer cope with the increased number of vehicles, and the urban administration of Moscow, Russia, resolved to upgrade the traffic arteries connecting the inner city to satellite towns.

Greater Moscow (Oblast) has a population of over seven million, and to date traffic travelling to the city of Ljuberzy, 2km south-east of the Moscow roundabout, has been reached by means of an urban motorway.

Local and district streets run parallel to this route, and the second largest connecting road, an extension of the Komsomolsky Prospekt, is now being expanded. Traffic will now be routed over a newly constructed bridge, 1.737km long, where both of the lanes will be structurally separated from each other.

Construction is being carried out by LLC TransKapStroy (Moscow).

A distinctive feature of the architecture is found in additional connections for the stairways for the pedestrian crossings. There are two for each lane, which reach from the bridge to the ground in three stages.

However, the form of the stairway columns is so sophisticated that standard solutions were out of the question. The columns are manufactured locally by filling a prefabricated form with concrete, and they take the form of a symmetrical hexagon. (The cross-section is similar to the silhouette of a clam.) All 36 props have a height of 2–6.5m.

The Paschal representative office in Moscow assigned to the main factory in Steinach, Germany, a contract for the construction of a special form designed to be used repeatedly, which can sustain a pressure from fresh concrete of 80kN/m².

It created a total of four identical sets, each consisting of two extendable concrete forms, 805mm wide, 1,020mm deep and with heights of 2m and 3m respectively.

Each form consists of two parts with the required tight-fitting sharp-edged joints secured with locking screws.

According to Paschal, a feature of the design is the simplicity and efficiency brought to the construction site: “Situate the form, pour the concrete and it is done.”

“Tie openings or involved propping or any other preparation or post-processing were not necessary. In comparison with carpentry methods this means a large increase in the speed of completion in addition to millimetre precision when working with concrete,” said Paschal.

“The technical concept developed by Paschal convinced the contractor, as did the short production time of four weeks for all.

“The scope of delivery also covers props as well as a specially constructed working platform which fulfils the most rigorous safety criteria.”

The bridge has now been opened for traffic.

Related Content

  • Bridge project uses high performing formwork
    February 20, 2012
    Doka designed and supplied a high-performing formwork technology solution for a challenging bridge project south of the German town of Halle. The 8,614m long single-cell box girder superstructure of the Saale-Elster Viaduct, with a typical cross section width of 13.9m, is borne on 220 piers, and has a constructional depth of 4m. It is mainly being erected on launching girders to minimise the impact on flora and fauna.
  • Geosynthetics give extra strength to soil reinforcement
    March 14, 2012
    Using geosynthetics for soil reinforcement is highly effective but requires a high quality and trusted geogrid. When it comes to deciding which geogrid is best for a specific project, a number of product parameters must be taken into account. In the design of steep slopes, the most important parameter is the available long term design strength (Pdes). Recently, Colbond has significantly increased this factor for its high performance Enkagrid product, recognised with a newly updated BBA (British Board of Ag
  • Geosynthetics give extra strength to soil reinforcement
    May 3, 2012
    Using geosynthetics for soil reinforcement is highly effective but requires a high quality and trusted geogrid. When it comes to deciding which geogrid is best for a specific project, a number of product parameters must be taken into account. In the design of steep slopes, the most important parameter is the available long term design strength (Pdes). Recently, Colbond has significantly increased this factor for its high performance Enkagrid product, recognised with a newly updated BBA (British Board of Ag
  • Cranes coming down on Gordie Howe Bridge
    June 30, 2025
    The Gordie Howe International Bridge will route traffic away from more populated areas and directly connect Highway 401 in the Canadian province of Ontario with the Interstate 75 in the US state of Michigan.