Skip to main content

Special formwork for Moscow

Unusual staircase columns for pedestrian crossings outside Moscow required custom-made forms Every day the largest city in the largest country in the world is threatened with gridlock. The infrastructure of the present-day traffic system can no longer cope with the increased number of vehicles, and the urban administration of Moscow, Russia, resolved to upgrade the traffic arteries connecting the inner city to satellite towns. Greater Moscow (Oblast) has a population of over seven million, and to date
June 15, 2012 Read time: 3 mins
Paschal produced a total of four form sets, each with two forms, 2m and 3m high, respectivelyPaschal produced a total of four form sets, each with two forms, 2m and 3m high, respectively
Unusual staircase columns for pedestrian crossings outside Moscow required custom-made forms

Every day the largest city in the largest country in the world is threatened with gridlock.

The infrastructure of the present-day traffic system can no longer cope with the increased number of vehicles, and the urban administration of Moscow, Russia, resolved to upgrade the traffic arteries connecting the inner city to satellite towns.

Greater Moscow (Oblast) has a population of over seven million, and to date traffic travelling to the city of Ljuberzy, 2km south-east of the Moscow roundabout, has been reached by means of an urban motorway.

Local and district streets run parallel to this route, and the second largest connecting road, an extension of the Komsomolsky Prospekt, is now being expanded. Traffic will now be routed over a newly constructed bridge, 1.737km long, where both of the lanes will be structurally separated from each other.

Construction is being carried out by LLC TransKapStroy (Moscow).

A distinctive feature of the architecture is found in additional connections for the stairways for the pedestrian crossings. There are two for each lane, which reach from the bridge to the ground in three stages.

However, the form of the stairway columns is so sophisticated that standard solutions were out of the question. The columns are manufactured locally by filling a prefabricated form with concrete, and they take the form of a symmetrical hexagon. (The cross-section is similar to the silhouette of a clam.) All 36 props have a height of 2–6.5m.

The Paschal representative office in Moscow assigned to the main factory in Steinach, Germany, a contract for the construction of a special form designed to be used repeatedly, which can sustain a pressure from fresh concrete of 80kN/m².

It created a total of four identical sets, each consisting of two extendable concrete forms, 805mm wide, 1,020mm deep and with heights of 2m and 3m respectively.

Each form consists of two parts with the required tight-fitting sharp-edged joints secured with locking screws.

According to Paschal, a feature of the design is the simplicity and efficiency brought to the construction site: “Situate the form, pour the concrete and it is done.”

“Tie openings or involved propping or any other preparation or post-processing were not necessary. In comparison with carpentry methods this means a large increase in the speed of completion in addition to millimetre precision when working with concrete,” said Paschal.

“The technical concept developed by Paschal convinced the contractor, as did the short production time of four weeks for all.

“The scope of delivery also covers props as well as a specially constructed working platform which fulfils the most rigorous safety criteria.”

The bridge has now been opened for traffic.

Related Content

  • New formwork range from Paschal
    October 11, 2022
    PASCHAL is expanding the LOGO.pro wall formwork range with the panel height of 340cm for even faster forming of large areas.
  • Second Tees Valley Viaduct proposed at Middlesbrough
    March 19, 2019
    Proposals for a second crossing over the Tees River in northern England have gone out to public consultation, according to media reports. The Tees Valley Combined Authority, the local authority, said there are two options to take the A19 trunk road over the River Tees at the city of Middlesbrough. One plan, costing between €235-292 million, would be for a bridge parallel to the existing one where each bridge would traffic in only one directions. The other option is for a four-lane €350 million brid
  • Key Botswana road network gets an upgrade
    June 30, 2014
    Representing an investment of around US$113 million, Botswana’s A1 national road between Tonota and Francistown is undergoing a major upgrade This single-lane section is being progressively transformed into a north- and southbound dual carriageway, crossing four existing river bridges along the way. A strategically important transportation route for both Botswana and the southern African region, the A1 passes through Francistown, the nation’s second largest city, heading northwards to end at the Zimbabwe b
  • Machine control technology shortens road contract
    May 28, 2013
    The use of sophisticated machine control technology has helped halve the schedule required for a road contract – Jeff Winke. By using the latest machine control systems on the equipment fleet, a US contractor has managed to halve worker hours, machine time and overall costs. “We chopped 50% off the contract schedule,” said Jim Swenson, licensed professional land surveyor for Oregon Mainline Paving based in McMinnville, Oregon. “The project was completed a year ahead of the two-year schedule,” he explained