South Africa's world class tollway development

Part of an extensive motorway network measuring some 185km, the ongoing Gauteng Freeway Improvement Project (GIFP) is creating a modern, world-class toll route system that provides major impetus to socio-economic growth in South Africa's most populous and commercially active region.
May 8, 2012 Read time: 2 mins
Part of an extensive motorway network measuring some 185km, the ongoing Gauteng Freeway Improvement Project (GIFP) is creating a modern, world-class toll route system that provides major impetus to socio-economic growth in South Africa's most populous and commercially active region.

Being implemented in stages by the 3156 South African National Road Agency (SANRAL), these routes radiate outwards from the country's largest city Johannesburg to Pretoria's industrial and residential centres and to all points of the compass.

Already on major N1 and N3 transportation upgrades within Gauteng, previous congestion has now been replaced by free-flowing traffic that is foremost driven by business priorities that are time dependant. So too are the ensuing construction works.

National Route 12 (N12) is one of SANRAL's strategic priorities and it is here that civil engineering contractor 3038 Raubex Construction is  implementing a ACTFILE LOCATION:

• South Africa
PROJECT:
• National Route 12 (N12)
CONTRACTOR:
• Raubex Construction
EQUIPMENT:
178 Caterpillar RM500 rotary mixer
complete  overhaul on Section 19, an intensive programme running over 30 months.

Three major new interchanges, successive bridge widenings and an east and westbound three-lane highway in either direction will replace the existing N12 dual carriageway system along approximately 10km between the current Tom Jones and Daveyton on- and off-ramps.

The median reserve will be replaced by a central concrete median barrier to make room for the new lanes, which is where the roadworks begin, progressively moving from the inside out to complete the new freeway system.

This is the main access point passing into and out of Gauteng's West Rand region to the agricultural and mining heartland of Mpumalanga province.

Managing high traffic densities together with major road realignments will be just one of a number of challenges that need to be carefully managed. The N12 design calls for an emulsion and cement stabilisation mix for the sub-base layers.

"The N12 contract follows a similar pattern to the SANRAL project we completed in May 2010 for Section 1 of the R21 upgrade, which links OR Tambo International Airport with Pretoria [South Africa's capital]," explains Raubex Construction operations manager, Wouter van der Merwe.

For more information on companies in this article

Related Content

  • US$905 million loan for Philippines road
    January 29, 2025
    A US$905 million loan for a Philippines road project
  • New tunnelling technology saves time
    February 15, 2012
    New tunnelling technology from BASF has helped cut construction time on a major tunnel project in Australia. The system has been used to speed waterproofing, an important point as the link runs underneath one of Australia's major rivers. The spray-applied polymer membrane provided by a BASF sprayed concrete machine saved time and effort on the construction of the Clem Jones 7 Tunnel (Clem 7) in Brisbane, Australia. The 4.8km tunnel was completed seven months ahead of schedule and at its lowest point Clem 7
  • World’s largest bridge deck for KAIA expansion
    December 16, 2013
    A bespoke formwork solution from RMD Kwikform is playing a key role in creating the largest ever airport cast bridge deck as part of the multi-billion dollar expansion of King Abdulaziz International Airport near Jeddah, Saudi Arabia. The firm is also a leading player in the creation of arterial tunnels under the airport’s elevated roads, another key part of the project’s first phase works due for completion in 2014. Guy Woodford reports
  • A key section of highway is now open in Romania
    July 26, 2012
    In Romania the northern section of the bypass around the city of Constanta is open to traffic. The bypass forms part of the Pan-European Road Corridor IV and work on this section was financed by the European Bank for reconstruction and Development (EBRD). The southern stretch of the 23km bypass was completed in 2011. Now it is complete, the bypass will carry heavy port traffic away from Constanta. It will also provide a free-flowing route for tourist traffic from Romanian capital Bucharest and the north of