Pressure is on Superslim formwork

Temporary works specialist Altrad RMD Kwikform - Altrad RMDK - is helping realign the A452 road over a new rail line for England’s future high-speed trains.
By David Arminas February 4, 2025 Read time: 3 mins
Superslim Soldiers are designed to handle high loads, which for the A452 realignment project, ensured that the formwork would remain stable under the pressure of the concrete (image courtesy Altrad RMD Kwikform)

 

Altrad RMDK is working with HS2’s construction partner for the Midlands region, Balfour Beatty VINCI (BBV), and civil engineering and groundworks contractor Galldris. The A452 Kenilworth Road Overbridge is a fully integral box structure with in-situ concrete base, abutments and wingwalls, spanning more than 76m. The project is part of the vast HS2 landscape realignment of the trunk A452 road over the new high speed rail line.

The structure was one of the highest concrete pours undertaken by Altrad RMDK in Europe to date with a pouring height of 13.5m to one of the main wingwalls. The project’s success was critical in maintaining the momentum of the HS2 timeline, highlighting the collaborative efforts of all involved.

The project presented a multitude of challenges due to the complex shape and weight of the bridge. One of the main challenges was overcoming the complex geometric patterns used for the wingwalls. These wingwalls tapered in height along their length and also along their width across the base. Not only this, but the external shutters lean into the internal face to taper in width across the height.

Where the wingwalls met the abutment walls, there was a complex movement joint that was required to allow for the expansion of the respective elements while still retaining the backfill that would eventually encapsulate the structure. The project demanded meticulous planning, coordination, and execution, with the additional pressure of adhering to a tight schedule.

Altrad RMDK and Galldris worked in partnership, bringing together expertise and resources from both organisations, which proved instrumental in overcoming the complex challenges posed by the project’s scope.

The contractor needed a solution that could be configured into various shapes and sizes. The solution was a custom specification to be engineered using Superslim Soldiers and Alform Aluminium Beams to meet the complex requirements.

Superslim Soldiers are designed to handle high loads, making them an ideal solution for a pour of this stature; they ensured that the formwork would remain stable under the pressure of the concrete. The beams helped maintain the structure’s shape and integrity during the entire pouring process, which was crucial in order to prevent deformities and ensure the accurate formation.

The Alform Beams provided a quick, durable and lightweight solution, allowing for simple installation, which was particularly advantageous on this high pour as moving and positioning formwork can be time and labour intensive.

Despite being lightweight, Alform Beams withstood the substantial pressure from the concrete. They worked alongside Superslim Soliders to ensure that formwork remained intact and stable throughout the pour. This was important as it was essential that the solutions maintained the tapering shapes and dimensions of the wingwalls throughout the pouring process.

“The A452 Kenilworth Overbridge project highlights Altrad RMD Kwikform’s engineering capabilities and innovative solutions,” said Stuart Grant, senior sales representative at Altrad RMD Kwikform. “Through partnerships, careful planning and the use of advanced equipment, the project demonstrated the effective collaboration needed for this infrastructure development.”

Altrad RMD Kwikform provides of formwork, falsework/shoring, heavy-duty support, ground shoring and safety and access systems, specialising in temporary structure needed to deliver major infrastructure and building projects. The company designs, hires and sells formwork, falsework/shoring, heavy-duty support, ground shoring as well as safety and access systems.

Key sectors include civil engineering and infrastructure, ground works, energy and industrial, commercial and multi-storey residential buildings. The company works in 3D designs and BIM (building information modelling)-compliant models through its visualisation software LocusEye.

 

Related Content

  • ULMA bridges the Danube and Kayak rivers
    March 16, 2021
    The D4 motorway and R7 expressway project is Slovakia’s largest public-private partnership.
  • Doka’s UniKit is a quick way to support heavy concrete pours
    April 19, 2016
    Doka’s new UniKit is a modular shoring system for heavy civil engineering applications. Designed to be quick and easy to erect in a number of different configurations, UniKit provides a steel-girder like structure which can support loads from bridge deck or beam concrete pours. “It’s an efficient way to construct infrastructure without stopping existing infrastructure – such as roads – running underneath,” said Doka’s director of research and development Johann Peneder.
  • Doka rises to the challenge on Turkey’s Eyiste Viaduct
    June 4, 2019
    Formwork specialist Doka recently rose to the challenge on Turkey’s Eyiste Viadust, the country’s highest bridge with piers up to 155m tall. The Eyiste Viaduct will be part of a route between Central Anatolia and Turkey’s Mediterranean region, shortening travel time between the cities of Konya and Alanya. Cantilever forming travellers and Doka’s automatic climbing formwork Xclimb 60 were part of the construction solution. The viaduct is nearly 1.4km long and carried by two abutments and eight piers, stret
  • 'Tricky' bridge project
    February 7, 2012
    Contractor Ringway has completed work on a tricky project to replace Stile Farm Bridge, which crosses the Great Stour River near Chilham in County Kent, south-east England. Built in the 1920s, the bridge was in a severe state of disrepair resulting in weight restrictions of just 3tonnes. The new structure has a 16m span and is constructed using pre-cast concrete, with pre-stressed steel-reinforced beams based on cast in-situ abutment, and enables the bridge to carry heavier traffic. As well as helping to ea