Pressure is on Superslim formwork

Temporary works specialist Altrad RMD Kwikform - Altrad RMDK - is helping realign the A452 road over a new rail line for England’s future high-speed trains.
By David Arminas February 4, 2025 Read time: 3 mins
Superslim Soldiers are designed to handle high loads, which for the A452 realignment project, ensured that the formwork would remain stable under the pressure of the concrete (image courtesy Altrad RMD Kwikform)

 

Altrad RMDK is working with HS2’s construction partner for the Midlands region, Balfour Beatty VINCI (BBV), and civil engineering and groundworks contractor Galldris. The A452 Kenilworth Road Overbridge is a fully integral box structure with in-situ concrete base, abutments and wingwalls, spanning more than 76m. The project is part of the vast HS2 landscape realignment of the trunk A452 road over the new high speed rail line.

The structure was one of the highest concrete pours undertaken by Altrad RMDK in Europe to date with a pouring height of 13.5m to one of the main wingwalls. The project’s success was critical in maintaining the momentum of the HS2 timeline, highlighting the collaborative efforts of all involved.

The project presented a multitude of challenges due to the complex shape and weight of the bridge. One of the main challenges was overcoming the complex geometric patterns used for the wingwalls. These wingwalls tapered in height along their length and also along their width across the base. Not only this, but the external shutters lean into the internal face to taper in width across the height.

Where the wingwalls met the abutment walls, there was a complex movement joint that was required to allow for the expansion of the respective elements while still retaining the backfill that would eventually encapsulate the structure. The project demanded meticulous planning, coordination, and execution, with the additional pressure of adhering to a tight schedule.

Altrad RMDK and Galldris worked in partnership, bringing together expertise and resources from both organisations, which proved instrumental in overcoming the complex challenges posed by the project’s scope.

The contractor needed a solution that could be configured into various shapes and sizes. The solution was a custom specification to be engineered using Superslim Soldiers and Alform Aluminium Beams to meet the complex requirements.

Superslim Soldiers are designed to handle high loads, making them an ideal solution for a pour of this stature; they ensured that the formwork would remain stable under the pressure of the concrete. The beams helped maintain the structure’s shape and integrity during the entire pouring process, which was crucial in order to prevent deformities and ensure the accurate formation.

The Alform Beams provided a quick, durable and lightweight solution, allowing for simple installation, which was particularly advantageous on this high pour as moving and positioning formwork can be time and labour intensive.

Despite being lightweight, Alform Beams withstood the substantial pressure from the concrete. They worked alongside Superslim Soliders to ensure that formwork remained intact and stable throughout the pour. This was important as it was essential that the solutions maintained the tapering shapes and dimensions of the wingwalls throughout the pouring process.

“The A452 Kenilworth Overbridge project highlights Altrad RMD Kwikform’s engineering capabilities and innovative solutions,” said Stuart Grant, senior sales representative at Altrad RMD Kwikform. “Through partnerships, careful planning and the use of advanced equipment, the project demonstrated the effective collaboration needed for this infrastructure development.”

Altrad RMD Kwikform provides of formwork, falsework/shoring, heavy-duty support, ground shoring and safety and access systems, specialising in temporary structure needed to deliver major infrastructure and building projects. The company designs, hires and sells formwork, falsework/shoring, heavy-duty support, ground shoring as well as safety and access systems.

Key sectors include civil engineering and infrastructure, ground works, energy and industrial, commercial and multi-storey residential buildings. The company works in 3D designs and BIM (building information modelling)-compliant models through its visualisation software LocusEye.

 

Related Content

  • Modelling software aids highway widening
    February 22, 2012
    The Skanska Balfour Beatty Joint Venture has been selected by Autodesk to receive an Autodesk BIM Experience Award.
  • Bertha ends her Alaskan Way voyage in Seattle
    December 21, 2017
    Seattle's State Route 99 viaduct is coming down. David Arminas was on site. Bertha, the world’s largest diameter earth pressure balance tunnel boring machine, with a cutterhead diameter of 17.5m, is no more. Her 2.7km journey underneath the waterfront area of Seattle finished on April 4 and the power went off for the last time on an extraordinary TBM that had finally completed an extraordinary job. “A small sidewalk job would have had more impact on city traffic than we have had,” says Brian Russell a v
  • Nigeria’s giant city Lagos to benefit from a new cable-stayed bridge
    September 19, 2012
    The first cable-stayed bridge in Nigeria will link two districts of the megacity of Lagos Nigeria’s first cable-stayed bridge, the Lekki Ikoyi Bridge in the megacity of Lagos is scheduled for completion at the end of 2012. Its striking 90m high pylon characterises the appearance of the 1,357m long bridge, which will connect two districts of the West African city, Lekki on the Lekki Peninsula and Ikoyi on Lagos Island.
  • Closer ties with Highways England Collaborative Delivery Framework
    April 13, 2017
    Highways England is reconsidering its procurement to encourage innovation and ultimately deliver more for less. Kristina Smith spoke to client, contractors and material suppliers to find out more. A group of senior managers is being addressed by a local resident who lives close to some proposed road works. The resident is angry, persistent and quite rude. The question is: how will these managers respond?