Preparations are underway for a new bridge in Venezuela

A large bridge project is being planned in Venezuela, with ground investigation leading the way In Venezuela, preparation work is now being carried out for a major new bridge project. The European geotechnical specialist Lankelma is supplying its Combifloat C5 jack-up platform, JUP Sandpiper, to begin work on the ground investigation for the new Puente Nigale (in English: Nigale Bridge) over Lake Maracaibo in Venezuela. The Nigale Bridge will be the second crossing over Venezuela’s largest lake. The link,
June 25, 2013 Read time: 3 mins
The Combifloat has 27m long legs and will work on the project up to 10km offshore

A large bridge project is being planned in Venezuela, with ground investigation leading the way

In Venezuela, preparation work is now being carried out for a major new bridge project. The European geotechnical specialist 7396 Lankelma is supplying its Combifloat C5 jack-up platform, JUP Sandpiper, to begin work on the ground investigation for the new Puente Nigale (in English: Nigale Bridge) over Lake Maracaibo in Venezuela.

The Nigale Bridge will be the second crossing over Venezuela’s largest lake. The link, between Santa Cruz de Mara and Punta de Palmas, is being built by Brazilian contractor 1305 Odebrecht and was designed by consultant 2349 COWI. Lankelma is working for Venezuelan engineering consultant and contractor 7397 Geohidra to investigate locations for the foundations of the 10.8km road and rail bridge, which forms part of the new crossing at the Lake’s northern end.

The bridge is needed as Venezuela's vehicle population is increasing and it is believed that the existing infrastructure will be insufficient to meet with the demands of future traffic volumes. As an oil producer, Venezuela has the resources at present to fund major capital projects such as this new bridge and a number of other infrastructure projects are also either planned or are already underway in the country.

Geohidra and Lankelma will use three nearshore jack-up platforms to drill boreholes to a maximum depth of 70m into the mudstones beneath the lake during the nine-month contract. The Combifloat 18m by 12m platform, which has 27m long legs, will work up to 10km offshore on the project. This near-shore work platform is capable of operating in water depths of up to 18m.
Lankelma is a specialist geotechnical investigation contractor with staff and equipment resource dedicated to cone penetration testing (CPT). The firm has also purchased a wireline-deployable CPT rig from AP van den Berg in the Netherlands to combine the bes t offshore techniques with nearshore site investigations.

Eric Zon, managing director of Lankelma, said, “The expansion of our marine fleet is in line with the strategy of increasing Lankelma’s global presence, as well as expanding our specialist overwater capability.”

José Parra, geoscience manager of Geohidra, said: “We look forward to having Lankelma’s jack-up join forces with Geohidra’s three on-site exploration units: one geotechnical vessel and two jack-ups.”

Lankelma has also shipped a 6x6 21tonne CPT truck to Venezuela. The rig, which has been completely refurbished, will be used by Geohidra to carry out CPT as part of the onshore investigations for the bridge approaches. “This was the first CPT truck we brought to the UK when we set up Lankelma,” said Zon. “Having served us well, it will be sorely missed by the UK team but it is great to see that it will have a new lease of life in South America.”

For more information on companies in this article

Related Content

  • Cowi and Dissing+Weitling win Shenzhen and Zhongshan bridge deal
    April 18, 2016
    Engineering group Cowi and architecture firm Dissing+Weitling have won the tender for construction of a bridge and tunnel project to connect the Chinese cities of Shenzhen and Zhongshan. The US$5.51 billion 24km project in the southern province of Guangdong will include the world’s widest immersed road tunnel, two signature suspension bridges and two artificial islands. The road in the Pearl River Delta will have eight traffic lanes in two directions and a daily capacity of 90.000 cars, according to a
  • Versatile test boreholing rig from Central Alliance
    May 22, 2018
    A new modular rig from Central Alliance is said to opens access to areas that would otherwise be difficult to reach with conventional equipment. The firm says it has designed and built an innovative modular rig for use on difficult access areas. The modular rig was constructed in-house by Central Alliance’s development department, and can complete all the operations possible with a tracked rig including Standard Penetration Tests (SPT) and Cone Penetration Tests (CPT) at 1m intervals, U38, U70, U100 and U
  • Special formwork solution for tricky Orinoco project
    April 24, 2013
    Taking a road and rail link across one of the biggest rivers in South America, together with its swamps and flood plain, calls for a new crossing of superlative dimensions. Two 135.5m pylons for the third bridge across the Orinoco River in Venezuela are taking shape with the Venezuelan government investing in the showcase project at Caicara del Orinoco. The bridge will have an overall length of 11.125km on completion, which is scheduled for 2015. The main bridge is 2.28km long, and the roadway is 55m above
  • Bentley Systems expanding through acquisition
    May 14, 2019
    Bentley Systems continues to expand its operations through acquisitions. The firm is now further developing its portfolio with the acquisition of Keynetix, a UK-headquartered provider of cloud-based software for capturing, visualising, modelling, and sharing of geotechnical data. The company says that the addition of Keynetix software expands its geotechnical offerings and allows it to develop subsurface digital twins for infrastructure projects and assets. According to the company, subsurface digital twi