PERI for Austria’s A26 tunnels

For a project in Linz, PERI has provided what is says is Austria’s first fully hydraulic tunnel formwork carriage with a caterpillar drive
April 18, 2023 Read time: 3 mins
To construct the 1.6km-long access tunnel, PERI engineers developed the first customised and fully hydraulic special-purpose formwork carriage; sufficient to construct the different cross-sections in a total of 170 concreting sections (photo courtesy PERI SE)

The A26 project is one of the most important infrastructure projects in the Austrian city of Linz and the surrounding area. The key to success during the project implementation stage was a PERI engineering solution that was innovative, safe and efficient, coupled with comprehensive project support. The highlight of the work was that it was Austria’s first fully hydraulic tunnel formwork carriage with a caterpillar drive.

Tunnel construction to the north and south of the Danube River for the access and exit routes for the new Danube bridge has been in progress since May 2020 (see box). A large section of the tunnel runs underground so that the noise and pollution in the urban area are reduced to an even greater extent. Five different tunnel cross-sections, profile transitions, tight radii of between 50m and 750m in the bends and varying gradients were just some of the challenges that had to be overcome when constructing the 1,600m-long access tunnels for the new suspension bridge.

To overcome the challenges, Peri engineers developed Austria’s first customised and fully hydraulic special-purpose steel formwork carriage with caterpillar drive and a weight of 250tonnes. This alone was enough to produce the different cross-sections in a total of 170 concreting sections.

Given the fact that the very tight curve radii made it difficult to transport the tunnel carriage, an innovative caterpillar system was used to move it (photo courtesy PERI SE)
Given the fact that the very tight curve radii made it difficult to transport the tunnel carriage, an innovative caterpillar system was used to move it (photo courtesy PERI SE)

Given the fact that the very tight curve radii made it difficult to transport the formwork carriage, a caterpillar system was used to move it along. In addition, the formwork carriage impressed with its considerable dimensions of 8m in height and 14.5m in length as well as 10.7m in width when ready to move and 11.2m in width when ready to pour concrete.

The formwork carriage was assembled in front of the tunnel entrance under the guidance of a PERI supervisor. A short time later, the first concreting section was successfully completed, meaning that the formwork could be stripped away the very next day and the formwork carriage moved forward to the next concreting section – an efficient and time-saving solution.

Before the tunnel formwork carriage was called upon, a mobile 6m-long assembly carriage with rubber tyres and electric motor was used for the sealing work. This was followed by a reinforcement carriage adapted to the block length of 12m, the principle of which is similar to the sealing carriage. Both carriages consist of a stable VARIOKIT base frame on which a PERI UP scaffold adapted to the cross-sections was erected. This made it possible to convert and relocate the carriages quickly and cost-effectively. What’s more, the erected PERI UP scaffold served as a work platform for site personnel. In the end, the drive was controlled by an integrated hydraulic system.

Engineers from PERI Austria and the PERI Infrastructure Sales Support Unit worked together to develop a project solution that was tailored to all the customer's needs. PERI was intensively involved as early as the planning stage, providing solution-oriented input. When it came to the operational implementation stage, there was constant communication between the parties. This meant that the formwork systems could be used in an optimum fashion on the construction site and that the project was completed on schedule.

For more information on companies in this article

Related Content

  • HP series – strong pneumatic-tyre rollers with many options are performing impressively
    September 15, 2021
    The pneumatic-tyre rollers from the HP series have been on the market across the world for several months and are showing what they can do in practice. This is a completely new generation of pneumatic-tyre rollers, which have been a permanent feature of HAMM's product range since the 1960s. The new HP series model stands out thanks to the large, newly designed water tank. Like the diesel tank, it is generously dimensioned so that the machines have sufficient capacity for a full working day without stopping to refill. For this reason alone, the rollers are already extremely productive
  • Tunnels - an environmentally attractive option?
    February 21, 2012
    While tunnels are often more expensive than bridges, they can offer environmentally attractive options for transport schemes. Tunnels offer environmentally attractive options for a range of transport infrastructure schemes, but in many cases high construction costs may restrict their use.
  • Less edge spalling and a perfect joint pattern with Bomag
    June 27, 2023
    The BPR 60/65 D STONEGUARD paving plate builds quality.
  • Collaborative approach is delivering the Queensferry Crossing
    March 28, 2017
    The Queensferry Crossing forms the centrepiece of a major upgrade to the cross-Forth transport corridor in the east of Scotland. It will be the longest three-tower, cable-stayed bridge in the world and represents a Scottish Government capital investment of more than €1.5 billion. The 2.7km Queensferry Crossing is alongside the Forth Road Bridge and will carry the M90 motorway across the Firth of Forth between Lothian, at South Queensferry, and Fife, at North Queensferry. Each of the three towers are 207m