PERI for Austria’s A26 tunnels

For a project in Linz, PERI has provided what is says is Austria’s first fully hydraulic tunnel formwork carriage with a caterpillar drive
April 18, 2023 Read time: 3 mins
To construct the 1.6km-long access tunnel, PERI engineers developed the first customised and fully hydraulic special-purpose formwork carriage; sufficient to construct the different cross-sections in a total of 170 concreting sections (photo courtesy PERI SE)

The A26 project is one of the most important infrastructure projects in the Austrian city of Linz and the surrounding area. The key to success during the project implementation stage was a PERI engineering solution that was innovative, safe and efficient, coupled with comprehensive project support. The highlight of the work was that it was Austria’s first fully hydraulic tunnel formwork carriage with a caterpillar drive.

Tunnel construction to the north and south of the Danube River for the access and exit routes for the new Danube bridge has been in progress since May 2020 (see box). A large section of the tunnel runs underground so that the noise and pollution in the urban area are reduced to an even greater extent. Five different tunnel cross-sections, profile transitions, tight radii of between 50m and 750m in the bends and varying gradients were just some of the challenges that had to be overcome when constructing the 1,600m-long access tunnels for the new suspension bridge.

To overcome the challenges, Peri engineers developed Austria’s first customised and fully hydraulic special-purpose steel formwork carriage with caterpillar drive and a weight of 250tonnes. This alone was enough to produce the different cross-sections in a total of 170 concreting sections.

Given the fact that the very tight curve radii made it difficult to transport the tunnel carriage, an innovative caterpillar system was used to move it (photo courtesy PERI SE)
Given the fact that the very tight curve radii made it difficult to transport the tunnel carriage, an innovative caterpillar system was used to move it (photo courtesy PERI SE)

Given the fact that the very tight curve radii made it difficult to transport the formwork carriage, a caterpillar system was used to move it along. In addition, the formwork carriage impressed with its considerable dimensions of 8m in height and 14.5m in length as well as 10.7m in width when ready to move and 11.2m in width when ready to pour concrete.

The formwork carriage was assembled in front of the tunnel entrance under the guidance of a PERI supervisor. A short time later, the first concreting section was successfully completed, meaning that the formwork could be stripped away the very next day and the formwork carriage moved forward to the next concreting section – an efficient and time-saving solution.

Before the tunnel formwork carriage was called upon, a mobile 6m-long assembly carriage with rubber tyres and electric motor was used for the sealing work. This was followed by a reinforcement carriage adapted to the block length of 12m, the principle of which is similar to the sealing carriage. Both carriages consist of a stable VARIOKIT base frame on which a PERI UP scaffold adapted to the cross-sections was erected. This made it possible to convert and relocate the carriages quickly and cost-effectively. What’s more, the erected PERI UP scaffold served as a work platform for site personnel. In the end, the drive was controlled by an integrated hydraulic system.

Engineers from PERI Austria and the PERI Infrastructure Sales Support Unit worked together to develop a project solution that was tailored to all the customer's needs. PERI was intensively involved as early as the planning stage, providing solution-oriented input. When it came to the operational implementation stage, there was constant communication between the parties. This meant that the formwork systems could be used in an optimum fashion on the construction site and that the project was completed on schedule.

For more information on companies in this article

Related Content

  • Asphalt pavers in focus at major shows
    June 23, 2015
    Major manufacturers have unveiled new paving machines at key events in the US and Europe in recent months - Mike Woof reports The recent World of Asphalt and Intermat exhibitions have seen the introduction of several new asphalt paving machines. Major manufacturers were present at both events, with several new models being unveiled. The focus on World of Asphalt, held in the US city of Baltimore, was understandably on pavers for the North American and Latin American markets. Meanwhile new pavers on show at
  • Latest loader innovations
    January 21, 2025
    A range of loader innovations is coming to the wheeled loader segment – Mike Woof writes
  • G&Z is seeing healthy sales for pavers
    May 15, 2019
    Guntert & Zimmerman (G&Z) is experiencing healthy sales for its concrete pavers, with the factory also benefiting from upgrades. Improved manufacturing processes at the G&Z factory in Ripon, California, will help reduce delivery times for customers. This is important given the strong orders that the G&Z plant is handling at present, with the workforce also the highest for many decades. Rolf Guntert is executive vice president, sales and said, “We’re continuing to grow.”
  • Well structured maintenance
    January 4, 2013
    Major bridge maintenance and replacement projects across the world are extending the life of many impressive historic landmarks as Guy Woodford reports The Tamar Bridge, part of the main A38 trunk road linking Saltash in Cornwall with Plymouth in Devon, south west England, marked its 50th anniversary with a steel deck resurfacing project involving Stirling Lloyd's Eliminator bridge deck waterproofing system. Jointly owned by Plymouth City Council and Cornwall Council, the Tamar has a suspended length of 642