PERI for Austria’s A26 tunnels

For a project in Linz, PERI has provided what is says is Austria’s first fully hydraulic tunnel formwork carriage with a caterpillar drive
April 18, 2023 Read time: 3 mins
To construct the 1.6km-long access tunnel, PERI engineers developed the first customised and fully hydraulic special-purpose formwork carriage; sufficient to construct the different cross-sections in a total of 170 concreting sections (photo courtesy PERI SE)

The A26 project is one of the most important infrastructure projects in the Austrian city of Linz and the surrounding area. The key to success during the project implementation stage was a PERI engineering solution that was innovative, safe and efficient, coupled with comprehensive project support. The highlight of the work was that it was Austria’s first fully hydraulic tunnel formwork carriage with a caterpillar drive.

Tunnel construction to the north and south of the Danube River for the access and exit routes for the new Danube bridge has been in progress since May 2020 (see box). A large section of the tunnel runs underground so that the noise and pollution in the urban area are reduced to an even greater extent. Five different tunnel cross-sections, profile transitions, tight radii of between 50m and 750m in the bends and varying gradients were just some of the challenges that had to be overcome when constructing the 1,600m-long access tunnels for the new suspension bridge.

To overcome the challenges, Peri engineers developed Austria’s first customised and fully hydraulic special-purpose steel formwork carriage with caterpillar drive and a weight of 250tonnes. This alone was enough to produce the different cross-sections in a total of 170 concreting sections.

Given the fact that the very tight curve radii made it difficult to transport the tunnel carriage, an innovative caterpillar system was used to move it (photo courtesy PERI SE)
Given the fact that the very tight curve radii made it difficult to transport the tunnel carriage, an innovative caterpillar system was used to move it (photo courtesy PERI SE)

Given the fact that the very tight curve radii made it difficult to transport the formwork carriage, a caterpillar system was used to move it along. In addition, the formwork carriage impressed with its considerable dimensions of 8m in height and 14.5m in length as well as 10.7m in width when ready to move and 11.2m in width when ready to pour concrete.

The formwork carriage was assembled in front of the tunnel entrance under the guidance of a PERI supervisor. A short time later, the first concreting section was successfully completed, meaning that the formwork could be stripped away the very next day and the formwork carriage moved forward to the next concreting section – an efficient and time-saving solution.

Before the tunnel formwork carriage was called upon, a mobile 6m-long assembly carriage with rubber tyres and electric motor was used for the sealing work. This was followed by a reinforcement carriage adapted to the block length of 12m, the principle of which is similar to the sealing carriage. Both carriages consist of a stable VARIOKIT base frame on which a PERI UP scaffold adapted to the cross-sections was erected. This made it possible to convert and relocate the carriages quickly and cost-effectively. What’s more, the erected PERI UP scaffold served as a work platform for site personnel. In the end, the drive was controlled by an integrated hydraulic system.

Engineers from PERI Austria and the PERI Infrastructure Sales Support Unit worked together to develop a project solution that was tailored to all the customer's needs. PERI was intensively involved as early as the planning stage, providing solution-oriented input. When it came to the operational implementation stage, there was constant communication between the parties. This meant that the formwork systems could be used in an optimum fashion on the construction site and that the project was completed on schedule.

For more information on companies in this article

Related Content

  • Increasing quarry efficiency in Senegal
    November 2, 2022
    Every year, three million tonnes of basalt rock, from gravel to riprap, are taken from the Gécamines Quarries in Diack, Senegal, for use in public and maritime work sites. The quarry also produces around 500,000tonnes of limestone for use in cement factories and construction projects in the region – making the site essential for infrastructure development in West Africa.
  • Innovative diesel-electric bulldozer
    July 12, 2012
    With the launch of its innovative D7E diesel-electric bulldozer, Caterpillar has shaken up this traditionally conservative market Only rarely do product innovations come to market that can truly be described as groundbreaking, but Caterpillar's D7E fits that bill. To understand the giant leap that the D7E represents, it is important to recognise Caterpillar's long history in the bulldozer market, which is unmatched by any of its rivals. Caterpillar pioneered the crawler track with founder, Ben Holt, havin
  • Terex built for bridge paving
    November 29, 2012
    To meet a need to carry out complex modern bridge designs, the Terex Bid-Well 3600 paver is available with truss transition inserts, increasing maximum paving width from 27.4-33.5m. The inserts adjust truss depth from 914-1219mm toward the paver’s centre, reducing frame deflection and this is said to increase surface profile smoothness. Offering paving widths from 4.6-33.5m with optional transition inserts, the 3600 gives companies more versatility for paving a wide variety of bridge designs, including mult
  • Small and sustainable: Carmix concrete mixers
    July 3, 2023
    Carmix’s self-loading mobile concrete mixers have always been successful in developing markets and remote locations where there are no nearby static plants to supply jobsites. But now contractors are interested in reducing waste and carbon emissions in developed countries by using these small, mobile plants.