The first cable-stayed bridge in Nigeria will link two districts of the megacity of Lagos Nigeria’s first cable-stayed bridge, the Lekki Ikoyi Bridge in the megacity of Lagos is scheduled for completion at the end of 2012. Its striking 90m high pylon characterises the appearance of the 1,357m long bridge, which will connect two districts of the West African city, Lekki on the Lekki Peninsula and Ikoyi on Lagos Island.
September 19, 2012 Read time: 4 mins
On the left is Peri’s ACS system for the inclined front sides, while right is the RCS system (Photo: Peri)

The first cable-stayed bridge in Nigeria will link two districts of the megacity of Lagos

Nigeria’s first cable-stayed bridge, the Lekki Ikoyi Bridge in the megacity of Lagos is scheduled for completion at the end of 2012.

Its striking 90m high pylon characterises the appearance of the 1,357m long bridge, which will connect two districts of the West African city, Lekki on the Lekki Peninsula and Ikoyi on Lagos Island.

For the pylon, 298 PERI engineers combined the two ACS (automatic climbing system) and RCS (rail climbing system) climbing systems to create a project-specific, optimally-adapted formwork solution. The crane-independent working operations, together with the careful execution by the construction team of Julius Berger Nigeria, has ensured rapid construction process, in spite of the very demanding task which features a wide range of geometric and safety-related challenges.

The 722m long approach bridge is supported on 37 piers and is being constructed using the so-called Full Span Launching Method with complete precast bridge sections.

The 635m long main bridge is realised using the segmental construction method and is suspended along a length of 225m on a centrally arranged individual pylon by means of stay cables.

Due to its special shape, the pylon has a markedly filigree appearance. Up to a height of 50m it is A-shaped and then the pylon legs change to the form of a fillet and, because of this, are inclined to the outside at the top.

The legs are also not touching in the area of the cable anchorage but are subsequently connected with each other by means of crossbeams. In addition, the external dimensions of the shaft hollow sections continuously taper from 6.4m x 4.8m at the base to 4.1m x 2.4m at the narrowest point, in order to create a 3m widening on the front side at the upper end. The top of the pylon head is constructed with prefabricated components.

According to Peri the combined use of two of its self-climbing formwork systems proved to be the ideal solution for forming the pylon. For the longitudinal surfaces with the forward and reverse inclinations, as well as the fillet with a continuously changing angle of inclination, the RCS provides the optimal basis. The internal formwork of the hollow cross-section climbs with help of the RCS on rails.

“The RCS modular design allows the standard solution to be easily adapted to suit site-specific requirements. Thus, there is an articulated connection between the top and bottom climbing rails.

“As a result, the fillet section can also be climbed over at only a 77m radius in generously-dimensioned sections with 3.6m concreting cycle heights, without requiring any modification work to be carried out on the formwork and working platform,” says Peri. “The one-off inclination correction was realised by means of adjustable spindles. With the help of mobile climbing hydraulics, moving to the next respective concreting section takes place without a crane.

“The ACS technology, however, has accelerated moving operations on the front sides. Even with the inclined surfaces with angles of up to 14°, and along with likewise arranged climbing rails, the stable ACS system ensures that the high loads can be reliably carried. The two climbing technologies, optimally adapted to suit the respective construction tasks, have provided the site personnel with efficient and safe working procedures.”

An important element of the Peri overall solution is the integration of the most appropriate access technology. For this project, the connecting bridge between the climbing platforms of the two pylon shafts in particular was the contributing factor. The so-called skywalk is joined to the inner platforms by means of an articulated connection. As a result, the bridge is climbed automatically and does not have to be separately pulled up on chain hoists and re-adjusted from cycle to cycle. Ultimately, the connection of the elevator to the RCS working platform was also included in the concept developed by the Peri engineers.

For more information on companies in this article

Related Content

  • Bridging the gap in African infrastructure
    December 20, 2013
    Leading formwork manufacturers have secured some impressive contracts in Africa, as the continent’s transport infrastructure continues to improve at a rapid pace. Meanwhile, other bridgework equipment companies are also seeing their products in demand in Africa, as well as North America and Australia.
  • VST used on Portuguese bridge
    February 17, 2012
    PERI says that its new VST heavy-duty shoring tower serves as load-bearing scaffold for the large bridge and civil engineering projects. Each leg on the VST (VARIOKIT Shoring Tower) system can carry a load of around 600kN (the weight of about 60 VW Golf cars or one Leopard-2 tank), and the extremely flexible modular system can be assembled as segmental sections, towers or shoring tower frames for heights up to 40m.
  • Nigeria key connection from Lagos to Ibadan
    November 28, 2016
    Work on one of Nigeria’s busiest highways, the A5 route connecting Lagos with Ibadan, is close to completion. Lagos and Ibadan are two of the largest cities in Nigeria and as the distance between the two is comparatively short at 128km, the highway carries heavy traffic. The tender process for the project was won by Julius Berger Nigeria in 2013, with the work being handled in two sections from Lagos to the Sagamu Interchange and from the Sagamu Interchange to Ibadan. Work on the project was halted temporar
  • Peri has Polish bridge covered
    February 6, 2012
    A new bridge is being constructed across the Vistula River near Grudzi?dz, Poland, and for the foreland bridge from south-east direction, a so-called incremental launching method is being used. Two lanes, each some 556m long, are being constructed in 25 concreting cycles with standard lengths of 24m, while the formwork is 25m long and is positioned behind the bridge abutments.