Nigeria’s giant city Lagos to benefit from a new cable-stayed bridge

The first cable-stayed bridge in Nigeria will link two districts of the megacity of Lagos Nigeria’s first cable-stayed bridge, the Lekki Ikoyi Bridge in the megacity of Lagos is scheduled for completion at the end of 2012. Its striking 90m high pylon characterises the appearance of the 1,357m long bridge, which will connect two districts of the West African city, Lekki on the Lekki Peninsula and Ikoyi on Lagos Island.
September 19, 2012 Read time: 4 mins
On the left is Peri’s ACS system for the inclined front sides, while right is the RCS system (Photo: Peri)

The first cable-stayed bridge in Nigeria will link two districts of the megacity of Lagos

Nigeria’s first cable-stayed bridge, the Lekki Ikoyi Bridge in the megacity of Lagos is scheduled for completion at the end of 2012.

Its striking 90m high pylon characterises the appearance of the 1,357m long bridge, which will connect two districts of the West African city, Lekki on the Lekki Peninsula and Ikoyi on Lagos Island.

For the pylon, 298 PERI engineers combined the two ACS (automatic climbing system) and RCS (rail climbing system) climbing systems to create a project-specific, optimally-adapted formwork solution. The crane-independent working operations, together with the careful execution by the construction team of Julius Berger Nigeria, has ensured rapid construction process, in spite of the very demanding task which features a wide range of geometric and safety-related challenges.

The 722m long approach bridge is supported on 37 piers and is being constructed using the so-called Full Span Launching Method with complete precast bridge sections.

The 635m long main bridge is realised using the segmental construction method and is suspended along a length of 225m on a centrally arranged individual pylon by means of stay cables.

Due to its special shape, the pylon has a markedly filigree appearance. Up to a height of 50m it is A-shaped and then the pylon legs change to the form of a fillet and, because of this, are inclined to the outside at the top.

The legs are also not touching in the area of the cable anchorage but are subsequently connected with each other by means of crossbeams. In addition, the external dimensions of the shaft hollow sections continuously taper from 6.4m x 4.8m at the base to 4.1m x 2.4m at the narrowest point, in order to create a 3m widening on the front side at the upper end. The top of the pylon head is constructed with prefabricated components.

According to Peri the combined use of two of its self-climbing formwork systems proved to be the ideal solution for forming the pylon. For the longitudinal surfaces with the forward and reverse inclinations, as well as the fillet with a continuously changing angle of inclination, the RCS provides the optimal basis. The internal formwork of the hollow cross-section climbs with help of the RCS on rails.

“The RCS modular design allows the standard solution to be easily adapted to suit site-specific requirements. Thus, there is an articulated connection between the top and bottom climbing rails.

“As a result, the fillet section can also be climbed over at only a 77m radius in generously-dimensioned sections with 3.6m concreting cycle heights, without requiring any modification work to be carried out on the formwork and working platform,” says Peri. “The one-off inclination correction was realised by means of adjustable spindles. With the help of mobile climbing hydraulics, moving to the next respective concreting section takes place without a crane.

“The ACS technology, however, has accelerated moving operations on the front sides. Even with the inclined surfaces with angles of up to 14°, and along with likewise arranged climbing rails, the stable ACS system ensures that the high loads can be reliably carried. The two climbing technologies, optimally adapted to suit the respective construction tasks, have provided the site personnel with efficient and safe working procedures.”

An important element of the Peri overall solution is the integration of the most appropriate access technology. For this project, the connecting bridge between the climbing platforms of the two pylon shafts in particular was the contributing factor. The so-called skywalk is joined to the inner platforms by means of an articulated connection. As a result, the bridge is climbed automatically and does not have to be separately pulled up on chain hoists and re-adjusted from cycle to cycle. Ultimately, the connection of the elevator to the RCS working platform was also included in the concept developed by the Peri engineers.

For more information on companies in this article

Related Content

  • Bridge engineering worldwide
    July 1, 2013
    Guy Woodford looks at vital bridge construction, repair and inspection projects in China, Europe, North America and Australia The Heron Road Bridge in Ottawa, Ontario in Canada is a vital link within the City’s transport network, as it crosses the Rideau River, which divides the east and west parts of the City. Constructed in 1966-1967, the Heron Road Bridge is approximately 275m long and includes six lanes.
  • Bertha ends her Alaskan Way voyage in Seattle
    December 21, 2017
    Seattle's State Route 99 viaduct is coming down. David Arminas was on site. Bertha, the world’s largest diameter earth pressure balance tunnel boring machine, with a cutterhead diameter of 17.5m, is no more. Her 2.7km journey underneath the waterfront area of Seattle finished on April 4 and the power went off for the last time on an extraordinary TBM that had finally completed an extraordinary job. “A small sidewalk job would have had more impact on city traffic than we have had,” says Brian Russell a v
  • Climbing in Corpus Christi
    September 17, 2020
    The challenge for Doka on the new Harbor Bridge in Texas was to use the same formwork for each pylon despite each pylon’s different geometry.
  • Formwork solutions for bridge maintenance and repair
    January 6, 2015
    An array of innovative formwork solutions have helped in the repair and construction of key bridge links - Mike Woof writes Formwork producers are continually developing novel solutions for bridge maintenance and construction applications. Several key structures have benefited from the novel use of formwork systems, with suppliers such as Doka, PERI, Pilosio and RMD all working on important structures in recent times. In Estonia, construction work is underway on the bypass around Tartu, the country’s