A new asphalt plant in Cameroon

A Lintec CSM4000 containerised asphalt plant in Cameroon has helped with the construction of the country’s first-ever expressway linking its two largest cities, Douala and Yaoundé. The new route replaces an older roadway in use for over three decades that no longer met traffic needs.
January 27, 2023 Read time: 3 mins
A Lintec asphalt plant has played an important role in the construction of Cameroon’s first expressway

The 60km stretch of Phase 1 of the project was completed just in time for the 2021 Africa Cup of Nations football tournament, which took place in Yaoundé in early 2022.

The plant played a pivotal role in the construction of the expressway, connecting capital Yaoundé with its largest city, Douala, home to the region’s major airport and largest port.

The rapid growth of traffic on the old National Road No 3 had left it struggling to support the economic and population growth of the two cities. Once labelled the world’s sixth-most dangerous road, at one time it was even responsible for a third of the country’s crashes; the combined result of high traffic levels and neglected infrastructure.

A brand-new road was required and, in 2011, plans were confirmed for the construction of 196km of six lanes of dual carriageway, divided by a 5m-wide median strip. This would reduce the total travel distance between the two cities from 265km to 215km and allow the introduction of a 110km/h speed limit on the route.

In January 2015, China First Highway Engineering Company (CFHEC), a subsidiary of China Communications Construction Company, began work on Phase 1. This involved the construction of a 60km stretch between Yaoundé and Bibodi, plus 25km of access roads connecting it with National Road No3. At 98% progress in January 2022, the next step was to finalise construction of functional infrastructure, including five interchanges, nine toll booths, three rest areas, two service areas and 11 river crossings.

“This was such an important project that the government made opening up the 60km of Phase 1 a priority,” said Tony Liu, CEO, Lintec & Linnhoff China. “Progress had suffered from the frequent heavy rains and other setbacks.”

The mixing plant’s containerised design played an important role, protecting the working components from the harsh weather, reducing maintenance demands while also offering increased security by restricting access to just one lockable door.

The CSM4000 has an output of 320tonnes/hour of asphalt in batch sizes of 4tonnes and the containerised design enables it to be transported to other jobsites quickly. Each container houses the key components, enabling fast commissioning onsite. Offering fast erection and relocation times for large-capacity asphalt plants, these units require no concrete foundations to be prepared at the next destination due to their flat, rigid surface area ensuring high stability on compacted soil.

“It’s always rewarding to play a part in enabling such vital improvements to a country’s infrastructure,” concludes Tony. “The old National Road No 3 was slowing the country’s growth, and the problem was only worsening as it struggled to cope with rising traffic levels. Building Cameroon’s first expressway improved the lives of ordinary citizens through enhanced public safety, greater GDP and speeding up access between two major hubs.”

The cost of Phase 1 has been estimated at between US$441 million and $528 million. Phase 2 will be carried out under the PPP model for the remaining 136km to Douala at an estimated cost of $1.27 billion.

For more information on companies in this article

Related Content

  • Barrier innovation putting traffic safety and flow first
    April 3, 2014
    Cutting-edge barriers offering greater safety at the same time as limiting traffic disruption are proving in demand on busy world highways, as Guy Woodford reports Small footprint; minimum disruption after impact; lower labour costs; all said to be elements contributing to the growing popularity of the Trend terminal from Trinity Highway Products. This family of end terminals offers a range of safe and efficient solutions to barrier ends with quick and easy assembly and installation. Trinity claims th
  • US$2.5 billion boost for Cameroon
    May 20, 2024
    A US$2.5 billion investment will boost Cameroon’s development.
  • Tunnelling project under Micang Mountain
    October 15, 2018
    Equipment from XCMG has played an important role in the excavation of a new tunnel link underneath the Micang Mountain in China. The project to build the right-hand bore for the Micang Mountain tunnel on the Sichuan-Shaanxi Expressway has taken 54 months to complete. The tunnel was needed as the Micang Mountain has been a barrier to direct transportation at the junction of Hanzhong and Bazhong. This has blocked the major transport route between Sichuan and Shaanxi, preventing traffic flows across the reg
  • Papua New Guinea mends its bridges
    February 28, 2022
    Under the latest tranche of the Sustainable Highlands Highway Investment Programme, 45 of the estimated 71 bridges will be completely replaced.