Nairobi road to nowhere?

International environmental pressure groups claim a vital road in Kenya goes through parkland as Shem Oirere reports. Kenya’s Nairobi Southern Bypass, a 28.6km stretch has become the second road project in East Africa to run into problems. Designed to the Class A International Trunk Road Standard, the route has been targeted by international environmental pressure groups following Tanzania’s Serengeti Highway, which was derailed last year. The US$208 million bypass will link Mombasa Road, near Ole Sereni Ho
January 3, 2013 Read time: 4 mins
Nairobi: plans are in hand for a southern bypass

International environmental pressure groups claim a vital road in Kenya goes through parkland as Shem Oirere reports

Kenya’s Nairobi Southern Bypass, a 28.6km stretch has become the second road project in East Africa to run into problems.

Designed to the Class A International Trunk Road Standard, the route has been targeted by international environmental pressure groups following Tanzania’s Serengeti Highway, which was derailed last year.

The US$208 million bypass will link Mombasa Road, near Ole Sereni Hotel, through Nairobi National Park into Kikuyu town, on the Nairobi-Nakuru Highway at Rironi.

The bypass is said to be an answer to the capital city’s dilemma of being located in the confluence of an international trunk road that is subjected to heavy transit traffic congestion, which cuts through it for lack of a bypass or ring road, says a report.

Two service roads, a 6km Mombasa- Lang’ata road and 2.5km Lang’ata Road-Ngong’ Forest Road will be added to the bypass project.

Both service roads have the same cross-section of 0.5m soil shoulder; 2m hard shoulder; 2×3.5m carriageway; +0.5m soil shoulder.

The bypass will be dual four-lane carriage ways on 22.5m wide subgrade with a design speed of 80km/hour.

China Road and Bridge Construction Corporation (CRBC) has been awarded the engineering procurement and construction contract for the bypass link, which is considered critical in easing transport in Nairobi and to allow the movement of cargo from the port of Mombasa to neighbouring countries of Uganda, Rwanda and Burundi.

However, opposition to the project has been mounting with a group of local and international organisations saying that constructing the road through the Nairobi National Park will endanger the protected area.

The organisations under an umbrella group, Friends of the Nairobi National Park, successfully petitioned the National Environmental Tribunal in June after accusing the Ministry of Roads and the National Environmental Management Authority (NEMA) of encroachment into the park, the only protected area in the world close to a capital city.

The group is particularly opposed to the construction of the stretch between Mombasa Road and Lang’ata Road, arguing the dual carriageway will eat into the park’s land.

“The Environmental Impact Assessment [EIA] submitted to NEMA concerned a road bypass. However, the road has since been expanded into a corridor with two railway lines. Under these circumstances, the Environmental Management and Coordination Act (EMCA) requires a fresh proposal for the project and a new assessment must be taken,” the group argues in its petition to the government.

“The corridor is now 120m wide, thus encroaching even further into the National Park.

“A licence issued by NEMA on 18 February, 2011 said the bypass should not encroach on the Nairobi National Park, yet 4km of the new road is aligned in the park and therefore constitutes a breach of EMCA under which the license was issued.”

The Cabinet, chaired by President Mwai Kibaki, held on 17 May, 2012 approved excision of 60 acres (24.2 hectares) of land occupied by the park for the development of the corridor. The Cabinet said the government will find alternative suitable land for compulsory acquisition and “amalgamated to Nairobi National Park so as to maintain the size and ecological resources of the park.”

NEMA has dismissed the concerns of the environmental organisations and insisted no land belonging to the park has been encroached on by the bypass, which was commissioned by President Kibaki earlier this year.

“We wish to inform the public 2639 Kenya National Highways Authority (KeNHA) has not encroached on the park. We are not at present aware of any contravention in regard to the conditions of the EIA licence. We wish to inform the public that there has been no variation on the conditions of the licence,” said NEMA’s director general Professor Geoffrey Wahungu.

KeNHA is a state agency for developing national highways.

“The authority promotes integration of environmental considerations into development, policies, plans, programmes and projects with a view to ensuring the proper management and rational utilisation of environmental resources on a sustainable yield basis for improvement of Kenyans.”

A joint report by the contractor and KeNHA says: “The Southern Bypass may encroach on the edge of the Nairobi National Park along the existing service road running from Mombasa road through to Lang’ata Road. However, the impacts will not be adverse since the bypass follows the boundary of the national park and thus does not affect movement routes, mating grounds and corridors followed by the wild animals.”

The bypass will link up Nairobi’s trunk roads of Mombasa, Outer Ring, Lang’ata (C58), Ngong (C60), Dagoretti (C63), Thogoto (D411). It will pass over the Ondiri River before joining the Kabete Limuru road (A104) in the town of Kikuyu, south-west Nairobi.

“The project road, once completed, will provide the Nairobi metropolitan area with a vital high-speed artery for the traffic, hence facilitating prompt diversion of the transit traffic and the urban traffic movement,” the report adds.

For more information on companies in this article

Related Content

  • India’s longest tolled expressway is open to traffic
    January 2, 2013
    Earlier this year, a new expressway was opened to traffic in India, adding connectivity to the country’s road network - Mike Woof reports. India’s economic growth has fuelled a massive construction boom in the country. Road building has been set as a priority by the Indian Government to help ensure continued economic development and improve connectivity between major population centres. One major new expressway has recently opened to traffic, having been designed to international standards and provides insi
  • New US$200 million ring road to be built in Belarus capital Minsk
    May 23, 2014
    Minsk is to benefit from a new ring road that will cut city congestion - Eugene Gerden reports The government of Belarus is investing more than US$200 million in the building of a new ring road around the country’s capital Minsk, in accordance with a government decree. Implementation of the project is taking place as part of the existing large-scale state road building programme in the country until 2017, with the total cost estimated at US$5 billion. The new road will measure some 85km long and will feat
  • LagoonHull project put on hold
    February 8, 2023
    The plan by the UK city of Kingston upon Hull is to transform the city centre and river frontage running from the 2.2km-long, single-span suspension Humber Bridge.
  • Balfour Beatty wins road contract for Norfolk
    November 27, 2015
    Balfour Beatty has been awarded a €147.72 million (£104 million) road scheme by Norfolk County Council to complete works on the Norwich Northern Distributor Road (NNDR). The new road will serve Broadland, Norfolk, and improve access to North Norfolk and Norwich International Airport, with better links to Great Yarmouth and the south of the region. It will also bring relief on congested and unsuitable roads around the north and east of Norwich and improve capacity for future growth in jobs and housing.