Milling a runway surface

Milling machines from Wirtgen were used as part of the successful project to resurface a runway for Leipzig/Halle Airport in Germany
May 26, 2023 Read time: 3 mins
A team of 15 Wirtgen milling machines was used to remove the old concrete runway and taxiway surfaces at Leipzig/Halle Airport in Germany

No less than 15 planers were used for the job, one of the world’s biggest ever milling projects. The airport is one of Germany’s largest and is a key international facility for airfreight. The refurbishment of Leipzig/Halle Airport has been carried out by contractor Kutter & Co. The first phase of the project involved the removal of the concrete of the north runway and the associated taxiways within a 30-day slot. The resurfacing could only begin after the completion of this first phase, which was very challenging and involved removing 350,000tonnes of concrete reinforced with steel rebar from an area of 300,000m2.

The continuously reinforced concrete pavement (CRCP) was extremely hard and abrasive but had to be removed by this cutting method within the tight timeframe.

Concrete milling is already an established technology and technological advances mean that most grades of concrete pavement can be removed cost-efficiently. The removal of reinforced concrete pavements containing tie-bars, dowels and rebar mats is possible. At the same time, selective removal enables the separation of concrete layers with different properties and, consequently, also the reduction of contaminated material. In addition, milled concrete can be recycled without further treatment.

Concrete cancer was the reason for the need to resurface the 3,600m of runway and taxiways. This alkali-silica reaction occurs when aggregate constituents used in the production of the concrete come into contact with water. The silica reacts with the cement contained in the concrete and forms a gelatinous mass. The ensuing expansion begins to exert pressure within the concrete and can lead to an explosive reaction if untreated.

The concrete surface being removed was hard and abrasive but careful selection of cutting tools optimised wear life
The concrete surface being removed was hard and abrasive but careful selection of cutting tools optimised wear life

A project of this magnitude requires high-performance machines and optimal cutting tools for the milling drum. The Wirtgen W 250i milling machines used were carried additional ballast to ensure better traction and drum cutting performance. The machines were fitted with ECO milling drums featuring fewer picks at larger tool spacings than is the case with standard milling drums. The lower number of cutting tools reduces cutting resistance, making it possible to mill harder concrete. To meet the target of removing 350,000tonnes of concrete in 30 days, each machine had to mill off an average of over 1,100tonnes concrete/day. The first step was the fastest possible removal of the concrete surface in layers. After this, machines equipped with 3D levelling technology delivered the specified target height for the subsequent resurfacing. A total of around 60 employees from Kutter worked on the project in two shifts to meet the deadline. A total of 12,500 truck loads were required to shift the 330,000m3 of concrete removed.

“In order to get through this challenging project and deliver within the tight deadline, we constantly had 10 (and sometimes 14)

W 250 Fi class large milling machines working simultaneously in two shifts. We also always had backup machines onsite as reserves,” according to Bernhard Fischer, project manager and branch manager at Kutter

The planning of the project began at an early stage to assure a smooth process chain. Eight months before the project start, the specialists from Wirtgen and Kutter began conducting a series of tests. The experts agreed on the type of round-shank pick required to achieve optimal milling performance and long service life. This allowed accurate consumption estimates for picks and wearing parts and the procurement of sufficient stocks for the site, helping to minimise downtime once work began.

The concrete removed during the airport project in Leipzig was temporarily stockpiled close to the project site and recycled for use in the subsequent project phases as the base layer for the new runway. Short haulage distances and minimal new material requirements also reduced fuel consumption.

In addition, the Wirtgen cold milling machines themselves offered a broad spectrum of machine technologies. Optimised speed ranges controlled by Wirtgen Mill Assist and engine-temperature-controlled fan speeds helped lower fuel use. Automatic activation and deactivation of the water spraying system and milling-performance-dependent water metering meanwhile helped reduce water consumption.

For more information on companies in this article

Related Content

  • MB Crusher: Pushing attachment boundaries since 2001
    June 15, 2023
    For over 20 years, MB Crusher has offered a full line of innovative and patented jaw crusher and screener buckets and accessories for excavators, skid-steer loaders and backhoes of all sizes. Guy Woodford sat down with Alessia Valerio, MB's communications manager, at the recent 31st edition of SaMoTer in Verona to learn more about the company's latest developments and future growth plans
  • Austria's new tunnel meets safety regulations
    July 13, 2012
    New safety regulations and high traffic volumes require new tunnel construction all across Europe. Mike Woof reports Anew highway tunnel now being built in Austria will boost traffic volumes and safety standards on a key European route. The existing Pfänder Tunnel lies close to Austria's borders with Germany and Switzerland and carries a heavy traffic volume, so a new parallel tunnel is under construction to help spread this load, increasing capacity as well as safety. Stringent tunnel safety standards have
  • Wirtgen’s compact and powerful milling machine
    April 25, 2024

    Wirtgen is introducing its W 150 Fi planer, a mid-sized machine that now benefits from technology first seen in the firm’s larger mills. Power comes from a 9litre John Deere diesel delivering 313kW that meets the Tier 4 Final/Stage V emissions requirements.

    The machine is designed to cut a 1.5m width to a depth of 330mm, though it can be fitted with different width drums as well as a range of tooth patterns to suit the needs of the customer and the work being carried out.

  • Fehmarn Belt Tunnel opening set for mid-2029
    August 16, 2024
    Around 1,500 tonnes of reinforcement for casting the concrete tunnel elements are produced weekly for the 17.6km Fehmarn Belt Tunnel that will connect the Danish island of Lolland with the German island of Fehmarn.