Mabey Hire supports the Whorlton Bridge

By David Arminas June 10, 2025 Read time: 4 mins
Whorlton Bridge - one of the UK’s oldest road suspension bridges and with a timber deck supported by original iron chains – had to be completely dismantled and all components inspected, shotblasted, tested and repainted (image courtesy Maybe Hire)

Whorlton Bridge in England’s County Durham has had to be closed to traffic while a major programme of works is carried out. Every component is to be removed, refurbished and replaced.

To facilitate the works, a bespoke catenary system has been installed, with Mabey Hire’s adaptable and modular propping equipment used to construct the temporary structure.

Whorlton Bridge is one of the UK’s oldest road suspension bridges. The timber deck is supported by its original iron chains. Opened in 1831, it was originally designed to carry horse-drawn carts loaded with coal from Durham coal fields. As with many such historically important bridges, it has preservation orders on it regarding what can and can’t be done in order to maintain much of its original appearance.

After a routine inspection, the single-file road bridge was formally closed to traffic in December 2020. Subsequent assessments concluded that the structure could not withstand the effects of load combinations for pedestrians or vehicles, with the main chains and link pins also failing under loading.  

A programme of works started in early 2024 following consent from Historic England, an executive non-departmental public body of the UK government, tasked with protecting the historical environment. The entire structure of Whorlton Bridge had to be dismantled and all components inspected, shotblasted, tested and repainted. The parts will then be returned to their original position and as much of the original materials reused where possible.  

VolkerLaser, as specialist bridge refurbishment contractor, was appointed by Durham County Council to carry out the structural rehabilitation works. These were delivered in line with Historic England’s parameters and in coordination with the UK government’s Environment Agency.

Due to logistical challenges, it was decided that while the entire structure was dismantled piece by piece, a temporary catenary system would be installed to support the existing cables below the deck. Designed by CaSE Civil & Structural Engineering, the temporary cable crane structure used a range of Mabey Hire’s propping equipment, including its Mass 50, System 160 and Mat 125 products (see box).

“Working with CaSE Civil & Structural Engineering, we knew that we wanted a proprietary system that offered an adaptable ‘off the shelf’ solution,” explained Chris McHutchison, senior project manager at VolkerLaser. “We were attracted to Mabey Hire not only for their comprehensive and readily available product portfolio but also the detailed technical information made available. Thanks to the modular nature of the kit [temporary cable crane structure], we were able to easily interchange it with other systems, as well as minimise on-site fabrication due to the equipment arriving ready to install.”

The temporary cable crane is formed of two pivoted towers, which stand on the north and south sides of the bridge. It features five suspended catenary cables, spanning around 95m between the two towers.

“While this was the first time working with Mabey Hire in my current role at VolkerLaser, I have worked with them numerous times throughout my time in the industry,” said McHutchison. “Whorlton Bridge certainly… presented a lengthy and challenging early design process as a result of the bridge’s listed status. We had to clearly demonstrate our proposed plans and gain approvals from Historic England and other parties.”

Mabey assisted VolkerLaser with design and technical advice, including recommendations on what equipment would be best for the project requirements. Maybe has been working alongside VolkerLaser teams to gain sign-off on the proposed temporary works scheme.

The cable crane was successfully installed on site last September, with works to remove the timber deck, supporting beams, hangars and rods underway. The components will then be moved to a secure workshop for inspection and refurbishment.

With one of the largest range of temporary propping systems for hire, Mabey Hire’s solutions range from 100kN to 8000kN load capacities. These are used to facilitate modular towers, façade retention schemes and propping and shoring.

Meanwhile, for over 30 years, VolkerLaser, based in the English city of Worcester, has been working to protect, repair, strengthen and refurbish the built environment for clients across the UK construction industry. The company’s structural solutions include bridge deck waterproofing, expansion joints, concrete repair and cathodic protection works, steel repair and strengthening work, carbon fibre and temporary works, jacking and bearing replacement. VolkerLaser also provides specialist lightweight decking and access solutions, as well as being specialists in long bridge and cable refurbishment.

CaSE Civil & Structural Engineering was founded in Sydney, Australia, in 2017 and now has offices in Australia’s Queensland, Victoria and New South Wales states as well as in New Zealand, US, Brazil, UK and Spain. The company’s many contracts include the Australian West Gate Tunnel Project worth AUS$2.7 billion - a partnership between the Victoria states government and Transurban and for which CaSE & Pike Design was awarded several bridge engineering and temporary works packages.
 

For more information on companies in this article

Related Content

  • Formwork developments in bridge construction
    February 23, 2012
    Major infrastructure projects worldwide are relying on innovative formwork solutions for speed and safety as Patrick Smith reports. The 970m long cable-stayed Golden Ears Bridge crossing the Fraser River in Vancouver, Canada, is the core element of a six-lane, highway project near the Canadian west coast.
  • Collaborative approach is delivering the Queensferry Crossing
    March 28, 2017
    The Queensferry Crossing forms the centrepiece of a major upgrade to the cross-Forth transport corridor in the east of Scotland. It will be the longest three-tower, cable-stayed bridge in the world and represents a Scottish Government capital investment of more than €1.5 billion. The 2.7km Queensferry Crossing is alongside the Forth Road Bridge and will carry the M90 motorway across the Firth of Forth between Lothian, at South Queensferry, and Fife, at North Queensferry. Each of the three towers are 207m
  • Mini-bridge aids Forth repairs
    July 17, 2012
    An engineering "first" means that rehabilitation work on a vital Scottish bridge built over 40 years ago can be carried out smoothly A new report to the Forth Estuary Transport Authority (FETA) in Scotland recommends appointing Balfour Beatty Civil Engineering of Edinburgh as 'preferred bidder' to carry out the scheduled replacement of the bridge's main expansion joints in 2009. However, the report to the bridge authority says the tender price of £13.7 million (US$21.3 million) is some £5 million ($7.8 mill
  • Formwork solutions for bridge maintenance and repair
    January 6, 2015
    An array of innovative formwork solutions have helped in the repair and construction of key bridge links - Mike Woof writes Formwork producers are continually developing novel solutions for bridge maintenance and construction applications. Several key structures have benefited from the novel use of formwork systems, with suppliers such as Doka, PERI, Pilosio and RMD all working on important structures in recent times. In Estonia, construction work is underway on the bypass around Tartu, the country’s