Mabey Hire supports the Whorlton Bridge

By David Arminas June 10, 2025 Read time: 4 mins
Whorlton Bridge - one of the UK’s oldest road suspension bridges and with a timber deck supported by original iron chains – had to be completely dismantled and all components inspected, shotblasted, tested and repainted (image courtesy Maybe Hire)

Whorlton Bridge in England’s County Durham has had to be closed to traffic while a major programme of works is carried out. Every component is to be removed, refurbished and replaced.

To facilitate the works, a bespoke catenary system has been installed, with Mabey Hire’s adaptable and modular propping equipment used to construct the temporary structure.

Whorlton Bridge is one of the UK’s oldest road suspension bridges. The timber deck is supported by its original iron chains. Opened in 1831, it was originally designed to carry horse-drawn carts loaded with coal from Durham coal fields. As with many such historically important bridges, it has preservation orders on it regarding what can and can’t be done in order to maintain much of its original appearance.

After a routine inspection, the single-file road bridge was formally closed to traffic in December 2020. Subsequent assessments concluded that the structure could not withstand the effects of load combinations for pedestrians or vehicles, with the main chains and link pins also failing under loading.  

A programme of works started in early 2024 following consent from Historic England, an executive non-departmental public body of the UK government, tasked with protecting the historical environment. The entire structure of Whorlton Bridge had to be dismantled and all components inspected, shotblasted, tested and repainted. The parts will then be returned to their original position and as much of the original materials reused where possible.  

VolkerLaser, as specialist bridge refurbishment contractor, was appointed by Durham County Council to carry out the structural rehabilitation works. These were delivered in line with Historic England’s parameters and in coordination with the UK government’s Environment Agency.

Due to logistical challenges, it was decided that while the entire structure was dismantled piece by piece, a temporary catenary system would be installed to support the existing cables below the deck. Designed by CaSE Civil & Structural Engineering, the temporary cable crane structure used a range of Mabey Hire’s propping equipment, including its Mass 50, System 160 and Mat 125 products (see box).

“Working with CaSE Civil & Structural Engineering, we knew that we wanted a proprietary system that offered an adaptable ‘off the shelf’ solution,” explained Chris McHutchison, senior project manager at VolkerLaser. “We were attracted to Mabey Hire not only for their comprehensive and readily available product portfolio but also the detailed technical information made available. Thanks to the modular nature of the kit [temporary cable crane structure], we were able to easily interchange it with other systems, as well as minimise on-site fabrication due to the equipment arriving ready to install.”

The temporary cable crane is formed of two pivoted towers, which stand on the north and south sides of the bridge. It features five suspended catenary cables, spanning around 95m between the two towers.

“While this was the first time working with Mabey Hire in my current role at VolkerLaser, I have worked with them numerous times throughout my time in the industry,” said McHutchison. “Whorlton Bridge certainly… presented a lengthy and challenging early design process as a result of the bridge’s listed status. We had to clearly demonstrate our proposed plans and gain approvals from Historic England and other parties.”

Mabey assisted VolkerLaser with design and technical advice, including recommendations on what equipment would be best for the project requirements. Maybe has been working alongside VolkerLaser teams to gain sign-off on the proposed temporary works scheme.

The cable crane was successfully installed on site last September, with works to remove the timber deck, supporting beams, hangars and rods underway. The components will then be moved to a secure workshop for inspection and refurbishment.

With one of the largest range of temporary propping systems for hire, Mabey Hire’s solutions range from 100kN to 8000kN load capacities. These are used to facilitate modular towers, façade retention schemes and propping and shoring.

Meanwhile, for over 30 years, VolkerLaser, based in the English city of Worcester, has been working to protect, repair, strengthen and refurbish the built environment for clients across the UK construction industry. The company’s structural solutions include bridge deck waterproofing, expansion joints, concrete repair and cathodic protection works, steel repair and strengthening work, carbon fibre and temporary works, jacking and bearing replacement. VolkerLaser also provides specialist lightweight decking and access solutions, as well as being specialists in long bridge and cable refurbishment.

CaSE Civil & Structural Engineering was founded in Sydney, Australia, in 2017 and now has offices in Australia’s Queensland, Victoria and New South Wales states as well as in New Zealand, US, Brazil, UK and Spain. The company’s many contracts include the Australian West Gate Tunnel Project worth AUS$2.7 billion - a partnership between the Victoria states government and Transurban and for which CaSE & Pike Design was awarded several bridge engineering and temporary works packages.
 

For more information on companies in this article

Related Content

  • Bridge engineering worldwide
    July 1, 2013
    Guy Woodford looks at vital bridge construction, repair and inspection projects in China, Europe, North America and Australia The Heron Road Bridge in Ottawa, Ontario in Canada is a vital link within the City’s transport network, as it crosses the Rideau River, which divides the east and west parts of the City. Constructed in 1966-1967, the Heron Road Bridge is approximately 275m long and includes six lanes.
  • Innovations in formwork aid project completion
    February 14, 2012
    Innovative formwork solutions are helping to get projects completed on or before time, meaning savings in time and money as Patrick smith reports. The use of flexible, modular formwork to create innovative structures out of concrete is helping to increase productivity and thus drive down completion time and costs.
  • Mabey helps deliver bypass in congested UK city
    February 9, 2018
    The new Aberdeen Western Peripheral Route will cut journey times, reduce pollution costs and improve safety. Mabey has announced that its UK Hire business is working on a vital project to build a 58km bypass in Aberdeen. The Aberdeen Western Peripheral Route/Balmedie-Tipperty (AWPR/B-T) project is being delivered by Transport Scotland in partnership with Aberdeen City Council and Aberdeenshire Council. Aberdeen Roads Limited was awarded the contract to build the AWPR/B-T in December 2014 and has appointed
  • Advanced method for South Africa bridge construction
    May 16, 2016
    A sophisticated construction method has been used for the first time in South Africa for a suspended bridge project This novel method of bridge construction was used on a major road upgrade project for the South African National Roads Agency Limited (SANRAL). Main contractor Lonerock Construction, and subcontractor Tzandeboo Construction, used RMD Kwikform’s Megatruss system to construct a 60m-long bridge while suspended mid-air over the live N4 highway. Lonerock Construction’s US$8.5 million (R132