Skip to main content

The M-10 motorway to be a first PPP for Belarus

As Belarus opts for its first PPP, contractors should take note of contract nuances when working in CIS countries, explains Ove Arup’s Steve Gilpin Belarus is part of the Commonwealth of Independent States (CIS), a regional governmental organisation of 10 ex-Soviet bloc countries. The CIS includes Russia as well as Turkmenistan which is an associate member. Some countries, including Georgia, were part of the CIS but have left the organisation. Arup’s projects in CIS countries have been commissioned by
July 3, 2019 Read time: 4 mins
Steve Gilpin of Ove Arup warns that it is crucial to be careful of translations when it comes to contract work
%$Linker: 2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 9781 0 oLinkInternal <span class="oLinkInternal ">RSS</span> Events (Diary) false /rss/events/ true false%>As Belarus opts for its first PPP, contractors should take note of contract nuances when working in CIS countries, explains Ove Arup’s Steve Gilpin


Belarus is part of the Commonwealth of Independent States (CIS), a regional governmental organisation of 10 ex-Soviet bloc countries. The CIS includes Russia as well as Turkmenistan which is an associate member. Some countries, including Georgia, were part of the CIS but have left the organisation.

1419 Arup’s projects in CIS countries have been commissioned by a mix of international developers, national or local authorities and local private companies and developers. For a European company the requirements, both of the contract and the invoicing, can appear extremely bureaucratic – as there can be an abundance of official stamps.

Regardless, opportunities exist. Arup, which has an office in Moscow, has been working in the five five 'stans of Central Asia (Turkmenistan, Uzbekistan, Tajikistan, Kyrgyzstan and Kazakhstan) since 1993 - and Pakistan since 1951. Arup also maintains contacts in other CIS countries where it has no permanent office. The company can boast that it has, over the years, notched up around 1,700 successful projects.

Designers need to be registered and this varies among CIS member states. For example, in Kazakhstan there are three levels of expertise for which designers can be registered. Contractors need to be registered for the specific element of construction they will be undertaking.

What CIS countries have in common is their Soviet-era split planning approval and permitting process. Some countries, however, are looking to adopt either their own systems or use some of the systems and standards of other countries.

The permitting system used most commonly throughout the CIS is called the TEO - technical and economic justification system. The TEO covers design, costs for construction, operation and maintenance, any correspondence with affected parties such as rail or utility providers, and an production of an Environmental Impact Assessment (EIA) undertaken to local standards. Within the TEO there are three permitting stages - feasibility, architectural and construction.

Whatever the issues may be with the TEO, it has the advantage of universality throughout the CIS. Once a company becomes acquainted with the system, employees can use their knowledge in any CIS country.

A word of caution, however. The TEO is often translated into English as “feasibility study”. As such, any reference in a contract to creating or updating a ‘feasibility study’ needs to be carefully reviewed.

One example of this is in the conversion of a highway project for which a TEO has been produced, assuming a traditional remeasure procurement method, into a public-private partnership (PPP). If an international finance institution such as the European Bank for Reconstruction and Development (EBRD) or the World Bank’s International Finance Corporation (IFC), is considering the project as a potential PPP, the institution’s contract may stipulate: “undertake a feasibility study”.

Most consultants would assume this to mean that they should do a feasibility study of how the project would work as a PPP. But a translation of the contract for a client may be “undertake a TEO”. As such, the local client may expect a full TEO to be produced or the existing TEO to be updated. All parties should, therefore, be aware that the translated terms could have a different meaning than the finance institution intended and what the consultant has priced to undertake.

The cost side of a TEO needs to be developed as a “cMeTa” (estimate) based on a specific procedure developed in the Soviet period and uses prevailing government construction indices. This is a very specialised task and cannot be taken lightly. In Belarus, for example, the estimate goes to the detail of the length of reinforcement tie wire required.

The TEO contains an environmental assessment impact study and can be very thorough, although they are seldom completed to the requirements of the financial institution. As such, additional studies or consultations are likely to be needed. The time required for these additional consultations should be factored into the procurement programme such that by the time the preferred bidder is announced the ESIA (environmental social impact study), RAP (request for alternative procurement), SEP (safety equipment procurement) only require contractor specific data to be included to make them sufficiently complete for the financial institution’s required disclosure.

As with any project, local knowledge is paramount to success. Working in the CIS is, in many ways, no different from working anywhere else in the world. A company needs to be aware of local practices, tax and payment requirements and permitting systems. Arup is proud to have been involved with many completed projects and involved in many more that are planned and ongoing.

%$Linker: 2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 9781 0 oLinkInternal <span class="oLinkInternal ">RSS</span> Events (Diary) false /rss/events/ true false%>

For more information on companies in this article

Related Content

  • Tesab 1200TC tracked cone crusher with Cat C13 engine
    March 26, 2013
    New to the Tesab range of crushing and screening equipment is the 1200TC tracked cone crusher, a development that completes the company’s range of crushing and screening equipment. The 1,200mm diameter cone crusher unit is a well proven design having established itself in static applications in Scandinavia and Australasia.
  • Saltec brand Torgar is offering innovative access solutions
    January 6, 2017
    New access solutions have been developed for the TORGAR range by Spanish specialist Saltec. The new compact PT-02 industrial lift has been developed to meet the needs of the tower crane sector, for high mast applications. Meanwhile the new PL-20 is a platform type access machine that offers a 2tonne payload. The PW-6/12 work platform is the firm’s light and robust access machine that is specially designed for renovation jobs, but with a maximum platform length of 24.6m, platform width of 0.7m and maximum (s
  • Saltec brand Torgar is offering innovative access solutions
    March 27, 2013
    New access solutions have been developed for the TORGAR range by Spanish specialist Saltec. The new compact PT-02 industrial lift has been developed to meet the needs of the tower crane sector, for high mast applications. Meanwhile the new PL-20 is a platform type access machine that offers a 2tonne payload. The PW-6/12 work platform is the firm’s light and robust access machine that is specially designed for renovation jobs, but with a maximum platform length of 24.6m, platform width of 0.7m and maximum (s
  • Tenders open for England’s A66 northern trans-Pennine route
    October 31, 2019
    A €52 million contract to design the transformation of the A66 northern trans-Pennine route in England is now up for grabs, according to Highways England. A tender is open for dualling the remaining single carriageway sections of the A66 which links the M6 motorway at Penrith in Cumbria and the A1(M) motorway) at Scotch Corner in North Yorkshire. The formal notice for the A66 Preliminary Designer, Construction Technical Advisor and Supervision tender process has been published in the Official Journal of