Liebherr’s dozer factory in Austria

Liebherr is seeing strong demand for earthmoving machines, with healthy output at its earthmoving equipment factories
By Mike Woof May 4, 2022 Read time: 3 mins
The majority of machines made in the LWT facility are yellow for Liebherr or Green for Claas, although customers can order special colours such as this black dozer

As with most (if not all) of the major global manufacturers, Liebherr is seeing strong demand for its construction machines at present. With production and sales having been initially constrained during the COVID-19 pandemic as some customers held off from purchase decisions, there has been a pent-up demand for construction equipment. Many governments are investing in infrastructure development as a means to boost economic growth in the wake of the pandemic, further boosting demand for machines.

One of the earthmoving machine factories benefiting from that strong demand at present is the Liebherr Werk Telfs (LWT) facility in Austria, perhaps best known for its hydrostatic bulldozers.

Liebherr has been making bulldozers at the plant in Telfs since 1976 and the factory now sits on a 179,200m2 site and employs close to 800  staff, while turnover for the factory was around €270 million in 2021.

The company has invested heavily in the factory in recent years, buying new machine tools and extending the production facility. And a new building is being constructed at present that will house a logistics centre at a cost of around €35 million.

The new machine tools help ensure quality and the factory’s IGM welding robot is one of the most sophisticated in Europe, while more than €1 million was spent on an efficient dust extraction system to ensure the plant maintains a clean environment.

Since 2010, the number of units produced at the LWT facility has increased 330%. A substantial portion of this increase is due to the facility having started manufacturing the high volume telehandler models at the plant, although the firm has also increased its share of the dozer market.

Customers can order equipment machine-control ready at the factory, with a choice of technologies from Leica Geosystems, Topcon or Trimble
Customers can order equipment machine-control ready at the factory, with a choice of technologies from Leica Geosystems, Topcon or Trimble

Dozers were the first product to be built at the factory, with the crawler loaders and sideboom pipelayers coming into production afterwards. In more recent times the LWT facility also started building the firm’s telehandler models. Some of the telehandlers are sold as Liebherr machines, but the majority are badged as Claas units under a supply agreement Liebherr established with the German firm some years ago.

The LWT facility produced some 1,940 units in 2021, although output was constrained by the availability of some components. The factory is used to make seven dozer models from the 16tonne class PR 716 up to the 73tonne PR 776 as well as the LR 626 and LR 636 crawler loaders and two pipelayers.

The volume production machines from the LWT facility are the eight telehandler models, which are available in 26 different variants with lifting heights from 6-10m and load capacities up to 6tonnes.

Up to 70% of the production at the LWT facility is for the telehandler units while the majority of the remainder is for the dozers.

Around 3,000tonnes of steel is used for production every month and during 2021 the plant produced 1,142 of the telehandlers and 798 crawler dozers, loaders and pipelayers.

The telehandler line produces around five units/day, with around 80% being badged in Claas colours and the remaining 20% being sold as Liebherr machines.

The assembly line operates on a single shift/day, although there is a double shift system for some preparation tasks. Each dozer is assembled individually for the customer and there are no units built for stock. For 2022 customers are facing long lead times on all of the models.  Liebherr estimates it could fulfil orders for up to 30% more telehandlers if it could source the components. Katrycz said, “There is definitely a backlog because of COVID-19, but we can’t say how long it will last.”

For more information on companies in this article

Related Content

  • Wacker Neuson builds on Caterpillar link
    November 14, 2012
    Bolstered by building machines for Caterpillar and high demand for its VDS equipped excavators, Wacker Neuson has greatly increased its compact equipment building capability in Linz - Nick Johnson reports At a time when some other construction equipment makers have still scaled back their operations following the global economic crisis, Wacker Neuson has been busy building new facilities and increasing its production capacity. Last month the company officially opened its new compact equipment production fac
  • Liebherr upgrading wheeled loader output
    July 17, 2024
    Liebherr is upgrading its wheeled loader production capacity.
  • Machine control technology evolving fast
    February 8, 2012
    The machine control market is evolving fast and is increasingly becoming part of a much wider construction site management concept, Mike Woof reports. Machine control technology has come a long way in the past 20 years and the development of 2D and 3D systems has been rapid in the construction sector.
  • Liebherr’s PR 736 dozer launched on US market at Conexpo 2014
    January 6, 2017
    The PR 736 dozer being introduced to the US market at Conexpo 2014 is the first model in Liebherr’s new Generation 6 series and is said to offer customers increased efficiency and lower fuel consumption and CO2 emissions. Among the innovations on the Generation 6 machine models, including the 20-25tonne service weight PR 736, are electronic travel speed regulation with an integral eco-function, and pro-active power control.