Germany’s Rader High Bridge spanning the Kiel Canal along Germany’s A7 motorway is to be replaced and widened over the next few years. Eighteen Liebherr cranes are handling the lifting.
By David Arminas December 10, 2024 Read time: 4 mins
Assembly in the water: the first crane used for the replacement of the Rader High Bridge was assembled on the new pile cap of the first bridge pier (image courtesy Liebherr)

The replacement of the Rader High Bridge in Schleswig-Holstein, near the Danish border, is one of the largest bridge modernisation projects underway in Germany. The bridge, built in 1972, spans the Kiel Canal and is part of the A7 motorway.

Measuring just under 1.5km-long, it is Germany's second-longest steel road bridge and plays an important role in the flow of traffic to and from Denmark and the Scandinavian peninsula. But the bridge is approaching the end of its useful life as a result of high traffic volumes; a rebuild and simultaneous widening of lanes has become necessary as result of increased vehicle usage.

In water, on land

Strong support for this major construction project is being provided by 18 Liebherr cranes from the rental fleet of the contractor Friedrich Niemann, based in Kronshagen near Kiel. Five fast-erecting cranes, two 65 K.1s and three 81 K.1s, are on site to assist with the foundations. The new bridge piers are being built with the help of six 125 EC-B and seven 150 EC-B flat-top cranes.

Conditions on site are responsible for some spectacular crane assemblies. The first crane to arrive on the construction site, a 125 EC-B, was assembled at the end of 2023. Assembly took place in the waters of Lake Borgstedt, where the crane stood on the first pier’s pile cap secured by foundation anchors. This involved working with a Liebherr crawler crane from Nenzing (Austria).

The 250-tonne LR 1250 crawler crane required for the assembly was positioned on a floating platform between the crane site and the ferry that was used for transporting parts. The flat-top crane reached a hook height of 44m. Three 125 EC-B cranes were also assembled using the 250-tonne crawler crane, from its floating platform on the water.

The cranes were initially assembled at a height of 30m and then climbed to their final hook height of 50m using hydraulic climbing equipment. This allowed them to work some 15m above the height of the roadway.

A 150 EC-B 8 Litronic started by working on the bridge pier on land. But the progression of the site required the crane to be moved to a new location. At the end of this June, it was time: the flat-top crane was moved from the north side of the bridge to the next bridge column and reassembled in the water. The disassembled crane was transported to its new location on a ferry and put back together again with the help of a 220-tonne crawler crane on a floating platform.

Once assembled, it climbed to a hook height of around 50m and reached a jib length of 40m. The crane has the capacity to lift up to eight tonnes.

Liebherr project department

Precise planning was required in advance for the use of the cranes and Liebherr’s own project department for large and special projects (Tower Crane Solutions, TCS) provided valuable support. A major challenge lay in the cranes being assembled by the crawler crane on the floating platform.

As the permissible hook height of the crawler crane on the floating platform was restricted, the assembly height had to be kept as low as possible. However, a certain tower height was also necessary so that the cranes could be climbed. Various options and tower systems were therefore investigated in the run-up to the project in order to find the best solution.The configuration of the tower combinations was another major issue prior to planning crane operations; it was essential to prevent the towers from colliding with the newly erected bridge piers and any potential tower deformations.

Consequently, the fast-erecting cranes are only partly using their maximum hook height. The two 65 K.1 cranes are in use with their tower retracted as they slew under the bridge and the three 81 K.1 cranes are also assigned to work under the bridge as well as at maximum height above it.

The 13 flat-top cranes are assembled in a free-standing position on crosses and foundation anchors; some of them are set in concrete in the water. They are working with a hook height of between 49m and 68m. The hydraulic climbing equipment has been provided by the Liebherr Tower Crane Center, the Liebherr partner for special crane hire, crane components and used machines direct from the manufacturer.

 

For more information on companies in this article

Related Content

  • Barge-mounted Manitowoc MLC300 lists Illinois bridge into place
    June 28, 2018
    The reduced footprint and floating counterweight meant that it is much more efficient for contractors to barge-mount a crawler crane. The crane can be on smaller water-based barges because the machine automatically adjusts its centre of gravity for each lift. Kraemer North America recently used an MLC300 to help replace an 84-year-old truss bridge, the 756m Savanna-Sabula Bridge near Savanna, in the US state of Illinois. The Savanna–Sabula Bridge was a truss bridge and causeway crossing the Mississippi Ri
  • Norway’s massive Rogfast Tunnel project
    December 11, 2018
    The world's longest and deepest road tunnel is underway in western Norway - Adrian Greeman reports
  • Controversial Russian bridge opens
    August 10, 2018
    The first stage of a controversial Russian bridge project is now complete, with the link having been opened to use by cars and buses. The Kerch Strait bridge spans the Black Sea, connecting Russia’s Taman Peninsula in Krasnodar with Crimea, the latter having been controversially annexed by Russia from Ukraine in 2014. The official opening of the 19km-long bridge was carried out by Russia’s president, Vladimir Putin, who drove across the link in a Russian-manufactured Kamaz truck to reach the city of Kerch.
  • Forming iconic structures
    July 18, 2012
    Specially designed and constructed formwork is being used to create some iconic bridges worldwide The Golden Ears Bridge over the Fraser River will unite the municipalities of Richmond, New Westminister and Delta in the scenic British Columbia province of Canada. The bridge, part of a CAD$800 million (US$670 million) project, is an 'extra dosed' cable stayed bridge, which means the deck will be supported by both cables and the structure itself. This design reduces the overall height of the two towers as req