Kosovo motorway wins IRF award

Kosovo’s Route 7 Motorway is an 84km dual carriage motorway that will span Kosovo from the southwest border with Albania to the capital city of Pristina, tying the heart of Kosovo to the Albanian port city of Durres. This motorway is part of the pan-European motorway network for Southeast Europe and provides a key trade corridor. In November 2011, Bechtel-Enka General Partnership (BEGP) successfully delivered 38km to the people of Kosovo, only 19 months after the contract award. The second main achievement
May 30, 2013 Read time: 3 mins
Kosovo’s Route 7 Motorway is an 84km dual carriage motorway that will span Kosovo from the southwest border with Albania to the capital city of Pristina, tying the heart of Kosovo to the Albanian port city of Durres. This motorway is part of the pan-European motorway network for Southeast Europe and provides a key trade corridor. In November 2011, 4138 Bechtel-5252 Enka General Partnership (BEGP) successfully delivered 38km to the people of Kosovo, only 19 months after the contract award. The second main achievement came in November 2012 when a further 18.4km of motorway was opened after only 8 months of construction. BEGP is proud to have delivered this ‘fast track’ motorway while maintaining a high level of both safety and quality.

There were three major obstacles to be overcome upon contract signing in April 2010. The first obstacle was that the final design was not complete. With construction needing to start almost immediately to deliver the first three sections within the client’s required timeframe, BEGP had to begin construction while working in parallel with the designer to manage the delivery of the design to support these construction activities on site. The second obstacle was that while the expropriation process was underway, the government had not yet taken the final decision and therefore had not expropriated any of the land for construction. BEGP worked closely with the client’s expropriation teams to expedite the process in order of priority, so that major structures and areas of large excavation on the project's critical path could begin immediately. The third obstacle was the long and very cold winter weather conditions.

Staffing a major Infrastructure project is always a key challenge success. In total, BEGP trained 3733 individuals from 14 different countries including an unskilled majority from the local Kosovo community. The project also implemented a “buddy” system whereby employees who have been on the project less than 90 days are given a different color helmet and work closely with more experienced members of the team to ensure their safety on site and the quality of their product.

In order to maintain the required high quality standards and in addition to the craft training program, BEGP developed 172 procedures within the first 6 months of work. Development of the Quality Management System (QMS) was jointly completed by the Quality and Construction Departments with input from all department leads to ensure completeness.

The Kosovo Motorway Project won the 2012 Global Road Achievement Award for Program Management. Visit the 2462 IRF website for additional GRAA information, including how to enter a project into the 2013 competition.

Are you up for the challenge?

Since their launch, the IRF GRAAs have provided global notoriety to over 100 projects in 30 countries and highlighted how road programs help achieve broader development goals. The IRF is now taking applications across 11 categories. The deadline for submitting an entry is June 30, 2013.

Find out more online at %$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal www.irfnews.org/awards www.irfnews.org/awards false http://www.irfnews.org/awards false false%> or contact: Magid Elabyad at %$Linker: 2 Email <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkEmail [email protected] [email protected] false mailto:[email protected] true false%> or +1 703 535 10012914










For more information on companies in this article

Related Content

  • Kosovan highway ahead of schedule
    April 25, 2012
    In Kosovo, work is pushing ahead of schedule on the Route 7 highway to link capital Pristina with the Albanian border. Sections of the 120km highway have been opened, one year ahead of schedule. An official opening of several sections of the highway has been carried out by Kosovan leaders, including Prime Minister Hashim Thaçi, President Atifete Jahjaga, and members of Parliament, along with Albanian Prime Minister Sali Berisha and US representatives Eliot Engel (D- NY) and Gary Peters (D-MI) joined thousan
  • Nigeria president Goodluck Jonathan to open 1st IRF Africa Regional Congress
    May 28, 2014
    Nigeria president Goodluck Jonathan will deliver the opening address at the 1st International Road Federation Africa Regional Congress being held in Abuja on 4 June 2014. Dr Jonathan has been Nigeria's head of state since 2010, having previously served as federal vice president, as well as governor of the state of Bayelsa. Welcoming Dr Jonathan’s confirmation as opening address speaker, IRF president & CEO Patrick Sankey said, "President Jonathan's presence is an extraordinary honour for our industry. It
  • Bechtel Enka opens first section of Pristina-Skopje motorway
    October 29, 2015
    The first part of the €600 million Arber Dzaferi motorway between Pristina, the capital of Kosovo and Skopje in Macedonia, has opened to traffic. US-Turkish consortium Bechtel Enka is contractor for the 60km road that will eventually link Pristina, capital of the former Serbian province Kosovo, and the city of Skopje, capital of Macedonia, a former Yugoslav republic. The road - numerically Route 6 – is Kosovo’s second motorway and is named after the prominent Albanian intellectual and politician from
  • Plans for Serbia-Kosovo highway
    March 10, 2016
    Plans are moving forward for a new highway that will link Kosovo’s capital Pristina with Belgrade, the capital of neighbouring Serbia. The project is of importance as it reveals the continued improvement in diplomatic relations between Serbia and Kosovo. Serbia’s Ministry of Construction says that work on the route will commence in the first half 2017. The financing model for the project has yet to be established. Talks are being held with European partners. The cost of the project has not yet been revealed