Indonesia toll road completed on schedule

The construction of the Cipali Toll Road in Indonesia has been completed on time, despite numerous challenges during its construction. The Cipali Toll Road forms part of a larger network, the Trans-Java Toll Road that connects key freeways in Jakarta and beyond. The Trans-Java Toll Road is of enormous importance to Indonesia as it runs for 653km and reduces the existing route by 40km.
May 16, 2016 Read time: 3 mins
With its output of 150tonnes/hour, the plant had extra capacity as it was producing 120tonnes/hour for most of the time during the project
A new toll road in Indonesia will help transportation and boost the local economy

The construction of the Cipali Toll Road in Indonesia has been completed on time, despite numerous challenges during its construction. The Cipali Toll Road forms part of a larger network: the Trans-Java Toll Road that connects key freeways in Jakarta and beyond. The Trans-Java Toll Road is of enormous importance to Indonesia as it runs for 653km and reduces the existing route by 40km.

The Cipali Toll Road, stretching from Cikopo in the west to Palimanan in the east, is a crucial segment in the network and is carrying around 30,000 vehicles/day. As a result, the construction of this important stretch of road was followed closely by government officials and businesses.

But despite the numerous challenges, the project was finished on time and within budget. A key player in meeting both goals was asphalt producer PT. Dirgantara Yudha Artha, based in Bandung. The firm installed an 6791 Ammann JustBlack 150 plant to help finish the project, which was used to supply asphalt for key portions of the work.

Development work for the 110km Cipali Toll Road required around-the-clock asphalt production, with the plant output sometimes reaching close to 3,000tonnes/day. Meeting deadlines was no small task and the asphalt production set the pace for the rest of the team.

Experience was crucial and offered two major benefits to the production of the asphalt. This ensured the plant team was familiar with the required mixes, with only three grades being used: ACBC, ACWC and ATB. The second benefit was the team’s experience in making quick, frequent mix adjustments simplified the work for the minimal switches on the toll road project. Production was able to continue when a new mix was needed.
Capacity was also important as Dirgantara Yudha Artha used an Ammann JustBlack asphalt batch plant with a capacity of 150tonnes/hour. For most of the time the plant produced about 120tonnes/hour, but the extra capacity allowed additional production when required.

Capacity also involves reliability and one reason Dirgantara Yudha Artha purchased this plant was for its dependability. The Ammann JustBlack plant produced 120tonnes/hour for 20-hour shifts, providing an average of 2,400tonnes/day.

The company’s use of the JustBlack plant also brought savings on fuel of around 20%, according to Dirgantara Yudha Artha. When the project was complete, Dirgantara Yudha Artha had produced enough mix to cover 55km of the 110km of multilane highway. Production had gone well and set the pace for the entire project.

Privately owned by Jahja Tear Tjahjana, Dirgantara Yudha Artha has  five asphalt plants and works on general construction, roads, tolls roads and airport runways.

For more information on companies in this article

Related Content

  • The dark arts of asphalt production
    January 5, 2017
    Asphalt production is a complex process featuring many variables - Mike Varner, chief engineer at Astec Inc discussed methods with Mike Woof Asphalt production in a black art in more ways than one. It involves a complex process of mixing bitumen with aggregates under temperature and optimising this operation is crucial to maximise quality. But with so many variables, determining exactly what is going on inside an asphalt plant involves extensive research, sophisticated computer modelling and the use of a
  • Peru’s Oyón -Ambo Highway presents challenges
    August 30, 2022
    Peru’s Oyón-Ambo highway project represents a landmark in construction for the country, while facing significant technical challenges – Paula Chapple, editor of Carreteras Pan-Americana (CPA), writes
  • Indonesia’s traffic accidents cause near US$18.16bn annual loss
    October 31, 2013
    In Indonesia, economic losses due to traffic accidents reportedly add up to around US$18.16 billion (IDR 200 trillion) a year – 2.9% of the nation’s annual gross domestic product. Data from the police showed that a total of some 120,000 traffic accidents were reported in 2012 contributing to a death toll of nearly 30,000 people. The figures were revealed during the 12th Regional Conference of Road Engineering on 22 October 2013 in West Java.
  • Concrete runway paving in the US
    December 15, 2017
    A new Wirtgen SP 94i slipform paver has helped deliver the successful reconstruction of a runway in the US state of Missouri. With more than 30,000 take-offs and landings a year, Jefferson City Memorial Airport (JEF) is one of the most heavily frequented airports in Missouri. Thousands of visitors travel through it every day on their way to the government and congress offices in the state capital on the Missouri River. At the end of April 2016, work commenced on the reconstruction of a runway approximately