Indonesia toll road completed on schedule

The construction of the Cipali Toll Road in Indonesia has been completed on time, despite numerous challenges during its construction. The Cipali Toll Road forms part of a larger network, the Trans-Java Toll Road that connects key freeways in Jakarta and beyond. The Trans-Java Toll Road is of enormous importance to Indonesia as it runs for 653km and reduces the existing route by 40km.
May 16, 2016 Read time: 3 mins
With its output of 150tonnes/hour, the plant had extra capacity as it was producing 120tonnes/hour for most of the time during the project
A new toll road in Indonesia will help transportation and boost the local economy

The construction of the Cipali Toll Road in Indonesia has been completed on time, despite numerous challenges during its construction. The Cipali Toll Road forms part of a larger network: the Trans-Java Toll Road that connects key freeways in Jakarta and beyond. The Trans-Java Toll Road is of enormous importance to Indonesia as it runs for 653km and reduces the existing route by 40km.

The Cipali Toll Road, stretching from Cikopo in the west to Palimanan in the east, is a crucial segment in the network and is carrying around 30,000 vehicles/day. As a result, the construction of this important stretch of road was followed closely by government officials and businesses.

But despite the numerous challenges, the project was finished on time and within budget. A key player in meeting both goals was asphalt producer PT. Dirgantara Yudha Artha, based in Bandung. The firm installed an 6791 Ammann JustBlack 150 plant to help finish the project, which was used to supply asphalt for key portions of the work.

Development work for the 110km Cipali Toll Road required around-the-clock asphalt production, with the plant output sometimes reaching close to 3,000tonnes/day. Meeting deadlines was no small task and the asphalt production set the pace for the rest of the team.

Experience was crucial and offered two major benefits to the production of the asphalt. This ensured the plant team was familiar with the required mixes, with only three grades being used: ACBC, ACWC and ATB. The second benefit was the team’s experience in making quick, frequent mix adjustments simplified the work for the minimal switches on the toll road project. Production was able to continue when a new mix was needed.
Capacity was also important as Dirgantara Yudha Artha used an Ammann JustBlack asphalt batch plant with a capacity of 150tonnes/hour. For most of the time the plant produced about 120tonnes/hour, but the extra capacity allowed additional production when required.

Capacity also involves reliability and one reason Dirgantara Yudha Artha purchased this plant was for its dependability. The Ammann JustBlack plant produced 120tonnes/hour for 20-hour shifts, providing an average of 2,400tonnes/day.

The company’s use of the JustBlack plant also brought savings on fuel of around 20%, according to Dirgantara Yudha Artha. When the project was complete, Dirgantara Yudha Artha had produced enough mix to cover 55km of the 110km of multilane highway. Production had gone well and set the pace for the entire project.

Privately owned by Jahja Tear Tjahjana, Dirgantara Yudha Artha has  five asphalt plants and works on general construction, roads, tolls roads and airport runways.

For more information on companies in this article

Related Content

  • Building Egypt's world class Desert Highway
    April 13, 2012
    A huge highway upgrade project will transform the Cairo-Alexandria road link into a world-class connection as Mike Woof reports. The work to upgrade the Desert Highway connecting Egypt's sprawling capital Cairo with its major port Alexandria, is one of the country's largest infrastructure projects for many years. This 220km highway link is being widened and improved to cope with the hugely increased traffic volumes resulting partly from Egypt's fast growing vehicle population. The Egyptian economy is strong
  • Indonesia’s toll roads under development
    July 18, 2019
    Indonesia is working on plans to develop its toll road network during 2019. A further 400km of new toll roads will be completed during 2019, bringing Indonesia’s total toll road length to 2,000km in all. Key toll road sections due for completion include stretches of the Jakarta Outer Ring Round 2 and the Balikpapan-Samaridan toll road. Indonesia’s Trans-Sumatra toll road is one of the country’s key projects, with some 561km of the route due to be in use by the end of 2019. The Balikpapan-Samarinda toll road
  • Higher productivity, lower cost asphalt plants
    February 14, 2012
    Manufacturers are producing innovative asphalt equipment, and operators are benefiting from this as Patrick Smithreports. Asphalt plant manufacturers and operators are understandably placing great emphasis on higher productivity but with lower costs. At the same time they are aware of environmental issues and the ever-increasing use of recycled material in mixes.
  • Astec’s Azerbaijan asphalt application
    June 9, 2015
    In Azerbaijan an Astec batching plant is said to be giving a major contractor an advantage over its competition The firm, Aztikintiyol, is one of the leading producers of aggregates and hot-mix asphalt in Azerbaijan and decided to expand its operations into the southern regions of the country. The need for asphalt in this area was growing as there is massive infrastructure development close to the border with neighbouring Iran taking place. However a simple plant was not suitable as the firm required