Indonesia toll road completed on schedule

The construction of the Cipali Toll Road in Indonesia has been completed on time, despite numerous challenges during its construction. The Cipali Toll Road forms part of a larger network, the Trans-Java Toll Road that connects key freeways in Jakarta and beyond. The Trans-Java Toll Road is of enormous importance to Indonesia as it runs for 653km and reduces the existing route by 40km.
May 16, 2016 Read time: 3 mins
With its output of 150tonnes/hour, the plant had extra capacity as it was producing 120tonnes/hour for most of the time during the project
A new toll road in Indonesia will help transportation and boost the local economy

The construction of the Cipali Toll Road in Indonesia has been completed on time, despite numerous challenges during its construction. The Cipali Toll Road forms part of a larger network: the Trans-Java Toll Road that connects key freeways in Jakarta and beyond. The Trans-Java Toll Road is of enormous importance to Indonesia as it runs for 653km and reduces the existing route by 40km.

The Cipali Toll Road, stretching from Cikopo in the west to Palimanan in the east, is a crucial segment in the network and is carrying around 30,000 vehicles/day. As a result, the construction of this important stretch of road was followed closely by government officials and businesses.

But despite the numerous challenges, the project was finished on time and within budget. A key player in meeting both goals was asphalt producer PT. Dirgantara Yudha Artha, based in Bandung. The firm installed an 6791 Ammann JustBlack 150 plant to help finish the project, which was used to supply asphalt for key portions of the work.

Development work for the 110km Cipali Toll Road required around-the-clock asphalt production, with the plant output sometimes reaching close to 3,000tonnes/day. Meeting deadlines was no small task and the asphalt production set the pace for the rest of the team.

Experience was crucial and offered two major benefits to the production of the asphalt. This ensured the plant team was familiar with the required mixes, with only three grades being used: ACBC, ACWC and ATB. The second benefit was the team’s experience in making quick, frequent mix adjustments simplified the work for the minimal switches on the toll road project. Production was able to continue when a new mix was needed.
Capacity was also important as Dirgantara Yudha Artha used an Ammann JustBlack asphalt batch plant with a capacity of 150tonnes/hour. For most of the time the plant produced about 120tonnes/hour, but the extra capacity allowed additional production when required.

Capacity also involves reliability and one reason Dirgantara Yudha Artha purchased this plant was for its dependability. The Ammann JustBlack plant produced 120tonnes/hour for 20-hour shifts, providing an average of 2,400tonnes/day.

The company’s use of the JustBlack plant also brought savings on fuel of around 20%, according to Dirgantara Yudha Artha. When the project was complete, Dirgantara Yudha Artha had produced enough mix to cover 55km of the 110km of multilane highway. Production had gone well and set the pace for the entire project.

Privately owned by Jahja Tear Tjahjana, Dirgantara Yudha Artha has  five asphalt plants and works on general construction, roads, tolls roads and airport runways.

For more information on companies in this article

Related Content

  • Concrete mixing technology offers advanced recipes
    February 13, 2012
    Modern concrete production plants are using technology to offer more sophisticated mix recipes as Patrick Smith reports. The growing trend towards ever more sophisticated concrete recipes calls for fully developed mixing technology. Companies are responding to the challenges with equipment that offers new levels of sophistication including computer controls and units that can deliver a huge variety of mix recipes.
  • Increased asphalt demand - meeting the challenge
    February 8, 2012
    With demand for asphalt predicted to increase, manufacturers are ready to meet the challenge as Patrick Smith reports
  • Recycled asphalt cuts costs, maximises performance
    February 10, 2012
    The need to maximise road performance and cut costs has resulted in Indonesian contractors being keen to adopt cold recycling methods
  • Efficient earthmoving builds new road links
    February 7, 2012
    Efficient earthmoving is allowing productive road construction in the Egyptian desert, Mike Woof reports. Despite ferocious desert temperatures, efficient earthmoving operations will help build new road links in Southern Egypt. Close to the Egyptian city of Assuit, the contractor Orascom is working on three key desert highway projects that will provide vital transport connections for the country's growing economy.