First deck span completed for Mersey Gateway's north approach viaduct

The Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed. Work started on site in May 2014 to build a six-lane toll bridge over the Mersey River between the towns of Runcorn and Widnes and opening is set for the autumn of 2017. As well as construction of the new bridge, works include the upgrading of 7km of highway to the north and south of the river - the main bridge is 2.2km long – and changing traffic flow so the majority of tra
April 4, 2016 Read time: 4 mins
First span of the north approach viaduct showing the north abutment. Photo: David Hunter
The Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed.

Work started on site in May 2014 to build a six-lane toll bridge over the Mersey River between the towns of Runcorn and Widnes and opening is set for the autumn of 2017. As well as construction of the new bridge, works include the upgrading of 7km of highway to the north and south of the river - the main bridge is 2.2km long – and changing traffic flow so the majority of traffic uses the new bridge.

The reinforced concrete deck span was revealed when Merseylink's movable scaffolding system (MSS) 'Trinity' moved to its second casting position. It is the first of 11 spans that will be cast by the MSS for the deck of the elevated approach viaduct on the north side of the River Mersey.

The MSS, which acts as a giant concrete mould, was specially designed for the 6126 Mersey Gateway Project. It is being used to build the two elevated approach viaducts over the Mersey estuary.

The span connects the beginning of the approach viaduct from the north abutment in Widnes to the first supporting pier. It measures around 60m long and 18m wide and is angled at 5 degrees to allow vehicles to travel safely around the curve of the approach road.
Construction teams worked around the clock to get the span ready. This involved pouring 1,146m3 of concrete into the MSS non-stop over 34 hours.

"This is a real achievement for the project and a milestone that we've been looking forward to with anticipation,” said Declan Cannar, Merseylink's general foreman in charge of the MSS operation. “We're now busy preparing the MSS so it's ready to cast the next section."

The approach viaduct deck is being constructed in three phases. The deck spans are constructed first by the MSS, then a deck slab is built on top of the span, and finally the outer deck or ‘wings' are built by a wing traveller machine to provide the full six-lane width of the approach road.

The MSS has moved to its second casting position ready for work to begin on the next span, which will be cast in March.

Meanwhile, Total Plant Hire, based in Manchester, has hired out two new Doosan DA30 30tonne articulated dump trucks (ADTs) fitted with high flotation tyres for the project.

Like all 695 Doosan ADTs, the DA30 model features an articulation hinge behind the turning ring to provide equal weight distribution to the front axle even during maximum steer articulation. This together with a free-swinging rear tandem bogie ensures equal distribution of weight to each wheel and delivers permanent six-wheel contact and drive for equal power distribution and excellent performance on difficult terrain.
The specially shaped body and sloping frame on the DA30 offers a low centre of gravity and perfect weight distribution. The Doosan machines purchase by Total Plant Hire have been equipped with high flotation tyres to further help traction in the tough working conditions.

A temporary trestle bridge has been built as an access platform for workers build the new structures in the river. Accessed from the trestle bridge, temporary cofferdams have been built to enable foundations to be laid for the three pylons that will support the main bridge. The Doosan DA30 ADTs are removing earth excavated from the cofferdams and from others across the site.

The Doosan DA30 ADTs are also being for construction of supporting piers for the elevated approach viaducts, which cross the Manchester Ship Canal and the St Helens Canal. Each approach viaduct is supported by a number of supporting, there being 20 in total. These will march across the salt marsh on either side of the estuary.

For more information on companies in this article

Related Content

  • Australian award
    November 27, 2012
    Two major awards have been given to the Gateway Upgrade Project in Queensland, Australia. One of these was for engineering excellence while the other was the overall RW Hawken Award. These were given as part of the Engineering Australia Awards (Queensland Division) scheme. Following this, the Gateway Project will now be a contender for the national Australian Engineering Excellence Awards being held in November 2012. The Gateway Upgrade is of note as it is one of the largest road and bridge projects ever ca
  • AECOM and University of Salford announce research partnership
    August 17, 2016
    Global infrastructure services firm AECOM and the UK’s University of Salford have launched a research partnership with the aim of improving understanding of how major infrastructure programmes interact with the natural environment. A statement from AECOM said that the two organisations will jointly fund environmental research on topics directly applicable to major infrastructure projects. “Research areas will be chosen to provide benefits to particular schemes and to help reduce adverse impacts and im
  • VIDEO: Sarens raises the pylon for New Wear Crossing in Sunderland
    February 13, 2017
    It was as weekend working in Sunderland city, northeast England, for global lifting specialist 8569 Sarens.

    Over the two days, the Belgian company gently raised a 1,550tonne steel pylon that will form the backbone of the New Wear Crossing – no official name yet – across the River Wear.

    General work on the two-span cable-stay bridge started on the bridge in May 2015. The structure will be supported by the single double pylon and will have four vehicle lanes, as well as dedicated cycle and pedestrian routes.
  • The UK’s A14 route is seeing a major upgrade
    June 14, 2018
    Work is progressing well on the project to upgrade the busy A14 route in the UK. A major milestone has been achieved with and important phase of the bridge installation having taken place. A 39m viaduct beam has been placed successfully for the bridge, which spans the River Ouse in Cambridgeshire. A key role in this work has been taken by the firm Cleveland Bridge UK. As part of Highways England’s £1.5 billion A14 Cambridge to Huntingdon improvement scheme, Cleveland Bridge was contracted by the A14 Integr