First deck span completed for Mersey Gateway's north approach viaduct

The Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed. Work started on site in May 2014 to build a six-lane toll bridge over the Mersey River between the towns of Runcorn and Widnes and opening is set for the autumn of 2017. As well as construction of the new bridge, works include the upgrading of 7km of highway to the north and south of the river - the main bridge is 2.2km long – and changing traffic flow so the majority of tra
April 4, 2016 Read time: 4 mins
First span of the north approach viaduct showing the north abutment. Photo: David Hunter
The Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed.

Work started on site in May 2014 to build a six-lane toll bridge over the Mersey River between the towns of Runcorn and Widnes and opening is set for the autumn of 2017. As well as construction of the new bridge, works include the upgrading of 7km of highway to the north and south of the river - the main bridge is 2.2km long – and changing traffic flow so the majority of traffic uses the new bridge.

The reinforced concrete deck span was revealed when Merseylink's movable scaffolding system (MSS) 'Trinity' moved to its second casting position. It is the first of 11 spans that will be cast by the MSS for the deck of the elevated approach viaduct on the north side of the River Mersey.

The MSS, which acts as a giant concrete mould, was specially designed for the 6126 Mersey Gateway Project. It is being used to build the two elevated approach viaducts over the Mersey estuary.

The span connects the beginning of the approach viaduct from the north abutment in Widnes to the first supporting pier. It measures around 60m long and 18m wide and is angled at 5 degrees to allow vehicles to travel safely around the curve of the approach road.
Construction teams worked around the clock to get the span ready. This involved pouring 1,146m3 of concrete into the MSS non-stop over 34 hours.

"This is a real achievement for the project and a milestone that we've been looking forward to with anticipation,” said Declan Cannar, Merseylink's general foreman in charge of the MSS operation. “We're now busy preparing the MSS so it's ready to cast the next section."

The approach viaduct deck is being constructed in three phases. The deck spans are constructed first by the MSS, then a deck slab is built on top of the span, and finally the outer deck or ‘wings' are built by a wing traveller machine to provide the full six-lane width of the approach road.

The MSS has moved to its second casting position ready for work to begin on the next span, which will be cast in March.

Meanwhile, Total Plant Hire, based in Manchester, has hired out two new Doosan DA30 30tonne articulated dump trucks (ADTs) fitted with high flotation tyres for the project.

Like all 695 Doosan ADTs, the DA30 model features an articulation hinge behind the turning ring to provide equal weight distribution to the front axle even during maximum steer articulation. This together with a free-swinging rear tandem bogie ensures equal distribution of weight to each wheel and delivers permanent six-wheel contact and drive for equal power distribution and excellent performance on difficult terrain.
The specially shaped body and sloping frame on the DA30 offers a low centre of gravity and perfect weight distribution. The Doosan machines purchase by Total Plant Hire have been equipped with high flotation tyres to further help traction in the tough working conditions.

A temporary trestle bridge has been built as an access platform for workers build the new structures in the river. Accessed from the trestle bridge, temporary cofferdams have been built to enable foundations to be laid for the three pylons that will support the main bridge. The Doosan DA30 ADTs are removing earth excavated from the cofferdams and from others across the site.

The Doosan DA30 ADTs are also being for construction of supporting piers for the elevated approach viaducts, which cross the Manchester Ship Canal and the St Helens Canal. Each approach viaduct is supported by a number of supporting, there being 20 in total. These will march across the salt marsh on either side of the estuary.

For more information on companies in this article

Related Content

  • Managing urban motorway complexity in Sydney
    October 4, 2012
    Sydney’s Hills M2 motorway is being widened while still carrying traffic and meeting tough environmental criteria More than 100,000 vehicles and over 27,000 bus commuters use the Hills M2 motorway on a typical workday, making it one of Sydney’s busiest motorway corridors. Owned and managed by Hills Motorway Ltd (HML) and a key part of the city’s orbital motorway network, the road stretches over 21km, providing a seamless link between the Lane Cove Tunnel and Westlink M7. The Hills M2 Upgrade is one of many
  • Poland's A1 motorway progressing well
    February 9, 2012
    The second major phase of a north-south motorway in Poland is well underway. It will reduce congestion and improve safety as Patrick Smith reports Before the whistle blows to herald the start of Euro 2012, Poland's main seaport Gdansk will boast new roads, a new airport and a new stadium. The historic city in the north of the country on the Baltic coast will be one of the venues for football's 14th European Championship, being co-hosted by Poland and Ukraine.
  • Cofferdams completed for Sunderland city’s New Wear River Crossing
    May 25, 2016
    In the UK, foundation work for Sunderland city’s new bridge is about to start as the huge cofferdam in the middle of the River Wear nears completion. Water has been drained out of the cofferdam, a large steel watertight structure within the river, to allow the building of pylons for the bridge deck. It is the first bridge to be built over the Wear in Sunderland for more than 40 years and is part of the wider strategic transport plan to link the Port of Sunderland and city centre with the A19 road.
  • Zhejiang Jiashao Bridge Investment & Development Co
    April 6, 2017
    Located in Zhejiang Province of China, Jiashao Bridge spans the Qiantang River and connects the cities of Jiaxing and Shaoxing. The total length of the bridge project is 10.14km and carries an eight-lane expressway The Qiantang River suffers from a high flow rate of up to 7.5m/s. As the tidal range is around 7-9m, the water depth is less than 2m in time of low level tide, so ships can only move at high tide and large scale ship-lifting equipment cannot be used downstream of Jiashao Bridge. However, to